Volly Best Investment Ltd v. Joinland Holdings Ltd
Read the full judgment text of HCA 1438/2013 on BabelCite. This High Court CFI judgment was delivered on 25 April 2018.
1. At the hearing on 25 April 2018, there were before me two applications:
Cited by 3 cases · Cites 10 cases
|
HCA 1438/2013 [2018] HKCFI 977 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO 1438 OF 2013 _________
_________ Before: Madam Recorder Yvonne Cheng SC in Chambers Date of Hearing: 25 April 2018 Date of Decision: 25 April 2018 Date of Reasons for Decision: 7 May 2018 ___________________________ REASONS FOR DECISION ___________________________ THE APPLICATIONS 1.At the hearing on 25 April 2018, there were before me two applications:
2.I dismissed both summonses at the hearing. I now set out my reasons for doing so. THE BACKGROUND 3.The following are undisputed facts, taken from the parties’ statement of agreed facts of 11 April 2018, or otherwise not disputed. The Plaintiff is the owner of a development known as “Celestial Heights” at 80 Sheung Shing Street, Ho Man Tin, Kowloon. 4.On 4 June 2008, the Defendant entered into formal sale and purchase agreements for the purchase of nine units (“the Units”) in the development (“the Agreements”). Clause 3(1) and Schedule 4 of each of the Agreements provided for payment of the purchase price to the Plaintiff’s solicitors in the following manner:
5.The Defendant paid the 1st part payments due under the Agreements. 6.The Defendant did not pay the 2nd part payments due under the Agreements. 7.By letters dated 16 June 2009, the Plaintiff’s solicitors gave notice to the Defendant that the Plaintiff was in a position to validly assign eight of the nine Units to the Defendant and required it to complete the purchase on or before 2 July 2009. 8.By a letter dated 19 June 2009, the Plaintiff’s solicitors gave notice to the Defendant that the Plaintiff was in a position to validly assign the last of the Units to the Defendant and required it to complete the purchase on or before 6 July 2009. 9.By letters dated 15 July 2009, the Plaintiff’s solicitors referred to the Defendant’s failure to pay the 2nd part payments and to complete the purchase of the Units on the completion dates, and notified the Defendant that unless the purchase was completed within 21 days, the Plaintiff might enforce its rights to determine the Agreements. The letters were issued pursuant to clause 16(1) of each of the Agreements. The last paragraph of each of the letters stated that “All our client’s rights under the Agreement, at common law, in equity or otherwise are expressly reserved.” 10.The Defendant did not pay the outstanding 2nd part payments or complete the purchase within the time stipulated whereupon the Plaintiff exercised its right under clause 16(1) of each of the Agreements to determinethe Agreements and to forfeit the deposit paid. This was done pursuant to the Plaintiff’s solicitor’s letters of 25 August 2009 (“the Determination Notices”). The last paragraph of each of the letters stated that “All the Vendor’s rights and remedies whether under the Agreement, at common law, in equity or otherwise are hereby expressly reserved, and nothing herein shall prejudice or affect any rights or remedies of the Vendor against you arising from your breach of the Agreement.” 11.Between 1 and 12 March 2010, the Plaintiff resold the Units to third parties. Procedural background 12.On 5 August 2013, the Plaintiff commenced the present action. Its Statement of Claim pleaded:
13.The Plaintiff applied for summary judgment, seeking interlocutory judgment on liability, with damages to be assessed. On 11 May 2015, Madam Recorder Linda Chan SC ordered that interlocutory judgment be entered for the Plaintiff against the Defendant, with damages to be assessed (“the 2015 Judgment”). 14.On 1 February 2017, Master J Wong gave leave to the parties toset down the assessment of damages with five days reserved. Subsequently,the assessment of damages was set down for hearing before Anthony Chan J, to commence on 9 May 2018. 15.By a pre-trial review notice of 7 March 2018, the Plaintiff indicated that it would seek leave at the pre-trial review (of 14 March 2018) to file a supplemental expert report relating to the market values of the Units as at the completion dates (of 2 and 6 July 2009). 16.The Defendant’s Summons was issued on 12 March 2018. 17.At the pre-trial review on 14 March 2018, Anthony Chan J ordered, inter alia:
