Li Chuen Kwai v. Po Lam Construction Development Ltd
Read the full judgment text of HCA 2376/2013 on BabelCite. This High Court CFI judgment was delivered on 24 September 2014.
1. This is the defendant’s appeal against the decision of the Master dated 16 June 2014, ordering that summary judgment be granted in favour of the plaintiff against the defendant for the sum of HK$1,350,986.84, together with interest thereon and costs of this action.
Cited by 51 cases · Cites 2 cases
|
HCA 2376/2013 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 2376 OF 2013 ________________
________________________ D E C I S I O N ________________________ Introduction 1.This is the defendant’s appeal against the decision of the Master dated 16 June 2014, ordering that summary judgment be granted in favour of the plaintiff against the defendant for the sum of HK$1,350,986.84, together with interest thereon and costs of this action. Factual background 2.The defendant is a company incorporated in Hong Kong, carrying on the business of constructing “ting” houses for “ting” right owners. 3.Sometime in 2008, after some discussions, the plaintiff and one Lo Shu‑sang on behalf of the defendant orally reached agreement for the plaintiff to supply building materials to the defendant for the construction of “ting” houses by the defendant at the defendant’s various construction sites, and for a showroom to be set up at the construction sites of the defendant (“the Oral Agreement”). 4.The plaintiff is suing on the Oral Agreement in the present action. Whilst the defendant accepts that an oral agreement was reached with the plaintiff, there is factual dispute as to what terms were orally agreed on that particular occasion:
5.Since the Oral Agreement:
6.As a matter of practice, all payments from the defendant to the plaintiff were:
7.In late 2009, there is no dispute that the defendant did orally propose to the plaintiff that the price of the building material for each house be fixed at $45,000. However, whether the plaintiff agreed to the $45,000 arrangement is in dispute. 8.It is also the defendant’s case that in early 2012, the fixed price of $45,000 was increased to $55,000 by mutual agreement of the plaintiff and the defendant. The plaintiff completely denies this. 9.On 14 May 2013, the plaintiff went to the defendant’s office with two alleged “Receivable Summaries” and a set of Materials Lists. However, what happened in the defendant’s office resulting in the defendant’s chop and the Chinese characters “未確認對賬單” appearing on the two Receivable Summaries is in dispute. 10.The defendant stopped making payments to the plaintiff since September 2013. Relevant legal principles 11.As far as the plaintiff’s claim is concerned:
12.As far as the defendant’s defence is concerned:
13.Where there are unexplained features in both the claim and the defence, no tentative assessment of strengths should be made, but unconditional leave to defend should be given [see: Hong Kong Civil Procedure 2014 at Practice Note 14/4/9]. 14.Further, where (as here) an oral contract is sued on and its terms are in dispute, summary judgment must be refused unless the plaintiff can satisfy the court either that on the defendant’s version he is entitled to judgment, or that the defendant’s version is not truthful or capable of belief [see: Hong Kong Civil Procedure 2014 at Practice Note 14/4/11]. Plaintiff’s claim is problematic 15.In the present case, there is clear variance between the plaintiff’s claim as pleaded in the Statement of Claim and the plaintiff’s claim as asserted in the plaintiff’s affirmation in support of his Order 14 application. 16.The alleged agreed term on price pleaded in the Statement of Claim is simply different from that of the verifying affidavit. In the Statement of Claim, the plaintiff’s pleaded terms on price under the Oral Agreement is that the defendant agreed to buy from the plaintiff the materials for the properties according to each and every Materials List. 17.Yet, a substantially different term on price came to be asserted in the plaintiff’s affirmation. Indeed, there is just no mention (in the affirmation) of the “Materials List” being involved in determining the price payable by the defendant. 18.Further, other “material terms” as verified on affidavit are different from the “material terms” as pleaded in the Statement of Claim. By comparing the two versions, the following can be noted:
19.I agree with the defendant that the discrepancies identified above are fatal to the plaintiff’s application for summary judgment and sufficient to dispose of the application, in that:
The defendant has raised triable issues 20.In considering the defence raised by the defendant, it is important to bear in mind that this is not the typical scenario where a defendant tries to raise some collateral oral agreement as defence to a written agreement sued on by a plaintiff. Here, the plaintiff is himself suing on an oral agreement, the alleged terms of which are not supported by any contemporaneous record; and the defendant’s defence is to dispute what had been orally agreed. 21.Insofar as reliance is placed by the plaintiff on the subsequent conduct of the parties, it must be noted that the manner in which the plaintiff and the defendant conducted themselves subsequent to the Oral Agreement also contradicts the plaintiff’s version of the Oral Agreement (whether on pleadings or on affidavit). 22.Whilst the plaintiff says that it was orally agreed for the defendant to make payments for “each and every ‘ting’ house”, there is no dispute that, of the 38 payments made by the defendant listed in Schedule B, not a single payment was made according to the “price” for each house (as listed in Schedule A). 23.Similarly, the objective fact was that for most of the orders for building materials placed with the plaintiff, no deposit was made, nor was the full balance paid upon delivery, thus contradicting the plaintiff’s version of the Oral Agreement. 24.Indeed, on the plaintiff’s version of the Oral Agreement, there would have been multiple breaches of the Oral Agreement by the defendant right from the start in 2008, in that:
25.Given the above, there are clearly triable issues on the evidence as to what had been agreed between the plaintiff and the defendant orally. The plaintiff has sought to demonstrate that the defendant’s defence is incredible when tested against the conduct of the parties subsequent to the Oral Agreement. However, given that there are unexplained features also in relation to the plaintiff’s claim, no tentative assessment of strengths should be made of the claim and the defence, and the defendant should be given his day in court. There are clearly disputes on fact relating to the Oral Agreement, which factual disputes should be tried. Interim payment 26.The plaintiff has included an alternative application for interim payment by his summons. 27.For the same reasons stated above in relation to the Order 14 application, on the evidence before the court, the plaintiff clearly cannot satisfy the court that it will obtain judgment for a substantial sum, nor is there any reason why the court should exercise its discretion to order an interim payment. Conclusion 28.For all the above reasons, I would allow the defendant’s appeal against the order of the Master granting summary judgment. The judgment is set aside. (Submissions on the precise form of the order and costs) 29.I make an order in terms of paragraph 1 of the Notice of Appeal. 30.As to the question of costs, I think the defendant should have its costs both here and below in any event, but the plaintiff’s conduct is not such that he should pay the costs forthwith. Accordingly, I order that the costs of this appeal and of the plaintiff’s application for summary judgment, including the hearing before the Master on 16 June 2014 (with a certificate for counsel), be to the defendant in any event, such costs to be taxed, if not agreed.
Ms Van Ma, instructed by CO Chan & Co, for the plaintiff Mr Jeremy Kwong, instructed by Kevin Li & Co, for the defendant | ||||||||||||||||||||||
Cases cited in this judgment