Kensland Realty Ltd. v. Whale View Investment Ltd. and Another
Read the full judgment text of FACV 10/2001 on BabelCite. This Court of Final Appeal judgment was delivered on 10 December 2001 before Bokhary PJ, Chan PJ, Ribeiro PJ, Nazareth NPJ, Brennan NPJ.
Land law – sale and purchase of land – Hong Kong method of completion by undertaking – sub-sale by confirmor – split payment of balance of purchase price – clause requiring balance to be paid by cashier orders and solicitors' cheques in favour of persons as vendor may direct – whether implied term as to time for giving split payment direction – whether vendor in breach – whether vendor entitled to rely on time of the essence clause to rescind and forfeit deposit after late tender caused by its own breach – prevention principle – a man shall not be allowed to take advantage of his own wrong. The appellant confirmor contracted to buy a Mongkok shop from the head vendor for $53 million and, as confirmor, sub-sold it to the 1st respondent purchaser for $55 million, with completion to take place by the Hong Kong undertaking method. The purchaser's completion deadline was 1:00pm on 2 September 1997 and the confirmor's own completion deadline with the head vendor was 5:00pm the same day. Clause 37 empowered the confirmor to direct how the balance of $46.75 million was to be split between payees but did not specify any time for giving that direction. The confirmor's solicitors first faxed the split cheque direction (nine cheques and cashier orders) at 11:13am on 2 September, with a correction at 11:48am, after months of pressure from the purchaser's solicitors. The purchaser's solicitors dispatched a messenger to the bank at 11:35am, the bank officers verified the documents and signed the cashier orders between 12:25pm and 12:45pm, and the messenger delivered the instruments to the confirmor's solicitors at about 1:06pm. The confirmor refused to complete, treated the late tender as a repudiatory breach, and forfeited the $8.25 million deposit. The purchaser sued the confirmor, its bank, and its own solicitors (the 2nd respondents, Tam, Pun & Yipp), who in turn were the subject of a third-party claim by the bank. Held, dismissing the confirmor's appeal: (1) where the contract is silent as to the time for giving a split payment direction under a clause such as Clause 37, an implied term must be read into the contract requiring the vendor to give the direction within such time before the completion deadline as the purchaser reasonably requires to arrange for and make split payment in the ordinary course of business. The BP Refinery v Shire of Hastings conditions for implying a term must be satisfied, in particular that the term must not contradict any express term of the contract. The relevant time is not limited to the narrow 'mechanics of payment' needed to draw up cheques or cashier orders; it must include the time ordinarily required for dealings with the purchaser's lending institution for draw down of mortgage finance, the role of the purchaser's solicitors in collecting, checking and forwarding the instruments, and delivery to the agreed venue for completion (per Bokhary PJ, Ribeiro PJ). (2) The vendor's proposed 'mechanics of payment' test, based on cases such as Bank of Baroda v Panessar concerning repayment of debts on demand, was rejected as a mis-characterisation of a contract for the sale of land (per Ribeiro PJ). (3) On the facts, the 11:13am direction (with correction at 11:48am), less than two hours before the 1:00pm deadline and after the confirmor's solicitors had known for months that a direction would be required, did not give the purchaser a reasonable time to comply. The vendor was in breach of the implied term. The 48 minutes taken by the bank to verify documentation and authorise draw down of a substantial mortgage loan was a reasonable and necessary step, and Clause 3, providing a three-hour completion window, indicated the parties contemplated the full period would be available to the purchaser. (4) The Court of Appeal's second limb of the implied term, requiring the vendor to grant a reasonable extension of time where the direction is given too late, could not be supported: it contradicted the express Clauses 3 and 12 (time of the essence) and offended the fifth BP Refinery condition. (5) The correct approach to the consequences of the vendor's breach lay in the prevention principle, namely that a man shall not be allowed to take advantage of his own wrong (Lord Coke, Co Litt 206b). The principle applies where there is a breach of a duty owed by one party to the other under the contract and a causal connection between the breach and the right being asserted. The principle may be given effect as a substantive rule of law, as a rule of construction, or by deeming the relevant condition fulfilled. (6) The prevention principle, and Clause 13(a) of the contract (which preserved the vendor's rescission rights only where the purchaser's failure was not due to the vendor's default), together with section 11 of the Law Amendment and Reform (Consolidation) Ordinance (Cap 23), precluded the vendor from invoking Clause 12 to rescind and forfeit the deposit. The purchaser had affirmed the contract and was entitled to be relieved against the consequences of missing the 1:00pm deadline. The vendor's refusal to accept the 1:06pm tender was itself a repudiatory breach. (7) Result: the Court of Appeal's orders were affirmed. The vendor was ordered to return the $8.25 million deposit, to pay $8 million in damages for loss of bargain, plus interest at 10.5% from 3 August 1997 to 23 January 2001, and to pay the purchaser's and the solicitors' costs of the action, the appeal and the appeal to the Court of Final Appeal (the latter by order nisi).
Legal issues: Nature and scope of the implied term for giving split payment direction · Whether the vendor breached the implied term · Validity of the Court of Appeal's second limb of the implied term requiring an extension of time · Legal consequences of vendor's rejection of late tender following its own breach
Outcome: Appeal by Kensland Realty Limited dismissed; Court of Appeal's orders affirmed in favour of the Purchaser and the Solicitors, although on different grounds. The vendor was held to have repudiated the contract by refusing the 1:06pm tender.
