Messrs Baker & Mckenzie v. Hennex Industries Limited and Others

Read the full judgment text of DCMP 809/2014 on BabelCite. This District Court judgment was delivered on 20 August 2014.

1. The applicant seeks interpleader relief pursuant to Order 17 rule (1) of the Rules of the District Court.  The subject involved is the stakeholder money of $233,300, in relation to a sale and purchase of the Properties.

Cites 2 cases

Case No.DCMP 809/2014
Court
District Court
Date20 Aug 2014
Judge
Case Document
100%Judiciary

DCMP 809/2014

IN THE DISTRICT COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

MISCELLANEOUS PROCEEDINGS NO 809 OF 2014

--------------------------------

 

IN THE MATTER OF an application by Messrs Baker & McKenzie for interpleader relief against the claims of Kingdom Power Development Limited, Sheen Wealth Industrial Limited (Purchaser) and Hennex Industries Limited (1st Vendor) and Make Sales Enterprise Limited (2nd Vendor) for the stakeholder money in the sum of HK$233,300 pursuant to the Provisional Agreement For Sale and Purchase dated 22 October 2010 in relation to the sale and purchase of Shops Nos 1, 2, 3, 4, 5, 6, 7, 8, 9, and 10 all on the Ground Floor and the Entire first Floor and Offices Nos 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15 and 16 all on the Second Floor and the External Walls of the First Floor and the Second Floor of Tonnochy Towers, Nos 250-274 Jaffe Road, No 5 Tonnochy Road and No 4 Stewart Road, Hong Kong (‘the Properties”)

BETWEEN

  Messrs Baker & Mckenzie Applicant

and

  Hennex Industries Limited 1st Claimant
  Make Sales Enterprise Limited 2nd Claimant
  Sheen Wealth Industrial Limited 3rd Claimant
  Kingdom Power Development Limited 4th Claimant
----------------------------------
Before:  Deputy District Judge J Chow in Chambers (open to public)
Date of Hearing:  5 May 2014, 2 July 2014 and 18 August 2014
Date of Judgment:  20 August 2014

-------------------------------

JUDGMENT

-------------------------------

The Application

1.The applicant seeks interpleader relief pursuant to Order 17 rule (1) of the Rules of the District Court.  The subject involved is the stakeholder money of $233,300, in relation to a sale and purchase of the Properties.

The Background

2.The 1st and 2nd claimants are vendors.  The 4th claimant is the purchaser and the 3rd claimant is the nominee.  The applicant is the solicitors for the 3rd claimant. On 22 October 2010, the 1st and 2nd claimants and the 4th claimants entered into a provisional sale and purchase agreement for purchase of the Properties in sum of $435,000,000 (“the PS&P Agreement”).

3.The Properties were subject to two superseding orders issued by the Buildings Authority (“the Superseding Orders”). The 1st order and the 2nd order concerned the units on the 1st floor and offices on the 2nd floor respectively.

4.It was stated the 1st order, memorial number 0704110190315  (undated in exhibit “RL-1”)  ,

“It has been brought to my attention that the following building works have been carried out in or at the above premises: (i) Structure attached to the external wall at the front’ (ii) Metal rack attached to the external wall at the rear.

2. For the said building works, (a) the building works at item (i) and (ii) above has been carried out without having first obtained from the approval of building plans and consent for the commencement of such building works required by section 14 of the Buildings Ordnance.

3. In exercising the powers vested in me under section 24(1) of the Buildings Ordinance, I hereby order you to: - (a) demolish the said building works described under item (i) and (ii) above; and (b) to reinstate the parts of the building so affected by building works under item (i) and (ii) above in accordance with the plans approved by the Building Authority.

5.It was stated in the 2nd order, memorial number 0704110190322 dated 16th March 2007,

“It has been brought to my attention that the following building works have been carried out in or at the above premises: (i) Structure attached to the external wall at the front’ (ii) Air-conditioner duct and cooling tower supported frame attached to the external wall at the rear.

