|
LDCS5000 / 2012
IN THE LANDS TRIBUNAL OF THE
HONG KONG SPECIAL ADMINISTRATIVE REGION
LAND COMPULSORY SALE APPLICATION NO. 5000 OF 2012
______________
BETWEEN
|
EVERSOUND INVESTMENTS LIMITED |
Applicant |
|
and |
|
|
Tung Chun Hung (董鎮洪)
|
1stRespondent
(discontinued) |
|
Li Yeung and Helen Wai Maughan |
2nd Respondents
(discontinued) |
|
Ng Oi Mui (吳愛梅), Cheng Kam Fai Michael (鄭錦輝) and Cheng Kam Pui (鄭錦培) |
3rd Respondents
(discontinued) |
|
Winning Flag Holdings Inc |
4th Respondent
(discontinued)
|
|
Chung Ming Fai (鍾明輝)
and Chung Ching Man (鍾正文)
|
5th Respondents |
|
Star Keen Limited
(星建有限公司) |
6th Respondent
(discontinued) |
______________
| Before: Mr. Kenneth KWOK,
Temporary Member of the Lands Tribunal |
| Date of Hearing: 21 January 2013 |
| Date of Judgment: 23 January 2013 |
_______________
J U D G M E N T
_______________
Background
1.This is an application for compulsory sale of all the undivided shares in Section H of Kowloon Marine Lot No. 52 (“the Lot”), known as Nos. 11 & 13 Wan King Street and Nos. 12 & 14 Wan Shun Street, Kowloon (“the Building”), for the purposes of the redevelopment of the Lot pursuant to s. 3(1) of the Land (Compulsory Sale for Redevelopment) Ordinance, Cap. 545 (“the Ordinance”).
2.There is erected on the Lot a 9 storey composite building served by 2 common staircases. Altogether there are 37 units in the Building and each unit is allotted one share with a total of 37 undivided shares for the Building and the Lot. The Building is part of Block A of Nos. 18 & 20 Wan On Street, Nos. 1, 3, 5, 7, 9, 11 & 13 Wan King Street and Nos. 2, 4, 6, 8, 10, 12 & 14 Wan Shun Street, Kowloon Hong Kong (“Block A”).
3.The Applicantcommenced the present proceedings on 12th January 2012. At that time, the 1st Respondent is the registered owner of Ground Floor, No. 11 Wan King Street (formerly known as the Ground Floor of House No. 13 Block A); the 2nd Respondents, Ground Floor (formerly known as the Ground Floor of House No. 14 Block A), No. 12 Wan Shun Street, Kowloon; the 3rd Respondents, 2nd Floor, (formerly 2nd Floor of House No. 16 Block A), No. 14 Wan Shun Street, Kowloon; the 4th Respondent, 6th Floor, (formerly 6th Floor of House No. 14 Block A), No. 12 Wan Shun Street, Kowloon; the 5th Respondents, roof (formerly roof floor of House Nos. 13 & 15 Wan King Street, Nos. 14 & 16 Wan Shun Street), Nos. 11 & 13 Wan King Street, Nos. 12 & 14 Wan Shun Street, Kowloon; and the 6th Respondent, 1st Floor (formerly 1st Floor of House No. 13 Block A), No. 11 Wan King Street, Kowloon. The Applicant owns the remaining units in the Building and 31 equal undivided 37th parts or shares in the Lot representing 83.78%. The Applicant contends that it is entitled to make the present application by virtue of s. 3(2) of the Ordinance.
4.Since then, the Applicant has acquired the interests of the 1st Respondent, the 2nd Respondents, the 3rd Respondents, the 4th Respondent and the 6th Respondent and has discontinued the application against them.
5.As at the date of hearing, the 5th Respondents own 1 share in the Roof of the Building ("the 5th Respondents’ premises"). All the remaining shares and units in the Building and the Lot are owned by the Applicant. Thus, the percentage of the undivided shares owned by the Applicant in the Lot is 97.30%.
6.The 5th Respondents did not file any Notice of Opposition.
7.Before the hearing, the solicitors for the Applicant have duly served all the papers of the Application to the address of the 5th Respondents made known to the solicitors. The 5th Respondents were absent at the hearing and did not file any response or expert report.