Cited by 159 cases · Cites 2 cases
|
FACV No. 10 of 2001 IN THE COURT OF FINAL APPEAL OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION FINAL APPEAL NO. 10 OF 2001 (CIVIL) (ON APPEAL FROM CACV NO. 286 OF 2000) _____________________
_____________________
Date of Hearing: 9 and 10 October 2001 Date of Judgment: 10 December 2001 __________________ J U D G M E N T __________________ Mr Justice Bokhary PJ: 1.I have had the advantage of reading Mr Justice Ribeiro PJ's judgment which I understand entirely reflects not only his view but also that of Mr Justice Nazareth NPJ and Sir Gerard Brennan NPJ. I agree with that judgment and understand that Mr Justice Chan PJ also agrees with it. Nevertheless I consider it worthwhile to emphasise certain points on the important legal issues which arise. The questions of law before the Court 2.In Hong Kong the sale of land is routinely completed by way of undertaking rather than at a physical completion meeting. This is so even where the land is subject to an existing mortgage or (as in the present case) the sale is a sub-sale to be completed before completion of the head sale takes place. Where completion is by undertaking, the balance of the purchase price is not paid in simultaneous exchange for a duly executed assignment and any existing mortgagee's receipt operating as a release. Instead the balance of the purchase price is paid against the vendor's solicitors' undertaking to deliver such an assignment and release to the purchaser's solicitors within a specified time. 3.Completion by undertaking is favoured in Hong Kong for its speed and convenience. But it is recognised that it carries a risk. This risk is catered for by a system whereby the payment of the purchase price is split between the vendor and any other person or persons who must receive his or their money before the purchaser can expect good title. Accordingly it is standard for agreements for the sale and purchase of land in Hong Kong to contain (as the agreement in the present case does) an express term to the effect that the payment of the balance of the purchase price shall be by cashier's orders or solicitors' cheques in favour of such persons as the vendor may direct. And although such clauses are couched in terms of what the vendor may do, they must be taken to mean that the vendor is obliged to inform the purchaser how the balance of the purchase price is to be split. Indeed if an agreement for the sale of land does not expressly provide for split payment even though the land is subject to an existing mortgage or the sale is a sub-sale to be completed before completion of the head sale takes place, then a term for split payment would have to be implied. For it is unreal to imagine that in such circumstances any purchaser or his bankers would agree, or that any vendor would expect them to agree, to completion by undertaking without split payment protection. 4.Sometimes the split payment clause expressly stipulates the time by which split payment information must be given. This is obviously desirable. But sometimes (as in the agreement in the present case) the split payment clause contains no such express stipulation. It is common ground that in the absence of such an express stipulation, there must be an implied term as to the time for giving split payment information. The questions of law now before the Court are: (i) what is the time to be implied? and (ii) what are the consequences of failure on the vendor's part to give such information within time? The facts 5.Kensland Realty Ltd entered into an agreement to purchase certain shop premises in Mongkok from Delight Holdings Ltd for $53 million. Kensland then entered into an agreement ("the Agreement") to sell those premises to Whale View Investment Ltd for $55 million. Such sale was to be by Kensland as confirmor. The deadline for completion of Kensland's own purchase from Delight was 5.00 p.m. on Tuesday, 2 September 1997. The deadline for completion of Whale View's purchase from Kensland was four hours earlier i.e. 1.00 p.m. on the same day. Hardly anything more need be said about Delight, and I will from now on refer to Kensland as "the Confirmor" and to Whale View as "the Purchaser". 6.Deposits totalling $8.25 million were paid by the Purchaser to the Confirmor, leaving a balance of $46.75 million to be paid by the Purchaser to the Confirmor upon completion. For that purpose, the Purchaser got a bank loan of $33 million. A series of hitches preceded the eventual finalisation of this loan. By the time when the last of these hitches was sorted out, there were 40 minutes left before the deadline for completion. 7.Clause 37 of the Agreement provided for payment of the balance of the purchase price by such cashier's orders or cheques in favour of such persons as the Confirmor may direct. The Purchaser's solicitors had long been pressing the Confirmor's solicitors for split payment information. But none was given until one hour and 47 minutes before the 1.00 p.m. deadline when the Confirmor directed that the balance of the purchase price be paid by nine cheques. The split payment information given at that stage contained a discrepancy. By the time when the correct split payment information was eventually received, one hour and 12 minutes remained before the 1.00 p.m. deadline. 8.As is standard in agreements of its kind, the Agreement expressly provided that time shall in every respect be of the essence. Twice during the 20 minutes or so before the 1.00 p.m. deadline, the Purchaser's solicitors, realising that they may not be able to meet that deadline, telephoned the Confirmor's solicitors to seek an extension. When they spoke to the solicitor handling the transaction, he said that he would have to consult the partner concerned and take instructions from the Confirmor. He did not revert to the Purchaser's solicitors, so they telephoned again, asking for the partner. They were told that he was out. When they asked to speak to the solicitor with whom they had earlier spoken, they were told that he had gone out to lunch. 9.The place for completion was the Confirmor's solicitors' offices. Because of the limit on the amount which the bank was willing to credit into the Purchaser's solicitors' account, part of the balance of the purchase price had to be paid by cashier's order. As the mathematics dictated, one of the split payments had to be partly by cheque and partly by cashier's order In the result eight cheques and two cashier's orders were involved. The eight cheques were brought to the Confirmor's solicitors' offices by the Purchaser's solicitors just after 1.00 p.m. To their surprise, they found there the solicitor and the partner both of whom they had been told had gone out. Shortly after the Purchaser's solicitors' arrival, their messenger arrived from the bank with the two cashier's orders. So the eight cheques arrived just after the 1.00 p.m. deadline, and the two cashier's orders arrived six minutes after that deadline. 10.The Confirmor refused to complete. It treated the Purchaser's failure to tender the eight cheques and two cashier's orders until some six minutes after the 1.00 p.m. deadline as a repudiatory breach. And it treated the Purchaser's deposit of $8.25 million as forfeited. Later that day, the Confirmor's own purchase of the shop premises from Delight was completed. Proceedings commenced 11.On the following day, the Purchaser commenced proceedings. The Purchaser contended that the Confirmor was not entitled to treat the six minutes' delay as a repudiatory breach. Initially, the Purchaser sought specific performance. But when the property market fell a few months later, the Purchaser sought instead the return of its deposit and damages representing the profit which it would have made if the purchase had gone through and it had then sold the shop premises in the few weeks following 2 September 1997. The Purchaser also sued its own bankers, the Bank of East Asia ("the Bank") and its own solicitors, Messrs Tam, Pun & Yipp ("the Solicitors"), blaming both for the fact that completion had not taken place by the 1.00 p.m. deadline. The Bank, making the Solicitors a third party, sought an indemnity from them against any liability to the Purchaser. 