2. For the said building works, (a) the building works at item (i) and (ii) above has been carried out without having first obtained from the approval of building plans and consent for the commencement of such building works required by section 14 of the Buildings Ordnance.

3. In exercising the powers vested in me under section 24(1) of the Buildings Ordinance, I hereby order you to: - (a) demolish the said building works described under item (i) and (ii) above; and (b) to reinstate the parts of the building so affected by building works under item (i) and (ii) above in accordance with the plans approved by the Building Authority.”

6.In the PS&P Agreement, the 1st and 2nd claimants warranted to make good the Superseding Orders by carrying out necessary works, or to reimburse the 3rd and 4th claimants at a reasonable costs to comply with the same. It was particularly stated in Clause 1 of the Rider,

“The Vendor hereby warrants that they have completed the necessary works to comply with the Superseding Orders Memorial Nos. 07041101190315 and 07041101190322. Two respective Letters of Compliance discharging the said Orders have to be issued and duly registered in the Land Registry before completion of the sale and purchase of the Property. If the two Letters of Compliance shall not have been issued and registered in the Land Registry before the completion date, then the Vendor shall reimburse the Purchaser a reasonable cost of completing the necessary works to comply with the said two Superseding Orders and registering the two Letters of Compliance and a sum of $300,000.00 shall be deducted from the balance of the purchase price on completion and be held by the Purchaser’s Solicitors towards payment of such cost. Any excess shall be returned to the Vendor of if there is any deficiency, the Vendor shall reimburse the balance of the said sum. This clause survive completion. (emphasis added)”

7.The 1st and 2nd claimants did not make good the Superseding Orders at time of completion. On 26th January 2011, a sum of $300,500 was deducted from the balance of the purchase price and was deposited with the applicant, out of which $300,000 was stakeholder money and the additional $500 was meant to settle the fees for obtaining certified copies from the Land Registry.  Parties agreed this $500 does not form part of the stakeholder money.

8.On 3rd March 2011, prior to the commencement of such works, Mr. Lo Tsui Shan Rico of the 3rd claimant, arranged a site inspection with Mr. Yue Kin Wing of the Buildings Department. It was the 3rd claimant’s understanding apart from those particularly stated in the Superseding Orders, the asbestos structure and the signage attached on the external wall also formed part of the unauthorized structures, which have to be demolished.

9.The 3rd claimant requested for a number of quotations from various building contractors: (i) 順銘建築有限公司; (ii) Kenji Engineering Co. Ltd (“Kenji”) and (iii) 展輝建築公司. The 3rd claimant appointed Kenji because it has quoted the lowest price in its quotation dated 13 April 2011 (“the Quotation”). The costs of works were agreed at $260,000.

10.After completion of the works, the Buildings Department issued two Letters of Compliance both dated 22nd June 2011 with Memorial Nos. 11071501290013 and 11071501290029.

The Dispute

11.The 3rd claimant claimed $262,000 and an extra $4,089.09 as administrative costs as costs for completing the necessary works.  

12.The 1st and 2nd claimants disputed the sum of the works on the ground that the removal of the asbestos structure and the signage attached on the external wall did not form part of the unauthorized structures in the Superseding Orders (“the Disputed Works”).  The 1st and 2nd claimant refused to settle the costs of such works. To have a better understanding of the 1st and 2nd claimants’ stance, the particulars of the  Quotation are as follows:

(i) Item 1 – scaffolding : $ 35,000
(ii) Items 2 – 4: works in compliance  
  of the Superseding Orders : $ 55,000
(iii)  Items 5 – 6: Disputed Works: $160,000
(iv) Item 7 – insurance: $ 10,000
(v)  TOTAL : $260,000
    ======

13.The 1st and 2nd claimant submitted, as they are only liable for $55,000 (items 2 – 4 only) as opposed to the aggregate sum of $215,000 (items 2 – 6); they should bear the same proportion of the works in items 1 and 7[1]. The aggregate sum payable should be $66,700. Notwithstanding ongoing dispute, the sum of $66,700 was released to the 4th claimant on or about 9 September 2013.

