Shine Empire Ltd v. The Incorporated Owners of San Po Kong Mansion and Others
Read the full judgment text of HCA 3444/2001 on BabelCite. This High Court CFI judgment was delivered on 28 January 2011.
1. The Plaintiff (“P”) was the owner of the premises known as Roofs of San Po Kong Mansion (the “Roofs”).
Cited by 10 cases · Cites 6 cases
|
HCA 3444/2001 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE ACTION NO. 3444 OF 2001
BETWEEN
Coram : Before Master R. Lai in Court Date of Hearing : 22 November 2010 Date of Handing Down Decision : 28 January 2011 ___________________________ ASSESSMENT OF DAMAGES ___________________________ Background 1.The Plaintiff (“P”) was the owner of the premises known as Roofs of San Po Kong Mansion (the “Roofs”). 2.The 1st Defendant (“D1”) was the Incorporated Owners of San Po Kong Mansion. 3.The 2nd to 6th Defendants were telecommunication companies. 4.This is an action of P for possession of the Roofs and damages and/or mesne profits against all the Defendants. 5.At the material times since 1995, D1 had rented and/or granted licence to the 2nd to 6th Defendants for their installation of aerials and transmitters on the Roofs at monthly licence fees. 6.P issued the Writ herein on 1 August 2001. 7.On 20 October 2004, Mr. Justice Sakhrani ordered,inter alia, thatall issues on liability between P andD1 be tried first. 8.Deputy High Court Judge Mayo gave judgment on liability for P against D1 on 3 December 2004. D1’s appeals to the Court of Appeal and the Court of Final Appeal were dismissed. The Court of Final Appeal dismissed the appeal on 30 April 2007 and handed down its judgment on 31 May 2007 (the “CFA Judgment”). 9.On 13 October 2008, P took out summons for summary judgment against the 2nd to 6th Defendant. On 10 November 2008, interlocutory judgment with damages to be assessed was entered against the 2nd to 6th Defendants. The 2nd Defendant and P subsequently reached settlement on damages. 10.This is the assessment of damages hearing in respect of P’s claims against the 3rd to 6th Defendant (“D3 to D6”). 11.The quantum of damages has been agreed between P and D3 to D6 before the assessment hearing. Thesolicitors of the partiesinformed the Court of the agreed quantum by a joint letter dated 16 November 2010 (the “Settlement Letter”) and submitted a signed consent order dated 22 November 2010 (the “Signed Order”) to Court at the hearing for approval. 12.P and the 3rd Defendant (“D3”) agreed that D3 would pay damages to P for D3’s installation of aerials and transmitters on the Roofs from 1 December 1996 to 30 November 2004. The quantum of damages as agreed by P and D3is as follows:
13.P and the 4th Defendant (“D4”) agreed that D4 would pay damages to P for D4’s installation of aerials and transmitters on the Roofs from 16 April 1996 to 3 December 2004 and from 1 November 2006 to 30 April 2007. The quantum of damages as agreed by P and D4 is as follows:
14.P and the 5th Defendant (“D5”) agreed that D5 would pay damages to P for D5’s installation of aerials and transmitters on the Roofs from 1 May 1997 to 18 January 2005. The quantum of damages as agreed by P and D5 is as follows:
15.P and the 6th Defendant (“D6”) agreed that D6 would pay damages to P for D6’s installation of aerials and transmitters on the Roofs from 6 April 1995 to 5 April 2007. The quantum of damages as agreed by P and D6 is as follows:
16.In the Settlement Letter, the parties agreed that the due date of payment of each agreed monthly rental was deemed and agreed and ought to be paid on the first day of each corresponding calendar month. 17.P and D3 to D6 also agreed that the costs of this action including the hearing for assessment of damages and those costs reserved between P and D3 to D6 be to P to be taxed on party and party basis if not agreed. 18.The only outstanding issue before me is interest on the agreed quantum. The parties agreed that post judgment interest on the agreed quantum is payable at judgment rate from the date of judgment until payment. The dispute between the parties is only on pre-judgment interest. 