12.Disputing the claim, the Confirmor counterclaimed. The most significant items of relief which it counterclaimed were: (i) a declaration that it was entitled to forfeit the deposit up to the contractual limit of 10% of the price at which the Purchaser had agreed to purchase the shop premises; and (ii) damages representing the difference between that price and the value of the shop premises when the lis pendens registered against them was lifted upon the abandonment by the Purchaser of its claim for specific performance. At first instance 13.The action was tried by Deputy Judge Gill in the Court of First Instance of the High Court. As to the time within which the split payment information had to be given, the Purchaser pleaded that it was an implied term of the Agreement that such information had to be given within a reasonable time before completion to enable the Purchaser to comply with it. The judge accepted that there was an implied term that the Confirmor would give such direction within a reasonable time before completion. A reasonable time, he held, was the time "it would take for a reasonably competent conveyancer to check the figures and then comply with the request and complete, without undue pressure, before the deadline". He took the view that the split payment information in the present case had been given within such time. The failure to meet the deadline was, he held, due to the fact that the two cashier's orders were not issued until 12 minutes before the deadline. And this was due, he held, to mistakes made by the Solicitors in preparing the documents required by the Bank. 14.Accordingly, by the judgment which he delivered on 5 April 2000, the judge dismissed the Purchaser's claim against the Confirmor and gave the Confirmor judgment on its counterclaim. He limited the award thereunder to so much of the deposit as represented 10% of the price at which the Purchaser had agreed to purchase the shop premises. He dismissed the Purchaser's claim against the Bank. But he gave judgment for the Purchaser on its claim against the Solicitors, limiting the award thereunder as he had limited the award against the Purchaser on the Confirmor's counterclaim. Since no liability to the Purchaser was found against the Bank, it did not need any indemnity from the Solicitors. 15.As to the costs of the claim and counterclaim, the judge awarded costs: (i) to the Confirmor and the Bank against the Purchaser; and (ii) to the Purchaser against the Solicitors, such costs to include reimbursement to the Purchaser by the Solicitors of the costs ordered against the Purchaser in favour of the Confirmor and the Bank. The costs of the third party proceedings were awarded to the Bank against the Solicitors. In the Court of Appeal 16.The Solicitors appealed to the Court of Appeal (Keith, Stock and Le Pichon JJA) which gave its judgment on 23 January 2001. In contending that judgment should not have been given in favour of the Confirmor against the Purchaser, the Solicitors contended that it was the Confirmor, not the Purchaser, which had been in repudiatory breach. The Confirmor and the Purchaser each appealed to the Court of Appeal against the limit which the judge had placed on the award in its favour. The Bank was not a party to any proceedings after the first instance stage. As a party, the Bank dropped out of the picture after the judge decided in its favour. 17.As to the shape of the case before the Court of Appeal, Keith JA, giving the judgment of that court, explained:
18.Two terms were implied by the Court of Appeal. These were:
19.The Court of Appeal held that, in breach of the first implied term, the split payment information in the present case was not given in time for the Purchaser to arrange, without undue pressure, for split payment to be made by the deadline for completion. Therefore, the Court of Appeal held, the Confirmor's refusal to extend that deadline was in breach of the second implied term. The Confirmor and the Purchaser agreed before the Court of Appeal that if the Purchaser were to succeed, then the Confirmor would be liable to (i) return the Purchaser's $8.25 million deposit and (ii) pay the Purchaser damages in the sum of $8 million. 20.On the foregoing basis, the Court of Appeal (i) set aside the judge's orders against the Purchaser and the Solicitors; (ii) entered judgment for the Purchaser against the Confirmor in the sum of $16.25 million with interest at the rate of 10.5% from 3 August 1997 when the writ was issued until 23 January 2001 when the Court of Appeal gave judgment; and (iii) ordered that the Confirmor pay the Purchaser and the Solicitors their costs of the action and the appeal. 21.The Confirmor now appeals to this Court, making the Purchaser the 1st respondent and the Solicitors the 2nd respondent. Implied term as to the time for giving split payment information 22.Where completion is by undertaking and the land is subject to an existing mortgage or the sale is a sub-sale to be completed before completion of the head sale takes place, split payment of the balance of the purchase price is necessary in order that the purchaser may part with his money reasonably confident that he will receive good title to the property clear of any encumbrances. Therefore he cannot be expected to complete within the time fixed for completion unless he is given the necessary split payment information in time for him to arrange for split payment to be effected before the expiry of the completion deadline. Where such an agreement is silent as to the time by which the vendor must give the purchaser the split payment information, there must be an implied term as to such time. 23.In my view, any term to be implied in this context must comply with the conditions stated by Lord Simon of Glaisdale when delivering the advice of the majority in the Privy Council case of B.P. Refinery (Westernport) Pty Ltd v. President, Councillors and Ratepayers of the Shire of Hastings (1978) 52 ALJR 20 at p.26:
24.Mr John Griffiths SC for the Confirmor referred to Lord Wilberforce's discussion in Liverpool City Council v. Irwin [1977] AC 239 at pp 253F-254A. Mr Griffiths submitted that since the term to be implied involved payment of the balance of the purchase price, the only time to be implied is the time strictly necessary to implement the mechanics of payment. In other words, Mr Griffiths submitted, the time available to a purchaser who had to make split payment is no more than the time available to a debtor who has to make repayment on demand. 25.In Bank of Baroda v. Panessar [1987] 1 Ch 335 at p.348 B-D Walton J (repeating a statement which he had made in an unreported case in 1975) said:
26.I accept of course that a purchaser is not entitled to refrain from taking any steps to line up finance until he has received split payment information. But beyond that the position of a purchaser who has to make split payment is by no means analogous with that of a debtor who has to make repayment on demand. 27.Even though finance has been lined up, there may well be a number of checks to be made and authorisations to be obtained after the split payment information has been communicated to the lending institution and before draw down can proceed. That, the evidence discloses, was the position in the present case. It would be wrong to assume that draw down is a mere matter of the mechanics of signing cheques or drawing up cashier's orders. And even after the cheques or cashier's orders involved in any given case have been prepared and checked by the purchaser's solicitors, the instruments still have to be brought to the place for completion, usually the vendor's solicitors offices. 28.For an agreement for sale and purchase to be effective, a term must be implied to the effect that the requisite split payment information must be given within such time prior to completion as to give the purchaser the time which he reasonably requires to arrange for and make split payment before the expiry of that deadline. In assessing the time reasonably required, account must be taken of all the matters of which the parties to the transaction in question were aware, or ought reasonably to have contemplated, at the time when the contract was made. In the normal way, these matters would include the involvement of a lending institution and solicitors. It is also to be understood that the time reasonably required is not to be set at the minimum time in which things could be done under ideal conditions. Consequences of failure to give split payment information within time 29.The Court of Appeal thought that the consequence of a vendor's failure to give split payment information within time was the operation of a further implied term, being one that the vendor would grant the purchaser such an extension of time as the purchaser reasonably required to comply with the late split payment direction. That is open to two objections. First, it forces a late completion on the purchaser. Secondly, it involves the impermissible course of implying a term which contradicts an express term, namely the one for completion by the stated deadline with time being stated to be of the essence. 