14.Negotiation between parties to dispose of the remaining stakeholder money was unfruitful.  The applicant seeks interpleader relief in an originating summons filed on 28 March 2014.

15.The originating summons was returnable on 5th May 2014 for directions. I am given to understand the 3rd claimant agreed to waive the administrative costs $4,089.09. Parties further agreed (i) the 1st and 2nd claimants agreed to pay a further sum of $40,000 to the 3rd and 4th claimants; and (ii) the disputed sum was only $193,800[2]

16.The applicant was directed to pay the agreed disputed sum into court. The applicant’s attendance was excused in further hearings.

The Issues

17.As agreed between the parties, the issues of this application are (i) whether items 1, 5, 6 and 7 of the Quotation were reasonably necessary to comply with the Superseding Orders; and (ii) whether apportionment of items 1 and 7 is justified.

The 1st and 2nd claimants’ submissions

18.Mr Lam, counsel for the 1st and 2nd claimants submitted, they are liable for costs of works referred to demolish and reinstate the parts of building so affected of (i) structure attached to the external wall at the front on the 1st and 2nd floor of the Properties; (ii) metal rack attached to the external wall of the rear and (iii) air-conditioner duct and cooling tower supported frame attached to the external wall at the rear part of the building in accordance with the plan attached to the Superseding Orders[3] (items 2 – 4).  The asbestos ceilings and signage facing Stewart Road and Tonnochy Road are not within the ambit of the Superseding Orders (items 5 – 6). An apportioned amount of items 1 and 7 is appropriate.

The 3rd and 4th claimants’ submissions

19.Mr Ko, counsel for the 3rd and 4th claimants submitted, there is nothing in the evidence that items 5 and 6 fall outside the ambit of the Superseding Orders. He further suggested the court shall not rely on the alleged representations of Mr Yue on 3March 2011. Mr Ko further cited authorities on interpretation on contracts[4].

Analysis

20.The true construction of the works required for compliance of the Superseding Orders rests with the works expressly defined in the Superseding Orders themselves. I agree with Mr Lam that items 2 – 4 are within the ambit of the Superseding Orders. Clear reference of the location of the area concerned has been made in the plans attached. To the contrary, the Disputed Works (items 5 and 6), structures facing Stewart Road and Tonnochy Road,  were not mentioned.

21.The arguments raised by Mr Ko are misconceived. Firstly, The New China Hong Kong Group Ltd (in liquidation) case is distinguishable, it is unnecessary for me to analyze in detail because  that case concerns interpretation of contracts between contracting parties, which is not our case here. The 1st and 2nd claimants are not the contracting parties of the Quotation.

22.Secondly, the conduct of the 3rd and 4th claimants are relevant. The 3rd and 4th claimants said Mr Yue Kin Wing of the Buildings Department orally represented to them that the Disputed Works were required to be demolished at time of the site inspection on 3rd March 2011. The 1st and 2nd claimants were not present at time of the site inspection and the Disputed Works were unknown to them. The 1st and 2nd claimants then clarified with the Buildings Department of the alleged oral representation. In a letter dated 26th September 2013 issued by the Buildings Department, it expressly stated, amongst other things,

“In this respect, please note that his department has no record showing that our staff had so informed / told Sheen [the 3rd claimant] or their representative as alleged by Sheen [the 3rd claimant]. Nevertheless, please note that it is the responsibility of the owners to maintain their premises in a safe and sound condition and free from UBW and it is always this department’s advice to owners to remove any UBW at their premises voluntarily. (emphasis added)”

23.This provides a clear indication that the Disputed Works are  not a prerequisite for compliance of the Superseding Orders. The Buildings Department did not specifically ask the 3rd and 4th claimants to carry them out. I must say, the 3rd and 4th claimants are out of caution to arrange a site inspection with Mr Yue, unfortunately, the oral representation has not been reduced in writing, and no consent was obtained from the 1st and 2nd claimant. In this regard, the 3rd and 4th claimants are not entitled to rely on Mr Yue’s oral representation to justify the Disputed Works form part of the necessary works in compliance of the Superseding Orders.