19.P claims interest pursuant to section 48 of the High Court Ordinance (Cap. 4). The questions before me are whether interest shall be paid by D3 to D6 on the agreed quantum to P? If so, for which period of time and at which rate? 20.Miss Lok representing P submits that interest shall be awarded toP against D3 to D6 on the agreed monthly rental from the first day of their admitted trespass at 1% above the best lending rate of Hang Seng Bank, alternatively at judgment rate. 21.Mr. Yip representing D3 to D6 submits that P is not entitled to pre-judgment interest. Alternatively, there shall be no interest to P for the period before issuance of the Writ and also for the period from 30 April 2007 to 22 November 2010. As to the period from 1 August 2001 (i.e. the date of the Writ) to 30 April 2007 (i.e. the date when D1’s appeal was dismissed by the Court of Final Appeal), Mr. Yip submits that the appropriate rate of interest is the prime rate. Alternatively, Mr. Yip argues that interest shall be awarded at half of the relevant judgment rates on the agreed monthly rental from the respective starting dates of use of the Roofs by D3 to D6, to the date of judgment on damages. Whether interest shall be paid 22.P claims interest under section 48 of the High Court Ordinance (Cap. 4). Section 48(1) of the High Court Ordinance provides that:
23.Mr. Yip contends that no pre-judgment interest shall be awarded to P on the following grounds:
24.The first argument of Mr. Yip touches on jurisdiction of the Court to award pre-judgment interest in this case. The second argument is on whether the Court shall exercise discretion to award pre-judgment interest to P in this case. Jurisdiction of the Court to award pre-judgment interest in this case 25.Mr. Yip submits that a party claiming interest must plead specifically any claim for interest under section 48 of the High Court Ordinance or otherwise. If not, the court would not award pre-judgment interest to the plaintiff. Mr. Yip refers me to Bank of China v Sze Wang (unrep., HCMP 3825/2001, 23 December 2003, Temporary Deputy Registrar Thomas So) which was a proceeding commenced by originating summons. The plaintiff claimed pre-judgment interest under section 48 of the High Court Ordinance. The learned Temporary Deputy Registrar stated in para. 29 of his judgment that “I fail to see any such claim pleaded in the Originating Summons. Because of that I refused to award any pre-judgment interest to the Plaintiff.” 26.A claim for interest under section 48 of the High Court Ordinance need only be included in the prayer to a pleading (see Hong Kong Civil Procedure 2011, para. 18/8/15). In Bank of China v Sze Wang the pre-judgment interest claim was not pleaded in the originating summons. 27.In this action, P pleaded in prayer (e) of the Re-Amended Statement of Claim – “interest against all Defendants”. There is no reference to any statute or statutory provision at which interest is claimed. Mr. Yip has fairly pointed out that in Grandyield Knitters Ltd v MBE Engineering Ltd [2002] 2 HKLRD 88 the Court of Appeal held that the plaintiff’s failure, when pleading its case to interest, to make specific reference to the statutory provisions (in that case the District Ordinance) had not prejudiced the defendant and the Court of Appeal upheld the Judge’s award of interest. 28.Mr. Yip argues that even if P can rely on Grandyield Knitters Ltd v MBE Engineering Ltd to argue that D3 to D6 had notice of P’s intention to seek interest, it is still insufficient in this case in view of the substantial amount of interest involved. 29.Miss Lok submits that the amount of interest is not a relevant consideration when the Court exercises its discretion to award interest. 30.In Grandyield Knitters Ltd v MBE Engineering Ltd the relevant prayer read as follows:
31.The defendant in Grandyield Knitters Ltd v MBE Engineering Ltd contended that the court had no jurisdiction to award interest, whether pre-judgment or post-judgment, because the plaintiff failed to “specifically pleaded” the relevant statutory provisions under which interest was claimed. 32.In giving her judgment in Grandyield Knitters Ltd v MBE Engineering Ltd Le Pichon JA said in paras. 16 and 17 that
33.In this case, unlike Bank of China v Sze Wang where there was no claim for interest, there is a claim for “interest against all Defendants”. I find that P has in prayer (e) of the Re-Amended Statement of Claim given fair notice to D3 to D6 of its intention to seek interest. 34.P’s claims against D3 to D6 are for wrongful occupation of part of the Roofs. I have invited the parties to address me on the English case of Whitwham v Westminster Brymbo Co [1896] 1 Ch. 894 in which Chitty J. refused to award interest upon the damages given for wrongful user of land when he said (at 899) “in regard to interest claimed, I think that all interest ought to be excluded from the computation of damage. To give interest would be to treat the plaintiffs as having invested their damages at interest in the hands of the defendants.” 