30.Failure on a vendor's part to give the requisite split payment information within time is a breach of contract on his part. Where such failure results in a completion deadline being missed, the purchaser is not limited to treating such failure as an anticipatory breach with repudiatory effect. He may instead, if he so chooses, treat the contract as alive and tender split payment as soon as he reasonably can having regard to when he was given split payment information. Even if such tender comes after the completion deadline, the vendor cannot reject it. For he could only reject it if he is entitled to insist on that deadline even though his breach of contract caused it to be missed. And I have no doubt that he is not entitled to do that. In New Zealand Shipping Co. Ltd v. Societe des Ateliers et Chantiers de France [1919] AC 1 at p.8 Lord Finlay LC referred to the principle laid down by Sir Edward Coke that a man shall not be allowed to take advantage of a condition which he himself brought about. Whatever else that principle may or may not encompass, I have no doubt that it encompasses the proposition that where a state of affairs is brought about by a breach of contract, the law does not permit the party in breach to take advantage of that state of affairs to the detriment of the other party. Whether split information payment not given within time 31.The next question in this appeal is whether the split payment information in the present case was given within a reasonable time before completion. This was a question of fact and degree of the kind which the Court of Appeal was in as good a position as the judge to decide. The time allowed was very tight. Mr Griffiths has advanced a very skilful argument to the effect that, but for mistakes made by the Solicitors in preparing the documents required by the Bank before draw down, there would nevertheless have been enough time to complete by the completion deadline. However that is based on the "mechanics of payment" test which I have rejected. And even on that test, it would have been, as Mr Griffiths realistically accepted, a near run thing. On the true test, the time allowed was insufficient. The Solicitors' mistakes are open to criticism. But they were made while time was tight, and not enough time was left for correcting them. In my view, the Court of Appeal was correct in disagreeing with the judge and concluding that the split payment information had not been given within time. Whether the Purchaser tendered payment as soon as he reasonably could 32.In tendering split payment only six minutes after the completion deadline, the Purchaser plainly tendered such payment as soon as it reasonably could having regard to the lateness of the split payment information. That being so, for the reasons which I have given earlier, the Confirmor was not entitled to reject the payment tendered, and put itself in repudiatory breach by rejecting such payment. Result 33.Accordingly I would dismiss this appeal and affirm the Court of Appeal's orders, including those as to the costs in the courts below. As to the costs in this Court, I would make an order nisi for costs in favour of the Purchaser and the Solicitors against the Confirmor, such order nisi to become absolute within 21 days if no written application for some other order as to costs is made within that time. As to the position if such an application is made, I would order that the matter be dealt with on written submissions for which procedural directions should be sought from the Registrar if the parties are unable to agree on procedural matters in that regard. Mr Justice Chan PJ: 34.I agree with the judgments of Mr Justice Bokhary PJ and Mr Justice Ribeiro PJ. Mr Justice Ribeiro PJ: The contract 35.In May 1997, the appellant ("the vendor") entered into a contract ("the contract") to sell a property consisting of a shop in Mongkok to the 1st respondent ("the purchaser") for $55 million. The 2nd respondents ("the purchaser's solicitors") were solicitors acting for the purchaser in the transaction. Representing the vendor were Messrs Tai, Tang & Chong ("the vendor's solicitors"). The Bank of East Asia, Limited ("the bank") had agreed to provide mortgage finance for the purchaser's acquisition and was originally sued as a defendant. However, no claim is now made against the bank and it is not a party to this appeal. The vendor was selling as confirmor, having itself contracted to purchase the property from Delight Holdings Ltd ("the head vendor") for $53 million. 36.Material terms of the contract include the following :-
Transaction not completed 37.The transaction was never completed. The purchaser's solicitors arrived at the vendor's solicitors' offices and tendered the balance of the purchase monies six minutes after expiry of the period for completion stipulated by Clause 3, that is, at 1:06 pm on 2 September. The vendor refused to accept late tender and asserted the right to treat the contract as repudiated and to forfeit the deposits paid thereunder. 38.Where, as by Clause 12, time is made of the essence, it is well established that the time stipulated for completion must be strictly complied with and that no equitable or other relief is granted simply because the purchaser could be said to have been only slightly late: Union Eagle Ltd v. Golden Achievement Ltd [1997] AC 514. However, in the present case, the purchaser complains that its inability to complete in time was due to the vendor's default. 39.The vendor gave a direction that, on completion, the purchaser should pay the balance of the purchase price by nine cheques or cashier orders drawn in favour of various specified payees ("the split cheque direction"). Despite earlier requests made by the purchasers to be provided with any such direction, it was only at 11:13 am on 2 September, the day agreed for completion, that the purchaser's solicitors first received a fax containing the same. 40.Clause 37 does not lay down any deadline by which a vendor must give a split cheque direction. However, the parties all accept that the power to give such a direction must be subject to an implied obligation requiring the vendor to do so a reasonable time before completion was due. 41.The purchaser contends that giving the split cheque direction at 11:13 am (with a correction at 11:48 am), less than two hours before expiry of the specified completion period, constituted a breach of the implied term and that its own failure to meet the contractual deadline for completion was attributable to the fact of such breach. 42.On 3 September 1997 the purchaser issued a writ claiming specific performance of the contract of sale by the vendor. Subsequently the purchaser amended its statement of claim against the vendor to claim damages and consequential relief including repayment of the $8,250,000.00 which it had paid to the vendor by way of deposit and part payment of the purchase price. Decisions below 43.At the trial ([2000] 2 HKLRD 261), His Honour Judge Gill, sitting as a deputy judge of the Court of First Instance, decided that the split cheque direction, given at 11:13 am, had left time "sufficient for the experienced conveyancer to comply without risk of being too late for completion" and that accordingly, there had been no breach. The vendor was therefore held entitled to forfeit the deposits when the purchaser missed the deadline for completion. However, the judge also held that it was due to the negligence of the purchaser's solicitors that the completion monies had not reached the vendor's solicitors in time, making the purchaser's solicitors liable in damages to the purchaser. He assessed such damages as the value of the forfeited deposits. 44.The Court of Appeal ([2001] 2 HKLRD 342) reversed the judge's decision. Keith JA, giving the judgment of the court, held that it was appropriate to imply a term having two limbs in relation to the timeous giving of a split cheque direction, namely, that :-