18.12 days later, the Plaintiff issued the Plaintiff’s Summons. DEFENDANT’S APPLICATION TO RE-AMEND THE AMENDED DEFENCE AND COUNTERCLAIM 19.Clause 16 of the Agreements provided as follows:
20.The Defendant’s Summons sought leave to add new paragraphs 81A and 81B to the Amended Defence and Counterclaim, to plead reliance on clause 16(3) of the Agreements, and to take the point that since the Plaintiff had elected to resell the Units in March 2010, more than 6 months after the determination of the Agreements, the Defendant should not be called upon to bear any price deficiency or expenses relating to the resale. Proposed argument based on clause 16(3) not arguable 21.The Defendant’s argument is that clause 16(3) of the Agreements is a liquidated damages clause; as a matter of law, this precludes a claim for common law damages; that factually, by the act of reselling the Units, the Plaintiff has elected the remedy of liquidated damages; and that since the resale took place more than 6 months after the determination of the Agreements, the proviso in clause 16(3) applies and no liquidated damages are payable. 22.Mr Ismail, counsel for the Plaintiff, submitted that the Defendant’s proposed argument was not fairly arguable, so that the amendment would be futile, and ought to be refused. He cited VSC Building Products Company Limited v Kono Insurance Limited, unreported, HCA 947/2005, 9 September 2009, where Andrew Cheung J (as he then was) said:
23.Clause 16(3) of the Agreements is virtually identical to clause 17(3) of the sale and purchase agreement which was considered in King’s City Holdings Ltd v De Monsa Investments Ltd [2013] 4 HKC 450. Fok JA, with whom Lam JA and McWalters J (as they then were) agreed, held in [24] to [27] that:
24.Thus there are two Court of Appeal judgments which have construed a clause virtually identical to clause 16(3) of the Agreements as being a non-exclusive liquidated damages clause which did not preclude the vendor from claiming for common law damages as an alternative remedy — a construction which is directly contrary to the one sought to be pleaded by the proposed paragraphs 81A and 81B. The Court of Appeal judgments are binding on the Court of First Instance as to the question of construction of clause 16(3) of the Agreements. 25.Counsel for the Defendant, Mr Jean-Paul Wou, accepted that this was the case. However, he contended that the Defendant ought to be allowed its proposed amendment as it was entitled to challenge the Court of Appeal’s construction in the Court of Final Appeal. In support of this, he cited note 18/11/1 of Hong Kong Civil Procedure 2018, which says “In a proper case, the court will allow a party to amend his pleading so as to … keep the point open for argument in the final appellate court, as in Cummings v. London Bullion Co. [1952] 1 K.B. 327 ….” 26.Mr Wou submitted that Polyset Ltd v Panhandat Ltd (2002) 5 HKCFAR 234 was an authority which supported his argument on clause 16(3) of the Agreements. He referred to [76] to [79], where Ribeiro PJ compared the different intention and effect of deposit clauses and liquidated damages clauses. Mr Wou relied on [77], where Ribeiro PJ said that where a breach is covered by a liquidated damages clause, the amount prescribed by that clause represents the agreed sum of damages payable, regardless of the quantum of actual loss, and [79], where Ribeiro PJ reiterated that a liquidated damages clause is definitive of the damages recoverable where the actual loss exceeds the amount payable under the clause. Similarly, McGregor on Damages at paragraph 16-022 stated that the courts implement the intention of the parties in the case of liquidated damages by holding the claimant entitled to recover the stipulated sum, irrespective of the amount of actual damage. 