35.Mr. Yip refers me to Glenealy Mansion Limited v Norman Persaud (unrep., CACV 60/1986, 4 July 1986) in which the Hong Kong Court of Appeal followed the decision of Whitwham v Westminster Brymbo Co and refused to award interest on mesne profits 36.Miss Lok submits that P’s claim herein under section 48 of the High Court Ordinance is a claim for interest on damages and not interest as damages in Whitwham v Westminster Brymbo Co. Miss Lok refers me to Yim Kan v Tsang Siu Shing (unrep., HCMP 1804/1998, 21 August 2000, Master S. Cheung) when pre-judgment interest at judgment rate on mesne profits was awarded to the plaintiff in that case. 37.It is noted that Whitwham v Westminster Brymbo Co was decided before statutory intervention in England on interest claim first by section 3(1) of the Law Reform (Miscellaneous Provisions) Act 1934 and later by adding section 35A to the Supreme Court Act 1981 through section 15(1) and Schedule I Part I of the Administration of Justice Act 1982. 38.Statutory interest was introduced to Hong Kong by the Law Reform (Interest on Claims and Judgments) Ordinance 1970 when section 30A was added to the then Supreme Court Ordinance. Section 30A(1) of the 1970 Ordinance which concerns us read as follows:
39.When the Supreme Court Ordinance was re-enacted in 1975, provision for statutory interest became section 48 of the Ordinance. Section 48(1) of the 1975 Ordinance reads as follows:
40.The current version of section 48(1) of the High Court Ordinance set out in paragraph 22 above was introduced by the Supreme Court (Amendment) Ordinance 1987 except that the reference to “the Court of First Instance” in the current version was then read as “the High Court”. This was changed in 1998. 41.It can be seen that statutory interest has been available since 1970. It is also noted that in 1986 when Glenealy Mansion Limited v Norman Persaud was decided, the Court of Appeal did not allow interest on mesne profits citing the authority of Whitwham v Westminster Brymbo Co. 42.When the Court of Appeal dealt with interest on mesne profits in Glenealy Mansion Limited v Norman Persaud, their Lordship made no reference to section 48 of the then Supreme Court Ordinance which provided for statutory interest. Instead, their Lordship only referred to Whitwham v Westminster Brymbo Co. 43.In Whitwham v Westminster Brymbo Co, interest was excluded “from the computation of damage”. I agree with Miss Lok that Whitwham v Westminster Brymbo Co is a claim for interest as damages and is different from a claim for interest on damages under statutory provision. 44.As Lord Nicholls of Birkenhead said in Sempra Metals Ltd v Inland Revenue Commissioners [2008] A.C. 561 at 601 (para. 97): “If a party chooses not to prove his interest losses the remedy provided by the law is to be found in the statutory provisions.” 45.I am satisfied that this Court has jurisdiction under section 48 of the High Court Ordinance to award pre-judgment interest to P on the agreed damages from the respective dates when the cause of action against each of D3 to D6 arose. The period during which interest is payable and the interest rate are at the discretion of the Court. Whether discretion shall be exercised in favour of P in this case 46.Award of interest under section 48 of the High Court Ordinance is at the discretion of the Court. The Court shall exercise the discretion judicially. 47.In B.P. Exploration (Libya) v Hunt (No. 2) [1979] 1 W.L.R. 783 Robert Goff J. stated at 845 that: “The fundamental principle is that interest is not awarded as a punishment, but simply because the plaintiff has been deprived of the use of the money which was due to him.” 48.Mr. Yip submits that this is not an ordinary trespass case. D3 to D6 had entered into licence agreements with D1 for installation of their aerials and transmitters at the Roofs, mistakenly believing that D1 had the right to grant them the licence to use the Roofs. D3 to D6 had paid licence fees to D1. Mr. Yip submits that there was no unjust enrichment in this case on the parts of D3 to D6. 49.Mr. Yip further submits that there is no evidence that the Roofs had been in any commercial use at and before the material times. But for the installation of the aerials and transmitters, the Roofs were not generating any income to P. Mr. Yip submits that there is also no evidence that P has incurred any interest charges as a result of the non-receipt of the licence fees. 50.D3 to D6 had actually paid licence fees to D1 for their use of the Roofs. D3 to D6 will have their respective remedies against D1 for such payments which will no doubt include the element of interest. 