45.The Court of Appeal held that the split cheque direction was in the circumstances given too late. The court indicated, without so deciding, that half a working day would have been sufficient. In consequence, it was held that by virtue of the second limb of the implied term, the vendor came under an obligation to grant the purchaser an extension of time to tender the balance and, in refusing to accept the tender made at 1:06 pm, the vendor had repudiated the contract. 46.The Court of Appeal appears to have held that such repudiation was accepted by the purchaser's issue of the writ on the next day, 3 September 1997 (mistakenly stated in the judgment to be 3 August). The court also exonerated the purchaser's solicitors, holding that any contribution which they may have made to the late tender was irrelevant since the vendor was required to grant an extension and since the relevant breach was constituted by the vendor's rejection of the tender at 1:06 pm. 47.The purchaser was therefore held entitled to a return of its deposits totalling $8.25 million, plus damages for loss of bargain amounting to $8 million, reflecting the parties' agreement that the shop was worth $63 million on 2 September (mistakenly stated to be 2 August), plus interest on those sums. The issues on appeal 48.On the vendor's appeal to this Court, the issues are as follows :-
49.The first two issues arise only because Clause 37 does not provide for a deadline by which the vendor must give any desired split cheque direction. An express provision, such as that contained in the contract between the vendor and the head vendor, requiring the latter to give at least one day's notice of the necessary payment details, is obviously desirable. The nature and scope of the implied term 50.In Hong Kong, where interests in land are frequently regarded as marketable commodities, a method which facilitates the speedy completion of contracts for the sale and purchase of such interests is desirable, especially for sub-sales in a rising or falling market. The method which has been almost universally adopted was considered by the Privy Council in Edward Wong Finance Co Ltd v. Johnson Stokes & Master (A Firm) [1984] AC 296. Lord Brightman, quoting Roberts CJ, described the method :-
51.In the present case, this method of completion was expressly provided for in the vendor's agreement with the head vendor and was plainly contemplated for use in the sub-sale as between the vendor and the purchaser. 52.The Privy Council pointed out the steps which the solicitor for the purchaser ought to take in order to protect the interests of the purchaser when the purchase price is paid. Lord Brightman said (at pp 307H-308B) that what was needed :-
53.The requirement of split payments in cases involving purchases of land subject to a mortgage which has to be discharged (and by logical extension, involving a confirmor's sale subject to a head vendor's interest which likewise has to be cleared) represents the Hong Kong practice, as reflected in guidance provided by the Law Society. After the Court of Appeal's judgment in Edward Wong Finance, Circular 84/81 was issued, stating that completion by undertaking was still acceptable but adding in its paragraph 4 :-
54.After the Privy Council's decision, the Law Society's Circular 218/91 stated :-
55.In the ordinary case where the Hong Kong method of completion is to be adopted for completion of a sub-sale prior to completion of the head sale or for completion of a sale where the property is subject to a mortgage, both parties understand that a split cheque direction has to be given to enable the interests of the purchaser to be adequately protected when the purchaser's solicitor pays the purchase price without obtaining the stipulated title in exchange. That is the established usage in such cases. The court will imply a term that, in order to permit the purchaser's solicitor to complete the contract on behalf of his client, the vendor or his solicitor will provide a split cheque direction. Such a term will be implied because, to adopt the language of Lord Wilberforce in Liverpool City Council v. Irwin [1977] AC 239 at 253, the term is one that "both parties know and would, if asked, unhesitatingly agree to be part of the bargain." The implication falls within the first category to which Lord Wilberforce referred in that case. 56.Therefore, where the contract contains an express clause empowering the vendor or the vendor's solicitor to give a split cheque direction, there is an implication that the power will be exercised. The more tendentious question - the question which arises in this case - is the time for the giving of the direction. The answer to that question is not to be ascertained from established usage but rather by implication from the terms of the contract itself. In the absence of an express provision, business efficacy demands that the notice be given so as to allow the purchaser's solicitor a reasonable time in which to do what has to be done to comply with the notice prior to the time fixed for completion. And that time varies with the circumstances of the particular case. 57.For the contract to be workable, the parties must be taken to have intended that the giving of any split cheque direction would not be inconsistent with the purchaser's practical ability to effect timeous completion. (i) The Court of Appeal's implied term 58.The term implied by the Court of Appeal is set out above. The purchaser's solicitors, represented by Mr Joseph Fok SC, appearing with Mr Russell Coleman, sought to support that ruling. So did Mr Edward Chan SC, appearing with Mr Wallace Cheung for the purchaser, although his position was essentially that his clients were in any event entitled to compensation for their loss, either as against the vendor or as against the purchaser's solicitors and that he was to that extent "neutral". 59.In a well-known passage, Lord Simon, expressing the majority opinion of the Privy Council, sets out the requirements for implying a term in a written contract :-
60.The fifth requirement is of importance. While room for argument exists as to how precisely the first limb of the Court of Appeal's implied term ought to be formulated, no one doubts that some such term, importing a "reasonable time" condition, must be implied. However, the second limb of the Court of Appeal's implied term offends against Lord Simon's fifth requirement and cannot be supported. 61.By the combined effect of Clauses 3 and 12, the parties expressly agreed (i) that the purchaser was bound to tender the balance on completion and, as completion was to take place between 10:00 am and 1:00 pm on 2 September, the balance was to be tendered by no later than 1:00 pm; and (ii) that time was of the essence in respect of that obligation, so that, in the absence of any supervening event excusing late tender, the vendor was entitled to treat non-observance of the time limit as a breach of an essential term entitling the vendor to rescind. To hold that the vendor was under a duty by virtue of an implied term to extend the time for completion beyond 1:00 pm and therefore under a duty to accept tender at 1:06 pm, is unsustainable since such a term contradicts the two express clauses and cannot be implied. 62.This flaw in the Court of Appeal's reasoning wholly undermines its decision since its findings that the vendor was liable and that the purchaser's solicitors should be exonerated, rest crucially on the existence and breach of the unsustainable implied term. (ii) The vendor's approach 63.The approach adopted by Mr John Griffiths SC, appearing with Mr Benjamin Chain for the vendor, was understandably aimed at minimising the period of time necessary to satisfy the implied reasonable time requirement. 64.Mr Griffiths referred to the categories of implied term discussed by Lord Wilberforce in Liverpool City Council v. Irwin [1977] AC 239 at 253-255, and submitted that the term in the present case ought to be implied as a legal incident of the kind of contract in question rather than adopting any broader business efficacy approach. He argued that since the implication was of a term qualifying Clause 37, which is a clause dealing with payment of the purchase monies, the Court ought to characterise the relevant type of contract as one for the payment of money. It follows, so he argued, that the term to be implied as an incident of such a contract imposes requirements which relate only to what is strictly necessary for implementing the mechanics of payment. In support, he relied on a series of cases, all discussing the time allowable to a debtor to effect repayment when demand is made in respect of a debt contracted to be repayable on demand. 65.For instance, he relied on Massey v. Sladen (1868) LR 4 Exch 13, where, in relation to a bill of sale requiring the debtor to make repayment "instantly on demand", Kelly CB held that a reasonable time must nonetheless be allowed, stating :-