8.In view of the absence of the 5th Respondents, Mr. C.Y. Li SC, Counsel for the Applicant, simply called the Applicant’s witnesses to confirm their evidence. The Applicant contends that all the requirements of the Ordinance have been satisfied and asks for an order for sale in terms of the draft order submitted. The Applicant also asks there be no order as to costs.
Section 3 of the Ordinance – Ownership of the Applicant
9.Section 3(1) of the Ordinance requires the Applicant to have not less than 90% of the undivided shares in a lot before it can make an application.
10.Section 3(5) of the Ordinance also states that the Chief Executive in Council may, by notice in the Gazette, specify a percentage lower than the percentage mentioned in subsection (1) in respect of a lot belonging to a class of lots specified in the notice.
11.Pursuant to Section 3(5) of the Ordinance, the notice was gazetted on 22 January 2010 and tabled at the Legislative Council meeting on 27 January 2010. It came into operation on 1 April 2010. Section 3 of the notice lowered the threshold for compulsory sale from 90% to 80%. Section 4(1)(b) of the notice specified one of the classes for the purposes of Section 3, as “a lot with each of the building erected on the lot issued with an occupation permit at least 50 years before the relevant date (which is the date of the application)”. The occupation permit of the Building was issued on 4 February 1960, which is more than 51 years before the date of application. The Building therefore is covered by the notice and the applicable percentage is 80%.
12.As at the date of application, the Applicant owns83.78% of the shares in the Lot. The Applicant is clearly entitled to make the application.
Section 4(2) of the Ordinance - Justification and Reasonable Steps
13.In determining the Applicant’s application, s. 4(2) of the Ordinance requires me not to make an order for sale unless, after hearing the objections, if any, of the 5th Respondents, I am satisfied that:
(a) the redevelopment of the Lot is justified due to the age or state of repair of the Building; and
(b) the Applicant has taken reasonable steps to acquire all the undivided shares in the Lot (including negotiating for the purchase of the undivided share owned by the 5th Respondents on terms that are fair and reasonable).
14.Mr. Li submits that the relevant tests on age and state of repair were set out in Top Sail International Ltd v. Cheng Kai Ming, executor of the estate of Chan Hue also known as Chan Sum Hiu, deceased (LDCS 18000/2010, 15 November 2011, unreported). Mr. Li further submits that the tests were also applied recently in the decision of this Tribunal in Champion Success Limited & Another v. Leung Lai Lai the administratrix of the estate of Lai Yin King Deceased & Others((LDCS 41000/2011, 16 January 2013, unreported). I am of the view that “the age” and “state of repair” are two separate grounds and even though there may be considerations common to both, I should still consider them separately. Since Mr. Li relies primarily on “state of repair”, I shall deal with this ground first.
State of Repair of the Building
15.The Applicant’s expert, Mr Raymond Chan of Raymond Chan Surveyors Limited (“Mr R Chan”), in his Condition Survey Report, gives his opinion, inter alia, that:
(a) The Building is amongst the oldest buildings in the neighbourhood.
(b) The overall condition of the steel railing at Roof is fair. Unauthorized structures are erected on portions of the Roof.The condition of the canton tiles is poor. Irregular cracks are commonly found and most of the canton tiles are debonded from the roof slab. The waterproofing layers under the canton tiles are exposed at isolated locations. The external walls and roof of staircase hood are finished with cement sand render and paint. Rust stains are commonly foundon the finishes. Besides, sign of water seepage is noted on the ceiling soffit of the staircase hood.
(c) Based on our visual inspection to the external walls with the aid of binocular, the following defects are observed:
(i) The condition of render and paint of the external walls is fair.
(ii) Unauthorized building works, such as drying racks, antenna, air-conditioning supporting frames, corrugated canopies in rusting and dilapidated condition are noted at the external walls.
(iii) As the Building was built in the 1950’s, Mr R Chan suspects that the corrugated canopies commonly installed on the top of windows may contain asbestos materials which were widely used at that time for thermal insulation.
(iv) Unauthorized openings on external wall for shop fronts are commonly found for the units on the Ground Floor.
(v) Unauthorized enclosure of window openings is commonly found on the re-entrant of each floor facing Wan King Street and Wan Shun Street.
