Read the full judgment text of HCA 1725/2019 on BabelCite. This High Court CFI judgment was delivered on 27 May 2021.
1. This is an application made by the Defendants to stay the proceedings instituted by the Plaintiff against them. The 4 th Defendant (“ CAE ”) claims that the action should be stayed in favour of arbitration, on the basis of an arbitration agreement made between the Plaintiff and CAE and contained in a contract for works relating to the Tuen Mun - Chek Lap Kok Link - Northern Connection Sub-sea Tunnel Section project HY/2012/08 (“ Project ”). The 1 st to 3 rd and 5 th to 8 th Defendants claim
Cited by 7 cases · Cites 1 case