27.I do not consider that Polyset (or the passage from McGregor) is authority for an alternative construction of clause 16(3). All that Ribeiro PJ was saying was that where a liquidated damages clause applies, a claimant cannot receive more than the agreed amount of damages. But the point about clause 16(3) is that it has been construed by the Court of Appeal as not precluding a claim for common law damages. Where there is a such a claim, the liquidated damages clause, by definition, will not apply to fix the amount of damages recoverable. 28.Mr Wou also submitted that whilst the Plaintiff had stated that it was claiming common law damages, it had in fact elected, by the act of selling the Units, to claim liquidated damages only. In support of this submission, he cited Talley and anor v Wolsey-Neech (1979) 38 P&CR 45 at 52, where Browne LJ cited Horsler v Zorro (1975) 29 P&CR 180, in which Megarry J was addressing a innocent contractual party’s right to choose between terminating a contract for the other party’s breach and suing for restitution to his former position, or affirming the contract and suing for damages. Megarry J then dealt with the consequences of those alternative remedies. If the innocent party decided to sue for damages, he could choose whether to resell or not, and the measure of damages would be different according tohis choice. Browne LJ then went on to hold that as the plaintiffs had chosen to exercise their rights under condition 19(4)(c) in their contract, they were only entitled to recover the liquidated damages defined by that clause. 29.However, the clause in Talley was very different to clause 16(3) of the Agreements. In Talley, clause 19(4)(b) first provided that without prejudice to any other rights or remedies available to him at law or in equity, the vendor might (i) forfeit the purchaser’s deposit (ii) resell the property; clause 19(4)(c) then provided for the quantum of liquidated damages payable on resale. Thus the clause provided that the act of reselling would constitute an election of the remedy of liquidated damages. 30.I agree with Mr Ismail that the Defendant’s proposed argument on clause 16(3) is plainly unarguable. The authorities cited by Mr Wou do not show that King’s City or Woomera were wrongly decided. It is not a proper case for allowing the Defendant to make an amendment so that the point can be further argued in the Court of Final Appeal. 31.I therefore dismissed the Defendant’s Summons. Res judicata / abuse of process 32.Mr Ismail submitted that the Defendant cannot raise clause 16(3) at this stage, as it was a matter which could and should have been pleaded earlier and dealt with at the time of the summary judgment application. Mr Ismail relies on either the doctrine of abuse of process under Henderson v Henderson (1843) 3 Hare 100 or cause of action estoppel. 33.It seems to me that the Plaintiff has difficulty relying on res judicata in the traditional sense, since the 2015 Judgment did not deal with the construction of clause 16(3), the matter not having been raised by the Defendant at that stage. 34.Mr Ismail did rely on Virgin Atlantic Airways Ltd v Zodiac Seats UK Ltd [2014] AC 160 at [22], where Lord Sumption JSC said that cause of action estoppel is absolute in relation to all points which were had to be and were decided in order to establish the existence or non-existence of a cause of action, and also bars the raising in subsequent proceedings of points essential to the existence or non-existence of a cause of action which were not decided because they were not raised in the earlier proceedings, if they could with reasonable diligence and should in all the circumstances have been raised. 35.However, in the present case, it is not necessary for me to go further into the scope of the doctrine of cause of action estoppel, as the issue can be addressed under the Henderson principle. In Ko Hon Yue v Chiu Pik Yuk (2012) 15 HKCFAR 72, Ma CJ said at [82] to [83]:
36.I agree with Mr Ismail that the Defendant ought not to be allowed to raise clause 16(3) of the Agreements now for the argument that it precludes the Plaintiff’s claim for common law damages by reason of the fact that the Plaintiff resold the Units in March 2010.