(d) Based on Mr R Chan’s visual inspection with the aid of binocular, the following defects are observed at the light wells:
(i) The condition of render and paint of the two light wells are fair.
(ii) Unauthorized building works like corrugated canopies in rusting and dilapidated condition, air conditioning supporting frames and drying racks are noted at the light well.
(iii) Unauthorized structuresare erected at the light wells.
(iv) As the Building was built in 1950’s, Mr R Chan suspects that the corrugated canopies commonly installed on the top of windows may contain asbestos materials which were widely used at that time for thermal insulation.
(v) Part of the brick walls enclosing the light well has been demolished.
(vi) Unauthorized enclosure of window openings are commonly found at light wells of each floor. Alteration of windows at light wells is also commonly found.
(vii) Doors from some of the Ground Floor units leading to the light well facing are enclosed.
(e) It appears to Mr R Chan that repairs to the staircases have been carried out recently and the condition of them is acceptable. However, some of the promat fire-rated boards for the enclosure of the non-essential services are removed.
(f) Raised screed is found in the bathrooms of some of the flats. This might impose additional dead load onto the structure and might have adversely effect the structural stability of the Building.
(g) Door access from some of the flats to the roof of is blocked. The materials used for blocking the original door opening might not be up to current standard.
(h) Serious damp patches and peeling off paint are commonly found at the ceiling of some of the flats. Cracks are found near window openings and at beams. Serious concrete spallings are found at the ceiling of bathrooms and kitchens.
(i) Cracks and concrete spallings are commonly found near window openings and at beams. Signs of water dripping, damp patches and mould are found on the ceilings,
(j) Unauthorized cocklofts are erected at the high level of all Shops. Independent entrances connecting the main staircases are provided to the unauthorized cocklofts.
16.Based on the result of his condition survey, Mr R Chan concludes that the roof is generally in poor condition. The waterproofing of the main roof and upper roof should reach the end of its life expectance as serious water seepage, damp patches and peeling off paint are noted at the ceiling of the topmost storey. This indicates that the waterproofing system has failed to function. Unauthorized structures on the roof might have further weakened the waterproofing system of the main roof and also affect the roof structure. Substandard railing may not effectively serve as a barrier to prevent persons or objects from falling out. Although the external walls and the light wells are in fair condition when viewed externally, serious signs of water seepage are still noted at the interior. Site evidence showa that the external walls and the light wells serving as an external envelope for weather protection is defective. Site evidence also shows that a lot of unauthorized drying racks, supporting racks/frames at various residential flats remains at the external walls. Fixing bolts/nails of these metal frames are rusted which might expand and slowly push off the concrete cover and result in more serious concrete defects. Unauthorized building works(“UBWs”) are noted in the Building. They are not shown in the approved building plans and contravene the Building Ordinance. The corrugated canopies/sheets located at the external walls and the light wells are suspected to contain asbestos. Defective paint work is commonly identified at many internal locations. Cracks and concrete spallings were commonly found in the internal areas. Serious cracks and concrete spallings with corroded reinforcement bars greatly exposed are observed on the structural elements, such as beams and columns. This might affect the structural stability of the Building. Kitchen is a place with special hazard. Inadequate fire resistance rating on the walls and doors separating the kitchen with the rest of the flat will impose potential dangers to the people living inside the units in case of fire.
17.Mr R Chan is of the opinion that the Building is generally in a dilapidated and potentially dangerous condition. The structural stability of the Building is also affected by the defects and UBWs. The Building was built in 1960 and is more than 50 years old. Although extensive repair works may extend the Building’s life span, the continuous maintenance costs are expected to be increasingly high.Based on the result of his condition survey, the Building is in a state of disrepair with its structural frames in dilapidated condition. Some of the building components and finishes are at the end of their effective life span. Without substantial repairs, the Building is not up to tenantable standard. Indeed, putting aside the astronomical costs need to be incurred for the repair and maintenance of the Building, Mr R Chan is also of the opinion that it is not feasible or practical to undertake such a course as it would entail a closure of the Building for a substantial period of time. The Building is indeed in potentially dangerous condition and the only sensible solution is to rebuild.