66.He also relied on cases including Bank of Baroda v. Panessar [1987] 1 Ch 335, and Sheppard & Cooper Ltd v. TSB Bank plc [1996] 2 All ER 654. In the former decision, Walton J (at 348) reiterated a view of the law that he had taken in an earlier case in the following terms :-
67.On the basis of such authorities, Mr Griffiths contended that in the present case, the implied obligation excludes from the reckoning of "reasonable time" any periods that might be needed to arrange finance or to draw up or check conveyancing documents or bank security documents or otherwise to go through procedures relating to completion of the broader sale and purchase or mortgage transactions. Allowance should be made only for such time as may reasonably be needed to see to the mechanics of effecting payment of the purchase monies, that is, to have the payment instruments drawn up, issued and delivered to the vendor's solicitors. The precise period required may depend on the nature of the split cheque direction given. Thus, more time would have to be allowed if the direction was to deliver 100 cheques as opposed to say, two cheques. Accordingly, in deciding how much notice to give, it was argued that the vendor is entitled to assume that the purchaser and its bankers and solicitors had previously taken any other required steps, extraneous to those strictly involving payment. Mr Griffiths furthermore submitted that where, as in the present case, both firms of solicitors were in the Central District, the vendor could legitimately assume that any cashier order required would be issued by, or by prior arrangement with, a branch of the purchaser's bank situated within or close to Central so that the time needed to deliver the instrument to the vendor's solicitors would be a matter of minutes. 68.Adopting this "mechanics of payment" approach, and bearing in mind that the split cheque direction required the issue of nine cheques or cashier orders, the vendor submits that the implied obligation was to give only a short period of notice, a period certainly less than the 1 hour and 47 minutes actually allowed by the vendor to the purchaser. (iii) The proper formulation of the implied term 69.The vendor's approach cannot be accepted. As indicated above, the necessity for implying a reasonable time qualification on the operation of Clause 37 arises as a matter of business efficacy and not, as Mr Griffiths suggests, because such a term is an incident of the relevant type of contract. But even if the implied term were to be approached on the latter basis, it is a mis-characterisation to say that the relevant contract is one for the payment of money, ignoring the obvious fact that it is a contract for the sale and purchase of a shop. Mr Griffiths' reliance on the cases involving contracts for the repayment of debts due on demand and their adoption of a narrow "mechanics of payment" test rests on this mis-characterisation and is fallacious. 70.The contract is one for the sale and purchase of property in Hong Kong. In assessing what constitutes a reasonable period for present purposes, the court takes into account all matters relevant to completing such a contract which both parties are, or may objectively be taken to be, aware of at the time of making the contract. The time which the vendor must allow is the time reasonably required by the purchaser to perform its obligations in relation to such completion, in the ordinary course of business. 71.Thus, while there may be rare possible exceptions, one may assume generally that purchasers will rely on mortgage finance from a bank or some other financial institution and will need the assistance of solicitors in respect of title and the other legalities of the transaction. A vendor would need to have good reason to approach the transaction making any other assumption. It follows that an objective consideration of the steps a purchaser is likely to have to take in completing the contract must include any necessary dealings with its bankers and solicitors. 72.To take the bankers first, it is right to accept, as the parties agree, that one approaches the question of reasonable time assuming that the purchaser has previously secured its banker's commitment to any needed finance. This is so since the implied term relates to the time needed for completion and arranging finance is properly regarded as preceding, rather than part of, that completion process. On the other hand, one must realistically factor in a reasonable period to enable the purchaser to apply for a draw down of its loan and for the purchaser's bankers to go through the procedures followed by them in the ordinary course, involving any final checks on the relevant documents, credit authorisations, and so forth, before allowing the balance of the loan to be drawn by the purchaser. The bank is, after all, likely to be lending a substantial sum on the security of the property. It is therefore quite unreal to pare away these commercially essential steps and to postulate that the time needed for the purchaser's completion is limited to the few minutes required for signing cheques or drawing up cashier orders. 73.Similarly, a "mechanics of payment" test ignores the essential role to be played by the purchaser's solicitors in effecting completion on the purchaser's behalf, particularly where, as in the present case, the Hong Kong method of completion is to be adopted. 74.Plainly, a vendor giving a split cheque direction must make reasonable allowance for the purchaser's solicitors' performance of their duties in relation to the completion. The evidence in the present case indicated that it was usual, after issue of any cashier orders, for the instruments to be collected from the bank and checked by the purchaser's solicitors before they were forwarded to the vendor. As Mr Fok pointed out, input of this type by the purchaser's solicitors usually culminates in their preparation of a completion letter addressed to the vendor's solicitors. The letter generally encloses and lists the financial instruments drawn in accordance with any split cheque direction, as well as the Assignment engrossed for execution. It also sets out the undertakings required from the vendor's solicitors, makes proposals as to the purchaser's taking possession of the property and, subject to the stipulated conditions, authorises the vendor's solicitors to release the monies to their clients. The completion letter itself no doubt involves, in part, use of standard clauses, however, its issue is preceded by the exercise of professional care and skill in relation to the particular transaction in question. 75.Reasonable allowance should also be made for the time needed for delivery of the payment instruments and accompanying documents by hand to the agreed venue for completion, taking into account any actual notice of a possible requirement for an unusually long or time-consuming journey. At the hearing, there was discussion of the time needed to go from the bank branch issuing the cashier orders to the vendor's solicitors' premises. However, as indicated above, in the ordinary course, it is more likely to involve travel from the offices of the purchaser's solicitors to those of the vendor's solicitors as the former will usually first have collected and checked the bank instruments before sending them on. On the facts, was the vendor in breach and if so, did this cause the purchaser to miss the completion deadline? 76.The second and third issues identified above may be dealt with together. Applying the approach discussed above to the facts as found, there can be no doubt that in giving the split cheque direction at 11:13 am, the vendor failed to allow the purchaser a reasonable time to comply before completion was due. 77.The material events, which are not in dispute, may be summarised as follows :-
78.The purchaser's solicitors cannot be said to have been in any way dilatory in reacting to the split cheque direction once it was received.