37.In the circumstances, the defence based on clause 16(3) of the Agreements could with reasonable diligence have been raised much earlier, and should have been raised at the hearing of the summary judgment application before Madam Recorder Linda Chan SC. 38.Mr Wou does not suggest that the defence based on clause 16(3) of the Agreements could not have been raised before Madam Recorder Linda Chan SC. Rather, he says that the point goes to quantum, whereas Madam Recorder Linda Chan SC was only concerned with the question of whetherthe Defendant could raise any arguable defence. However, the Defendant’s own case is that its construction of clause 16(3) precludes the Plaintiff’s claim for damages entirely. If so, that must have been a matter which could have been put forward in defence to the application for summary judgment. It matters not whether one describes it as a defence going to liability or to quantum. 39.Mr Wou further argued there is no abuse of process as firstly, the upcoming assessment of damages is not a separate set of proceedings with a different case number, and secondly, there has been no judgment on the construction of clause 16(3) of the Agreements. However, the purpose of the Henderson v Henderson principle is to prevent abuse of the process of the Court. Its application cannot depend on whether the upcoming assessment of damages bears a different case number to that of the 2015 Judgment. Furthermore, the classic application of the principle is precisely in the situation where the issue in question was not dealt with in an earlier judgment, the point being that the issue could have been, but was not, raised for the Court’s consideration at that time. 40.Mr Wou also suggested in his skeleton argument that the argument based on clause 16(3) had been foreshadowed in the Defendant’s witness statement (paragraph 51 of the statement of Law Wai), and therefore that the Defendant could raise the point without pleading. At the hearing however, he accepted that the Defendant did need to make the amendments if it was to advance this defence. In any event, I do not accept that the point had been foreshadowed in the witness statement of Law Wai. Read in context, paragraph 51 was addressing the Plaintiff’s failure to mitigate its loss. 41.I therefore refused the Defendant’s proposed re-amendment to its Defence and Counterclaim pursuant to the principle in Henderson v Henderson also. Whether clause 16(3) of the Agreements goes to liability or quantum 42.Mr Ismail further submitted that clause 16(3) of the Agreements goes to the question of liability, which was already dealt with by the summary judgment application, rather than damages, with which the upcoming assessment before Anthony Chan J is concerned. He submitted that the Defendant is not entitled to argue at the assessment of damages that he is not liable to the Plaintiff for damages at all, and can only take issue with the quantum of such damages. 43.I am not convinced that one can “categorise” clause 16(3) as one of “liability” or of “quantum”. As Mr Ismail submits (and as held in King’s City), clause 16(3) is a liquidated damages clause. The clause wouldarise for consideration if there had been a claim for liquidated damages, and depending on the facts of the particular case, the clause might be relevant at the time of determining liability, or quantum, or both. PLAINTIFF’S APPLICATION TO AMEND THE STATEMENT OF CLAIM AND ADDUCE SUPPLEMENTAL EXPERT REPORT 44.The Plaintiff’s Summons sought leave to amend its Statement of Claim, and to file a supplemental expert report, for the purpose of introducing an additional basis for the assessment of damages. That basis is the difference between the price under the Agreements and the market value of the Units as at the date of the originally scheduled deadlines for completion in July 2009 (as opposed to the date of the Determination Notices). Principles on a late application to amend or introduce new evidence 45.The applicable principles are as follows.
Application of principles to the present case 46.The Plaintiff’s Summons, taken out on 26 March 2018, is clearly late.
47.Mr Ismail argued that no prejudice would be caused to the Defendant by the late amendment and supplemental report, as the Defendant’sown expert had indicated that he would be able to provide a responsive report by 2 May 2018. However, I agree with Mr Wou that the Defendant would have suffered prejudice if the Plaintiff’s amendments had been allowed:
48.I also agree that the explanation given for the delay is not satisfactory. In the 3rd Affirmation of Kwok Man Shun Wilson at paragraph 5, the reasons given for the delay are that:
49.However:
50.Therefore, even if it can be said that the claim in the Plaintiff’s proposed amendments is an arguable one, this is no answer to the Defendant’s complaint of delay and prejudice. 51.I bear in mind the fact that refusing leave for the making of the Plaintiff’s proposed amendments and filing of the Plaintiff’s supplemental report will mean that the Plaintiff will not be able to advance the case based on such amendments. However, this prejudice is self-induced. 52.Given the unexplained delay in the making of the application and the prejudice which the proposed amendments and new evidence would cause to the Defendant, I dismissed the Plaintiff’s Summons. COSTS 53.Given that both parties have been unsuccessful on their respective summonses, and that both summonses were the subject of substantial argument both in the written and oral submissions, I will make an order nisi that there be no order as to costs.
Mr Anthony Ismail, instructed by Chu & Lau, for the plaintiff Mr Jean-Paul Wou, instructed by ONC Lawyers, for the defendant [1] In saying this, I am not attempting to express a view as to whether or not the Plaintiff’s pleaded claim did in fact apply this measure of damages. I should record that Mr Wou submitted that even if the Plaintiff were to argue for the market value of the Units as at the date of completion ofsale, this would not be July 2009 (the originally scheduled dates for completion) but the dates ofthe Determination Notices (25 August 2009), when the Plaintiff in fact terminated the Agreements. | ||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCA 1438/2013