18.The Applicant instructs another expert, Dr Sammy Chan of Wong & Cheng Consulting Engineers Limited (“Dr Chan”)to prepare Structural Assessment Report. Dr Chanhas carried out a visual inspection with a team of engineers on the structural elements of the Building for recording and indentifying of structural defects, so that the general condition of these elements can be evaluated. He is able to inspect all structural elements within the accessible areas of the Building including staircases, corridors and roof, over 70% (23 out of 32) of flats are accessible and are also inspected.
(a) During the inspection, structural defects such as concrete cracking/ spalling, spalling with exposure of corroded reinforcing bar and water seepage are observed in 95% of the inspected flats. Some of the defective areas are extensive. In Dr Chan’s opinion, the Building is at an advanced stage of degradation. The observed structural defects are likely caused by years of neglect and poor maintenance.
(b) Many cracks are found to have extended into the inner bodyof the reinforced concrete columns and beams which would have reduced the strength of these structural elements. Concrete spalling with exposed and corroded reinforcing bars are observed in many locations and indicate that these areas have reached an advanced stage of corrosion. The diameters of many of these exposed reinforcements are significantly reduced due to corrosion.
(c) For the building inspected, the severe degradation of some of the structural members could likely cause local partial failure of the structural members, which if unabated could potentially lead to progressive failure of building.
(d) UBWs include unauthorized opening used as an extra access for the retail shopson Ground Floor, unauthorized mezzanine floor above the retail, and unauthorized metal canopies.
19.In order to obtain general information on the existing structural conditions of the Building, an approved laboratory namely "Qualitech Testing & Consultancy Ltd." (Qualitech) which are accredited by the HOKLAS is instructed to carry out in-situ and laboratory tests on the selected locations.
(a) Compressive Strength Test
16 nos. of 75mm diameter core samples have been taken and compression tests carried out in the laboratory to determine the estimated in-situ strength of concrete.
(b) Carbonation Test
The maximum and mean depths of carbonation are determined by the phenolphthalein method on 16 nos. structural elements. The results indicate that carbonation depth has exceeded the concrete cover in 15 out of the 16 nos. structural elements.
(c) Chloride Content Test
Chloride content tests are carried out on 8 nos. of structural elements. The results indicate that the chloride content ranges from 0.35% to 1.68% with an average of 0.79%.
(d) Cement Content Test
Cement content tests are carried out on 6 nos. of structural dements. The results indicate that the cement content ranges from 9.4% to 18.5% with an average of 12.1%.
(e) Sulphate Content Test
Sulphate content tests are carried out on 8 nos. of structural elements. The results indicate that the sulphate content ranges from 1.7% to 2.6% with an average of 2.05%.
(f) Cover Meter Test
Cover meter tests are performed on 8 nos. structural elements to determine the depth of concrete cover for each type of structural elements.
(g) Open Up Survey
16 nos. of identified areas are opened up to determine the extent of corrosion on reinforcement. The results are:
(i) Locally - The corrosion exists in only a specific part on the surface area of the reinforcement exposed under survey.
(ii) General - The corrosion exists in all or most part on the surface area of the reinforcement exposed under survey (approx 90% up to 100%).
(iii) Pitting - The corrosion makes pits or hollow on the surface area of the reinforcement exposed under survey.
The results indicate that all surface area of surveyed reinforcements are thoroughly weathered, thoroughly blistered, or thoroughly stained, 100% corroded and pitting. The results also indicate that over 80% (54 nos. out of 66) surveyed reinforcements are loss of cross-sectional area (loss from 30% to 100%).
(h) Infrared Thermography Survey
Extensive suspected voided areas/water seepage areas could be identified on the concrete structures of external walls by infrared thermographic survey.
20.From the test results, in Dr Chan’s opinion:
(a) Compressive Strength Test
The average estimated in-situ cube strength obtained from the compressive strength tests are 34.5MPa for slab, 26MPa for beam and 27MPa for column. Approved plans indicate that the general concrete strength is 21 MPa. Therefore, the average estimated in-situ concrete cube strengths can be considered to be higher than the design strength of 21MPa. However, almost 20% (3 nos. out of 16) of estimated in-situ cube strength from the cored samples of structural beams and columns are slightly lower than the design strength.