24.Having said that, I do not agree the 1st and 2nd claimants are only responsible for an apportioned amount of items 1 and 7, namely costs of scaffolding and insurance premium. I fail to see there are evidence by either party that such costs would be different had items 5 and 6 not formed part of the works. It is expected costs of erecting the scaffoldings and insurance premium have to be paid in any event, and needless to say, they are necessary.  The 1st and 2nd claimants should be responsible for the entire amount of items 1 and 7.

25.To conclude, the reasonable costs of completing the necessary works in discharging the Superseding Orders as follows:

(i) Item 1, costs of erecting scaffoldings $ 35,000
(ii) Item 2 – 4, costs with reference to the $ 55,000
  two Superseding Orders  
(iii) Item 7, costs of insurance premium $ 10,000
    $100,000
    ======

Costs

26.On 5 May 2014, I made an order that the applicant’s costs shall be in the cause of the interpleader proceedings and I have assessed costs of the applicant in sum of $33,884[5]. The same amount has been released to the applicant pursuant to an order of payment out on 15July 2014.

27.Costs should follow the event, the 3rd and 4th claimants shall pay the costs of the 1st and 2nd claimants.

28.Counsels for both parties agreed to assess costs of this interpleader proceedings summarily. The 1st and 2nd claimants submitted their statement on costs. I further heard submissions accordingly.

29.The 1st and 2nd claimants’ costs be allowed as per their statement on costs save and except the following:

(i) 2 hours be taxed off from Item C1;
(ii) 1 hour be taxed off from Item C3;
(iii) 1 hour be taxed off from Item D1;
(iv) 4.5 hours be taxed off from Item D2;
(v) Item D3 be taxed off;
(vi) 1 hour be taxed off from Item D4.

30.The costs of the 1st and 2nd claimants be assessed at $69,670.

Orders

31.Pursuant to Clause 1 of the Rider in the PS&P Agreement,  the 1st and 2nd claimants are obliged to pay items 1 – 4; and 7 of the Quotation, i.e. ($35,000 + $15,000 + $35,000 + $5,000 + $10,000) $100,000.

32.Taking into account the 1st and 2nd claimants have already released $106,700 (ie $66,700 + $40,000) from the original stakeholder money to the 3rd and 4th claimant, I make the following the orders:

(i) The remaining of the disputed sum of $159,916[6] be released to the 1st and 2nd claimants forthwith.

(ii) The 3rd and 4th claimants do jointly and severally reimburse $6,700 to the 1st and 2nd claimants forthwith.

(iii) Costs of the interpleader proceedings be paid by 3rd and 4th claimants jointly and severally to the 1st and 2nd claimants, be summarily assessed at $69,670.

(iv) Costs of the applicant be paid by the 3rd and 4th claimants jointly and severally, to the 1st and 2nd claimants in sum of $33,884.

  ( J Chow )
  Deputy District Judge

Mr Gary Lam Chin Ching instructed by Chong, Fu & Co for the 1st and 2nd claimants

Mr Tony Ko instructed by Tony Kan & Co for the 3rd and 4th claimants


[1] $55,000 / $215,000 = 0.26

($35,000 + $10,000) x 0.26 = $11,700

Total sum suggested by the 1st and 2nd claimant: $55,000 + $17,000 = $66,700

[2] $300,500 - $66,700 - $40,000 = $193,800

[3] The structures attached to the front referred to those facing Jaffe Road; the metal rack was meant to be those facing Stewart Road.

[4] The New China Hong Kong Group Ltd (in liquidation) v. AIG Asian Infrastructure Fund  LP, CACV 24/2008, 12 Feb 2009.

[5] See written decision dated 17 June 2014.

[6] ($193,800 - $33,884)