Building Authority v. Appeal Tribunal (Buildings)
Read the full judgment text of HCAL 25/2014 on BabelCite. This High Court CFI judgment was delivered on 19 June 2020.
1. This court handed down its judgment (“the Judgment”) on 20 December 2018, dismissing the applicant’s judicial review.
Cited by 4 cases · Cites 8 cases
|
HCAL 25/2014 [2020] HKCFI 1245 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE CONSTITUTIONAL AND ADMINISTRATIVE LAW LIST NO 25 OF 2014 ________________________ BETWEEN
________________________
________________________ DECISION ON COSTS ________________________ A. Introduction 1.This court handed down its judgment (“the Judgment”) on 20 December 2018, dismissing the applicant’s judicial review. 2.The court at [89] of the Judgment made a costs order nisi that the applicant shall pay half of the costs of the judicial review to the interested parties (“the IPs”) (being the only active opponent of the judicial review). This costs order nisi was made on the basis that, although the applicant failed in the judicial review as the court rejected its Grounds 1 and 3, it was successful in its Ground 2. In those circumstances, the court formed the view that a fair and just costs order should be that the applicant shall bear half of the costs of the judicial review. 3.Further, at [88] of the Judgment, the court allowed the applicant’s late amendments to the Form 86, with costs of the application to re-amend be in the costs of the application. Given that I had not heard any submissions on costs when that order was made, that costs order should also be understood to be made on a nisi order basis. 4.This is now the IPs’ application to vary the costs orders nisi[1]. They seek to vary them to the extent that the IP should have the full costs of the judicial review, or alternatively two-thirds of those costs. It also asks for the full costs of the re-amendment in any event. 5.The court directed that the application be dealt with on paper. The parties have for that purpose filed their respective written submissions. 6.This is the decision on the costs variation application. This decision should be read together with the Judgment. Unless otherwise stated, I adopt herein the abbreviations used in the Judgment. B. This costs variation application 7.For the present purpose, I will bear in mind the following relevant principles in dealing with costs[2]:
8.In support of the application that the IPs should have the full costs of the judicial review, Mr Ismail’s main contention is this:
9.With respect to Mr Ismail, I am not convinced by this submission. 10.The applicant in the judicial review sought the relief of (a) quashing the Tribunal’s Decision which allowed the IPs’ appeal, and (b) remitting the appeal to a differently constituted Tribunal to reconsider it. The Tribunal allowed the appeal on the basis of the First Reason and/or the Second Reason. As noted in the Judgment, these First and Second Reasons are distinct and separate reasons as to why the Tribunal allowed the appeal, and related to different obligations that the Tribunal said were imposed on the IPs by SC8 on a proper construction: see [20] - [24] of the Judgment. Hence, in order to succeed in the judicial review, the applicant had to succeed in challenging both the First Reason (based on Grounds 1 and 3) and the Second Reason (based on Ground 2). 11.It was therefore necessary for the applicant to raise and advance Ground 2 in the judicial review. Consequently, it was also necessary for the IPs to advance full submissions to contest it at the hearing. 12.In the premises, in my view, the issue raised under Ground 2 in seeking to challenge the Second Reason (which the applicant succeeded) is so separate and distinct in itself that the decision of it could be said to constitute on “event”. 13.I therefore do not agree with Mr Ismail that Ground 2 itself for the purpose of considering costs did not constitute a distinct and separate “event” (where the applicant succeeded) and hence the IPs should be entitled to the full costs. 14.I have arrived in the above conclusion even by adopting what Mr Ismail has submitted to be the “distinct and separate” approach laid down in Seepersad to construe what constitutes an “event” for the purpose of costs determination. 15.However, I must also mention that Mr Lui for the applicant has submitted that after the implementation of CJR in Hong Kong, the narrow approach to construing “event” in Seepersad should no longer be adopted. In support, he relies on Lam VP’s observations in Chan Shun Kei v Hong Kong Construction (Hong Kong) Ltd (CACV 192/2014, 7 March 2016) at [24] - [25]:
16.If needed, I will also respectfully adopt Lam VP’s above observations in Chan Shun Kei. In my view, even if Seepersad indeed was intended to lay down a more restrictive approach as to what constituted an “event” for the purpose of costs, it must now be understood and applied in Hong Kong in the context of our own jurisprudence and principles over costs determination developed and summarized in [7] above. In any event, Chan Shun Kei is binding on this court and represents the guiding principle this court should adopt in determining this application. Applying that, I would also clearly conclude that the issue raised under Ground 2 constituted an “event” which the applicant had succeeded. 17.I now turn to the alternative contention raised by the IPs that they should be entitled to two-thirds of the costs instead of one-half. This is so, Mr Ismail submits, as the majority of the legal arguments and analysis made and debated in the judicial review and at the hearing were related to Grounds 1 and 3. In the premises, it will not be just and fair to deprive the IPs half of their costs. 18.On reflection, I agree with Mr Ismail. It is indeed correct that a substantial part of the arguments and evidence referred to in the judicial review and in particular at the hearing were related to Grounds 1 and 3. In the circumstances, even though the IPs were unsuccessful in defending Ground 2, it would not be fair and just to deprive them half of their costs. Applying the principles summarized at [7] above, and taking the matters in the round, I would vary the costs order nisi to the extent that the applicant shall pay the IPs two-thirds of the costs of the judicial review. 19.Finally, the IPs say they should be entitled to all the costs of the applicant’s application to re-amend the Form 86. Mr Lui for the applicant has fairly agreed in his written submission that the applicant should bear such costs. 20.I would therefore also vary that costs order to the extent that the costs of the re-amendment application be to the IPs. C. Disposition 21.I will vary the costs orders nisi to the following extent:
22.As the IPs are successful in this variation application, I further order that costs of this application be to the IPs, to be taxed if not agreed. 23.I thank counsel’s assistance in this matter.
Mr Mike Lui, instructed by Department of Justice, for the applicant Mr Justin Ismail, instructed by Betty Chan & Co, for the interested parties [1] By its summons dated 2 January 2019. [2] See: Lo Yuk Sui v Fubon Bank (Hong Kong) Ltd [2019] HKCA 1345 at [17] - [18] perLam VP; Jonnex International Ltd v Town Planning Board [2018] HKCFI 836 at [4] per Au J; The Real Estate Developers Association of Hong Kong v Town Planning Board [2016] 2 HKLRD 642 at [6]; Pfeiffer GmbH v Cheung Hay Kit trading as Sun Wai Construction (CACV 245/2013, 29 October 2014, Kwan and Barma JJA, Poon J) at [20]; Fairbo Investment Ltd v Appeal Tribunal (Buildings) (HCAL 35/2012, 27 January 2015, Au J) at [7]. [3] Mr Ismail submits that this was adopted by Lam J (as the learned VP then was) in Hong Kong Kam Lan Koon v Realray Investment Ltd (No 4) [2005] 4 HKC at [13]. |
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCAL 25/2014