51.The mistake of D3 to D6 in making payment to D1 was caused by their failure to properly investigate the title of D1 to the Roofs and D1’s misrepresentation as owner of the Roofs. D3 to D6 only have themselves and D1 to blame for making such payments to D1. But for such mistake, D3 to D6 should have paid licence fees to P for their use of the Roofs during the material times or they would not have received the commercial benefits of having their aerials and transmitters installed at the Roofs during the material times. 52.If the Court denies interest to P on the ground that D3 to D6 had paid licence fees to D1 and had not obtained any unjust enrichment, the following will be the two possible scenarios in the claims of D3 to D6 against D1:
53.If D3 to D6 are relieved from paying interest to P which they will otherwise have to pay but for their own mistake and the wrongful act of D1, the Court is not doing justice to P. For the above reasons, in this assessment, I shall not take into account payments paid to D1 by D3 to D6 in considering the position between P and D3 to D6. 54.Interest should generally be awarded in cases where a party has been deprived of his money in order to do justice between the parties. 55.In this case, D3 to D6 should have paid licence fees to P for their usage of the Roofs. The fact that they had paid licence fees to D1 on the mistakenly belief that D1 was the lawful owner of the Roofs shall not relieve them from their obligations to pay P. 56.P has been deprived of the money which P should have received earlier. It is only fair that P shall be compensated by payment of interest. 57.In the premises, I would exercise my discretion to award pre-judgment interest to P on damages agreed to be payable by D3 to D6. For which period of time 58.Under section 48 of the High Court Ordinance, the Court has jurisdiction to award interest for all or any part of the period between the date when the cause of action arose andthe date of judgment. 59.There is no dispute that D3 to D6 started to use the Roofs on the following dates:
60.The following facts are records of the court files or have been agreed by P and D3 to D6 through their counsel at the hearing:
61.Mr. Yip submits that P was guilty of delay in prosecuting its claims herein and there should be no interest to P before the date of the Writ (i.e. 1 August 2001) and also for the period from 30 April 2007 to 22 November 2010. Mr. Yip refers me to Mok Merla v Ocean Crown Transportation Ltd (unrep., HCPI 266/1998, 11 July 2002, Deputy High Court Judge B. Yu SC) when interest for two years was disallowed on the ground of unexplained delay of over two years. 62.The complaints of D3 to D6 on P’s pre-action delay can be summarized as follows:
63.The complaints of D3 to D6 on P’s post-action delay can be summarized as follows:
64.Miss Lok submits that P learnt about the trespass only in about 1998. P took immediate action to clarify the situation with D1 without success. P also tried to open up dialogue with the Defendants to resolve the disputes and P had continued the negotiation with D3 to D6 up to November 2010 when the parties eventually settled on the quantum of damages. 65.Miss Lok submits that it is extraordinary if a potential litigant who tried to seek settlement or alternative dispute resolution before resorting to litigation would be penalized by disallowing interest to him for the period before the date of writ. She submits that this would be directly contrary to the spirit encapsulated under Order 1A, rule 1(e) of the Rules of the High Court. 66.Miss Lok submits that after the Court of Final Appeal handed down its Judgment on 31 May 2007, P had applied to the Court on 31 December 2007 for a checklist hearing date. The matter proceeded to checklist hearing in March 2008 and P took out summary judgment application on 13 October 2008. Interlocutory judgment was granted on 10 November 2008. Miss Lok argues that D3 to D6 was still adamant in contesting their liabilities after the CFA Judgment until P’s summary judgment application in October 2008. 