79.The attack mounted by Mr Griffiths focussed on the 48 minutes or so which the bank's officers had taken to verify the documentation before issuing the cashier orders. He argued, on the basis of his "mechanics of payment" test, that all of those checks should have been done in advance, so that no allowance for the process of verification ought to be made in assessing "reasonable time" for the purposes of the implied term. As indicated above, that is an unacceptable approach. A purchaser cannot be expected to procure its mortgagee bank to authorise a draw down until after the relevant documents have been checked in accordance with the bank's usual procedures. It is quite unreasonable not to factor in a time allowance for this process. 80.The assessment of reasonable time also takes account of any terms of the contract of sale and purchase which may throw light on the question. In the present case, Clause 3 provides for completion within a three hour period, stipulating that completion was to take place "between the hours of 10:00 am and 1:00 pm" on 2 September. It is therefore a clause which envisages that the purchaser might wish to offer to complete by tendering the balance from 10:00 am onwards. Clause 3 forms part of the machinery of completion and is a powerful indication that the parties must have intended that any split cheque direction ought reasonably to be given in sufficient time to allow the parties the full benefit of the entire completion period. 81.In the present case, the vendor did not give the direction until more than one-third of the Clause 3 completion period had already gone by. The purchaser would inevitably require time after receipt of the direction to try to comply with it. Accordingly, giving the direction at 11:13 am necessarily deprived the purchaser of at least a very large proportion of the completion period that had been expressly agreed. This provides strong support for the conclusion that the time allowed by the vendor in this case was not reasonable. 82.Turning to causation, the purchaser's inability to tender completion by 1:00 pm was plainly due to the vendor's breach of the implied term. The direction faxed at 11:13 am simply did not leave enough time to enable the purchaser's solicitors to draw down the completion monies from the bank and to get the cashier orders and other documents to the vendor's solicitors in the ordinary course of business. Indeed, the purchaser's solicitors had been prepared to depart from their usual procedure of having the cashier orders collected, brought back to the office and checked before forwarding the same to the vendor's solicitors. They told the messenger to go straight to the latter's offices. But there was still not enough time to get there by 1:00 pm. As indicated above, various slips, such as that involving the wrong heading in the letter from the purchaser's solicitors to the bank, were not on the critical path to completion and did not cause any delays. The causal connection between breach and the lateness of the purchaser's tender is therefore clear. The legal consequences (i) Contract still alive 83.Although the vendor, in breach of its implied obligation, failed to give the split cheque direction in reasonable time to allow the purchaser to complete by 1:00 pm on 2 September, the contract remained on foot. Whether or not the implied term amounted to a condition of the contract so that, on its breach by the vendor, the purchaser could have elected to treat the contract as no longer binding, the purchaser did not do so. To the contrary, the purchaser decided to hold the vendor to the contract and did its best to complete by the stipulated time notwithstanding the shortness of time allowed. 84.This was a course that the purchaser was entitled to take. Even if the vendor's breach had amounted to an anticipatory breach of its obligation to complete under the contract, the purchaser elected to leave the contract on foot. The vendor remained bound by the contract. As Viscount Simon LC put it in Heyman v. Darwins Ltd [1942] AC 356, 361 :-
85.When an innocent party elects to keep a contract alive in this manner, it remains alive for the benefit of both parties: White and Carter (Councils) Ltd v. McGregor [1962] AC 413, 444. The innocent party is therefore bound to perform his obligations under the contract. In Fercometal SARL v. Mediterranean Shipping Co SA [1989] 1 AC 788 at 805, Lord Ackner stated the principle as follows :-
86.The purchaser in the present case therefore faces the potential argument that, notwithstanding the vendor's breach, the purchaser, having affirmed the contract, remained bound to complete no later than 1:00 pm on 2 September by virtue of Clause 3 and that, time being of the essence under Clause 12, the vendor became entitled to rescind and to forfeit the deposits since the deadline was missed. In other words, it could be said that having elected to affirm the contract, the purchaser subsequently failed to render due performance, justifying the vendor's decision to rescind the contract and to forfeit the deposits. 87.However, the statement of principle by Lord Ackner in Fercometal cited above was expressed in reference to an argument that, when one party (the guilty party) repudiates his obligations under a contract and the other party (the innocent party) does not accept the repudiation and affirms the continued existence of the contract, the innocent party "is absolved from tendering further performance under the contract while the repudiatory attitude is maintained." (at 801). His Lordship rejected that argument (at 805). But he was not then dealing with the effect of the guilty party's conduct on that party's entitlement to insist on legal rights to which, but for its conduct, it would have been entitled under the terms of the contract: see Foran v. Wight (1989) 168 CLR 385. Thus, in reference to that question, his Lordship went on to say (at 805) :-
88.In Heyman v. Darwins Ltd [1942] AC 356 Viscount Simon LC, while stressing that an unaccepted repudiation generally means that the contract remains alive for the benefit of both parties, said (at 361) :-
89.But the fault of the guilty party may excuse the non-performance by the innocent party of an obligation that would otherwise be binding on him. Fry on Specific Performance (6th ed 1921 §941), citing Hotham v. East India Co (1787) 1 TR 638; 99 ER 1295, states that "non-performance by the plaintiff [is] excused when that has resulted from the neglect or default of the defendant." 90.In the present case, it is necessary to determine the effect of the vendor's failure to give the split cheque direction in reasonable time on the right to rescind the contract for the late tender of the purchase price - a right to which, but for that failure, the vendor would have been entitled by reason of clause 12 of the contract. (ii) The "prevention principle" 91.The relevant circumstances are that the right to rescind asserted by the vendor rests on the lateness of the purchaser's tender of the balance, which lateness was the direct consequence of the vendor's own failure, in breach of the implied term, to give the split cheque direction in reasonable time. These facts bring into play rules derived from the long-established legal principle that a person is not permitted to take advantage of his own wrong. 92.A nineteenth century example of the principle's operation can be found in Rede v. Farr (1817) 6 M&S 121, where the parties entered into a 12 year lease that contained a proviso stating that if the rent were to be unpaid for 40 days after it was due :-
93.In New Zealand Shipping Co Ltd v. Société des Ateliers et Chantiers de France [1919] AC 1, the principle was invoked but found inapplicable on the facts.