(b) Carbonation Test
For concrete with carbonated depth exceeding the concrete cover, the passivation layer which protects the reinforcing bars from corrosion is destroyed due to the lowering of pH by the carbonated concrete and corrosion of the steel reinforcement will start with sufficient moisture and oxygen. The test results indicate that over 90% (15 out of the 16 nos.) of the tested concrete elements are considerably carbonated. Corroded steel reinforcement would result in cracking/splaying concrete.
(c) Chloride Content Test
Chloride content in concrete is an important index indicating the status of reinforced concrete structures in respect to chloride-induced corrosion. In accordance with Building (Construction) Regulations, percentage of total chloride content of not greater than 0.35% is considered acceptable for concrete containing embedded metal and made with ordinary or rapid hardening Portland cement. The average of chloride content on all the tested locations is 0.79% which is obviously higher than the specified limit.
(d) Cement Content Test
The cement content of concrete is important from the aspect of durability, impermeability and strength. Too low a cement content may cause inadequate structural capability or more frequently may not provide a durable protective environment for the steel reinforcement, permitting rapid carbonation and subsequent loss of the protective alkaline environment for the steel. The design cement sand mixing is 1:2:4 according to the approved plans which is equivalent to a cement content of approximately 14.3%. The average result of 12.1% cement content is lower than the estimated design mix.
(e) Sulphate Content Test
Exposure of concrete made with Portland cement to sulphate salts can cause damage due to an expansive reaction between the cement and the sulphate salt to form crystals of ettringite. Given adequate space to form, the ettringite forms needle like crystals, but in confined space causes an expansive reaction. The results indicated that the sulphate content ranges from 1.7% to 2.6% with an average of 2.05%. Higher sulphate content decreasing the durability of concrete by changing the chemical nature of the cement paste, and of the mechanical properties of the concrete.
(f) Cover Meter Scan
Sufficient thickness of concrete cover will ensure adequate durability by providing proper protection to the steel reinforcement and also the required fire protection to the structural elements. From the approved plans retrieved from Buildings Department, the structure was designed to have a minimum concrete cover of 15mm for slab, 25mm for beam and 25mm for column. The test results indicated that the overall concrete cover for slab and beam are lower than the minimum design of concrete cover from the approved plans.
(g) Open Up Survey
Open up inspections confirm that the embedded steel reinforcement are extensively blistered, corroded and pitting. Corrosion of steel reinforcing bars would cause deterioration in concrete structures due to reduction in strength as a result of reduction in cross-sectional area of the reinforcing bar, cracking and spalling of cover concrete due to the expansive forces of the corrosion products and loss of structural bond between the reinforcement and cracked concrete.
(h) Infrared Thermography Survey
Thermography testing is capable of detecting evidence of air gap or moisture due to change in thermal conductivity and/or thermal capacitance of the external wall. Infrared thermographic survey results in the identification of extensive suspected voided/water seepage areas (31 nos. with total area of 46.9 sq. m.) on the concrete structures of external wall.