67.Miss Lok further submits that after interlocutory judgment was granted in November 2008, P applied in October 2009 to set down the assessment of damages hearing but the application was opposed by the 2nd to 6th Defendants on the ground that expert evidence was required. Miss Lok submits that it was the failure of D3 to D6 in complying with the Court’s directions on expert evidence which caused further delay in setting down the assessment of damages hearing until April 2010. 68.P’s case is that there is no unjustifiable delay on the part of P in this case which calls for disallowing part of the interest to P. Miss Lok refers me to The Hong Kong Electric Co Ltd v Commissioner of Rating and Valuation (unrep., LDGA 224/2004 & LDRA 356/2004, 12 April 2010) when the Lands Tribunal refused to disallow interest to the appellant in those cases on the ground that the Tribunal was not satisfied that the appellant was guilty of any unjustifiable delay. 69.In the Settlement Letter, the parties proposed that all the witness statements and the supplemental witness statements filed be adduced as evidence without calling the makers. Relying on the witness statements and supplemental witness statements filed herein, the parties have not called any witness to testify at the assessment of damages hearing. 70.In the witness statement of Kwan Daniel (“Mr. Kwan”) filed herein on 16 September 2003 on behalf of P, Mr. Kwan made the following statements:
71.It is P’s case that its representative never had any difficulty in gaining access to the Roofs and its staff frequently went up the Roofs. It is also P’s case that as early as 1996 it was aware of aerials, transmitters and associated cables being installed on the Roofs. 72.In such case, P should have discovered the installation of the aerials and transmitters by D3 to D6 at the Roofs shortly after their installation. 73.No explanation was given by P as to why it did not take up the matter with D1 until late 1998 or early 1999. Mr. Kwan’s evidence was that his staff went to the office of D1 in around late 1998 or early 1999 to make enquiries with D1. 74.In his judgment delivered herein on 3 December 2004 on the liability issues between P and D1, Deputy High Court Judge Mayo found in para. 127 that “the Plaintiff made its position clear from 27 April 1999 that it was contesting the 1st Defendant’s right to receive the licence fees in question.” 75.In this case, there has been a delay of about two years (in D5’s case) to four years (in D6’s case) before P made its position clear on 27 April 1999. Although P did not get into contact with D3 to D6 directly until later dates because D1 refused to divulge information to P, the licence fees should reasonably have been paid to P after P made its position clear on 27 April 1999. 76.In B.P. Exploration (Libya) v Hunt (No. 2) the learned judge said at 847 that: “The basic principle, is, however, that interest will be awarded from the date of loss.” 77.After considering the whole circumstances of this case, I am of the view that the date of loss for P in this case should be 27 April 1999 when P made its position clear but the licence fees were still not paid to it. In exercise of my discretion, I do not allow interest to P for the period prior to 27 April 1999 when P was aware of the installation of aerials and transmitters by D3 to D6 but did not make its position clear that it would claim fees for such usage of the Roofs. 78.After P got into contact with D3 to D6, P started discussion with them to resolve the matter. When negotiation was not successful, P issued the Writ on 1 August 2001 79.In The Hong Kong Electric Co Ltd v Commissioner of Rating and Valuation the Lands Tribunal cited with approval at para. 19(2) of its judgment the following principles stated by Jackson J in Clymore Services Ltd v Nautilus Properties Ltd [2007] BLR 452 at 460:
80.I agree with Miss Lok that P should not be penalized for its efforts to avoid litigation. I would award pre-action interest to P from 27 April 1999 to 1 August 2001. 81.After the CFA Judgment at the end of May 2007, P had been in negotiation with D3 to D6. At the same time this proceeding proceeded in the usual way. P applied for checklist at the end of December 2007. Directions were given in March 2008. Summary judgment application was taken out in October 2008. Although the matter had not been pressed on in the most efficient way, applying the aforesaid principles stated by Jackson J in Clymore Services Ltd v Nautilus Properties Ltd, I do not see gross or unjustifiable delay on the part of P in prosecuting its claim after the CFA Judgment until the interlocutory judgment against D3 to D6. 