(iii) The need for a relevant breach 94.In refining the principle's operation in the contractual context, the authorities have stressed two limitations. First, it is necessary to show the relevant party's "wrong" involves his breach of the contract in respect of an obligation owed to the other party.
(iv) The need for a causal connection 95.The second limitation on the operation of the principle is a causation requirement. It is necessary to show that the contractual rights or benefits which the party in question is seeking to assert or claim arise as a direct consequence of that party's prior breach. This requirement appears from some of the authorities quoted above. It has also been emphasised in certain decisions of the New South Wales Court of Appeal.
(v) How the principle is given effect 96.On the basis of the foregoing discussion, it seems clear, based on the underlying principle that a person is not permitted to take advantage of his own wrong, that a contractual party who is in breach of an obligation owed to the other party, will be prevented from asserting rights or claiming benefits which arise in consequence of his breach. The cases also show that where this "prevention principle" applies, it may be given effect in different ways. 97.In many cases, it will be appropriate to implement it as a substantive principle of law that precludes the wrongdoer from taking advantage of his own wrong, whatever the contract may say and however clearly the contract may appear to confer on the wrongdoer an unqualified right to enjoy such advantages. Cases like Rede v. Farr and the New Zealand Shipping case, may be considered examples. 98.In other cases, where appropriate, the courts give effect to the principle as one of construction, holding that the contractual terms with which they are concerned must be construed by applying the principle as a canon or presumption of construction: see Lewison, The Interpretation of Contracts, 2nd Ed (Sweet & Maxwell), §6.08.
99.Another possible manifestation of the underlying principle may be detected in cases where one party's conduct is the cause of the other party's failure to meet a condition precedent. Here, the principle has in some cases been given effect by deeming the condition to have been met.
(iv) Giving the principle effect in the present case 100.In deciding how the prevention principle is to be given effect in any particular case, it is necessary to identify with some precision, the relevant breach, the factual consequences flowing from such breach and what, if any, advantage the contract-breaker seeks to take on the basis of such consequences. The principle aims specifically to deny the contract-breaker those particular advantages. 101.There is no doubt that the prevention principle applies in the present case. The vendor was in breach of a duty owed to the purchaser to provide a split cheque direction a reasonable time before completion was due. This breach was the direct cause of the purchaser's failure to meet the deadline stipulated by Clause 3. It was in reliance on this late tender, a consequence of its own breach, that the vendor sought to invoke Clause 12, the time of the essence clause, as the basis for treating the contract as rescinded and for forfeiting the deposits. 102.The vendor's desired advantage was therefore its invocation of Clause 12 on the basis of the late tender caused by its breach. The prevention principle accordingly operates to prevent reliance on that clause. It follows that the purchaser's tender at 1:06 pm on 2 September is in law unaffected by any time of the essence provision in respect of the 1:00 pm deadline stipulated in Clause 3. 103.On this footing, by virtue of section 11 of the Law Amendment and Reform (Consolidation) Ordinance, Cap 23, the court applies the equitable rules on time stipulations and does not treat the purchaser's failure to meet the Clause 3 deadline as repudiatory of itself. Provided that the purchaser completes, or shows that he is ready and willing to complete, within a reasonable time after the stipulated deadline, equity is willing to grant specific performance and, as an incident thereof, to relieve against the consequences of failure to meet the strict time limit, where it can do so without injustice: Stickney v. Keeble [1915] AC 386, 415-6; Howe v. Smith (1884) 27 Ch D 89, 103; Rightside Properties Ltd v. Gray [1975] Ch 72, 83. 104.Tender of the balance six minutes after the time stipulated was obviously tender within a reasonable time. No injustice to the vendor arises. It follows that on the facts of the present case, in the events which took place, the vendor was not entitled to treat failure to meet the 1:00 pm deadline as repudiatory. The vendor was bound to complete at 1:06 pm when the balance of the purchase price was tendered. Its refusal to accept the tender was itself a repudiatory breach of the contract. 105.One may note that in the present case, the operation of the prevention principle is consistent with Clause 13(a) of the contract which expressly qualifies the vendor's right to rescind, to forfeit the deposits, etc, by reason of the purchaser's failure to complete on time. Such rights are only so exercisable if the purchaser's failure occurs "for any cause other than the default of the Vendor." The corollary is that if the purchaser's delay in completion is due to the default of the vendor the vendor is not entitled to treat the contract as repudiated or to take any consequential steps. 106.The appeal by the vendor must therefore be dismissed. Although this conclusion rests on grounds different from those adopted by the Court of Appeal, there is no reason to interfere with that court's orders in the purchaser's favour for the return of the deposits, damages, interest and costs. 107.I would deal with the costs in this Court in the manner proposed by Mr Justice Bokhary PJ. Mr Justice Nazareth NPJ: 108.I agree with the judgment of Mr Justice Ribeiro PJ. Sir Gerard Brennan NPJ: 109.I agree with the judgment of Mr Justice Ribeiro PJ. Mr Justice Bokhary PJ: 110.We unanimously dismiss this appeal and affirm the Court of Appeal's orders, including those as to the costs in the courts below. As to the costs in this Court, we make an order nisi for costs in favour of the Purchaser and the Solicitors against the Confirmor, such order nisi to become absolute within 21 days if no written application for some other order as to costs is made within that time. As to the position if such an application is made, we order that the matter be dealt with on written submissions for which procedural directions should be sought from the Registrar if the parties are unable to agree on procedural matters in that regard.
Representation: Mr John Griffiths SC and Mr Benjamin Chain (instructed by Messrs Iu, Lai & Li) for the appellant Mr Edward Chan SC and Mr Wallace Cheung (instructed by Messrs Bosco Tso & Partners) for the 1st respondent Mr Joseph Fok SC and Mr Russell Coleman (instructed by Messrs Deacons) for the 2nd respondent Mr Kenneth CK Chow for the Official Receiver |
Cases cited in this judgment
Other judgments that cite this case