82.After the interlocutory judgment in November 2008, the proceedings were governed by Order 37 of the Rules of the High Court and automatic directions were applied. P went before the Practice Master in October 2009 seeking leave to set down the assessment of damages hearing cannot be considered as undue delay. It was the objection of the 2nd to 6th Defendants which prevent the setting down of the assessment of damages hearing in October 2009. It was the failure of D3 to D6 in complying with the expert directions which caused further delay in setting down. The Court had to imposed an unless order on 12 March 2010 to compel D3 to D6 to serve their expert report. It lies ill in the mouths of D3 to D6 to complain that P had delayed setting down of the assessment of damages hearing. 83.Although P’s claims against D3 to D6 were not concluded until more than 9 years after the Writ was issued, this was not caused by delay on the part of P. The Court had in 2004 ordered the liability issues between P and D1 to be tried first. D1 took the issues all the way to the Court of Final Appeal. It took more than two years and four months from the date of judgment of the first instance for such issues to be finally determined by the Court of Final Appeal in April 2007. In such case, I would award interest to P for the whole period from the date of Writ to the date of judgment. At which rate 84.In respect of the rate of interest, Miss Lok submits that in commercial cases, the usual interest awarded was by reference to best lending rate of commercial banks. Miss Lok refers me to Polyset Ltd v Panhandat Ltd (unrep., FACV 28/2000, 25 April 2002). 85.In the third supplemental witness statement of Mr. Kwan dated 4 November 2010, Mr. Kwan stated that P’s banker had been Hang Seng Bank and that P had been able to borrow from Hang Seng Bank at the rate of about 1% over prime rate. Miss Lok submits that 1% above the best lending rate quoted by Hang Seng Bank, P’s banker, is appropriate. 86.Mr. Yip submits that interest awarded shall be at prime rate or at half of the judgment rate at relevant times. 87.In Polyset Ltd v Panhandat Ltd Mr. Justice Bokhary PJ stated in para. 13 of his judgment that: “To compensate a successful plaintiff for being kept out of his money, the general practice in Hong Kong has, at least since 1984, been to award interest reflecting the theoretical costs to the plaintiff of borrowing the sums withheld. This is a rate taken to be prime plus 1% unless the evidence in a particular case makes adoption of another rate appropriate: see Komala Deccof & Co SA v Perusahaan Pertambangan Minyak Dan Gas Bumi Negara (Pertamina) [1984] HKLR 219.” 88.I do not see circumstances in this case justifying departure from this general practice. I would award interest to P at the rate of 1% above the best lending rate quoted by the Hang Seng Bank from time to time. Conclusion 89.By consent of the parties, I assess the damages payable to P by D3 to D6 in the sums set out in the Signed Order. Particulars of the agreed damages have been set out in paragraphs 12 to 15 above. 90.I award pre-judgment interest to P on the agreed damages for the period from 27 April 1999 until judgment at 1% above the best lending rate quoted by the Hang Seng Bank from time to time. 91.Each of D3 to D6 shall pay interest to P on the respective amount of agreed assessed rental deemed and agreed to be payable on or before 27 April 1999 by each of them in accordance with the Settlement Letter from 27 April 1999 until judgment at the aforesaid interest rate. 92.Each of D3 to D6 shall pay interest at the same rate to P on the respective amount of agreed assessed monthly rental deemed and agreed to be payable after 27 April 1999 by each of them from the respective due date of each monthly payment deemed and agreed in accordance with the Settlement Letter until judgment. As D4 had made a part payment of $60,000.00 to P on 28 January 2008, interest payable on that sum shall cease on 28 January 2008. 93.By consent of the parties as set out in the Signed Order, I also order that the costs of this action (including the hearing for the assessment of damages and those costs reserved) between P and D3 to D6 be to P to be taxed on party and party basis if not agreed.
Miss Frances Lok, instructed by Messrs Huen & Partners, for the Plaintiff. Mr. Timmy C.H. Yip, instructed jointly by Messrs Gallant Y.T. Ho & Co., Messrs Chan, Wong & Lam, and Messrs Kenneth C.C. Man & Co. for the 3rd to 6th Defendants. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCA 3444/2001