21.In conclusion, Dr Chan confirms that a total of 82 defects are observed on the structural elements of G/F, 1/F to 8/F exhibiting signs of structural defects including concrete cracking/spalling, spalling with exposure of corroded reinforcing bar and water seepage. Over 90% (66 nos. out of 82 nos.) of observed defects are concrete cracking/ spalling, spalling with exposure of corroded reinforcing bar, large areas (from 0.5 sq. m. on 3/F to 0.6 sq. m. on 8/F) of serious spalling with exposure of corroded reinforcing bar could be observed on the structural beams. Severe/thorough corrosion also could be observed on those exposed reinforcing bars. The cracking/spalling, spalling with exposure of corroded reinforcing bar, are caused by concrete carbonation due to natural deterioration/degradation which reduces the alkalinity of the concrete pore solution leading to corrosion of the embedded steel reinforcing bars. The corroded reinforcement would cause the concrete to crack/spall due to the expansive forces of the corrosion products. Water seepages could be also observed on the slab soffit of lavatories or kitchens indicating defective waterproofing works which would allow water to penetrate into the concrete structures. UBWs cause concerns on structural danger to the Building such as fire risks and overloading. From the results of in-situ/laboratory tests submitted by Qualiteeh, almost 20% (3 nos. out of 16) of estimated in-situ cube strength from the cored samples of structural beams and columns are slightly lower than the design strength. The results of carbonation test indicate that the passivation layer which protects the reinforcing bars from corrosion is destroyed as over 90% (15 out of the 16 nos.) of the tested concrete elements are considerably carbonated. The results of chloride content test indicate that the average percentage of chloride content (0.79%) of tested concrete elements is obviously higher than the specified limit (0.35%). When a sufficient amount of chlorides reaches the steel reinforcement it permeates the passivating layer and increases the risk of corrosion. The resistivity of concrete can also be reduced, affecting the corrosion rate of the steel. The results of cement content test indicate that the average percentage of cement content (12.1%) of tested concrete elements is lower than the estimated mix (14.3%). Too low a cement content may cause inadequate structural capability or more frequently may not provide a durable protective environment for the steel reinforcement, permitting rapid carbonation and subsequent loss of the protective alkaline environment for the steel. The results of sulphate content test indicate that the average percentage of sulphate content (2.05%) of tested concrete elements. Higher sulphate content decreasing the durability of concrete by changing the chemical nature of the cement paste, and of the mechanical properties of the concrete. The result of cover meter scan indicate that the overall concrete covers for slab (9mm) and beam (21mm) are lower than the estimated minimum design of concrete cover (15 mm and 25mm respectively). Insufficient thickness of concrete cover decreasing the durability by providing proper protection to the steel reinforcement and also the required fire protection to the structural elements. The results of open up survey indicate that the embedded steel reinforcements are extensively blistered, corroded and pitting. Corrosion of steel reinforcing bars would cause deterioration in concrete structures due to (i) reduction in strength as a result of reduction in cross-sectional area of the reinforcing bar, (ii) cracking and spalling of cover concrete due to the expansive forces of the corrosion products and (iii) loss of structural bond between the reinforcement and cracked concrete. The results of infrared thermography survey identify there are extensive suspected voided/water seepage areas (31 nos. with total area of 46.9m2) on the concrete structures of external wall. Those voided areas would induce deterioration in concrete structures caused by natural deterioration/degradation of the Building due to improper maintenance and ageing problem.
22.Based on the findings of Mr R Chan and Dr Chan, I am satisfied that redevelopment of the Building is justified on the ground of state of repair.
Age of the Building
23.As to the age of the Building, there is no dispute that the Building is almost 53 years old. The relevant occupation permit was issued on 4 February 1960.
24.Mr. Li submits that I should not consider just the physical age of the Building, but should also consider the physical conditions of the Building. He relies on the remarks of Mr R Chan and Dr Chan that it would cost respectively $7,931,417 and $14,040,000 to properly repair the Building, and that it is more cost effective to demolish and rebuild the Building. I agree with Mr Li’s submission that the figure of 44%, being the total repair cost of $21,971,417, over the higher of the EUV of the Building, which is $49,903,556 as assessed by the Applicant’s valuer (see the discussion below), is a very substantial percentage.
25.In Dr Chan’s opinion, according to the results of in-situ/laboratory tests, the embedded steel reinforcements of the Building are extensively blistered, corroded and pitted, moreover, the protective concrete cover are considerably carbonated. Excessive carbonation of concrete indicates that the concrete cover has lost its function to protect the embedded reinforcement of the reinforced concrete members. This proposition is supported by the finding of substantial corrosion of reinforcement as observed from the open-up survey of structural elements. As a result, the overall stability of building may be adversely reduced for such degradation of structural members. In respect of the chemical test result, low cement content recorded showed that the structural members could have low concrete strength and could not provide a durable protective environment for the steel reinforcement, high sulphate content also decreases the durability of concrete. The resistivity of concrete is also low, increasing the corrosion rate of the steel bars. As the stability of the Building is provided by frame action of the reinforced concrete frame, the extensive poor condition of the embedded steel reinforcement identified could cause local structural failure of the building members. For the considerable extent in terms of area and degree of defects in the premises concerned, Dr Chan considers that normal concrete repair works may not be a cost-effective solution to restore the overall integrity of the existing building. Also, the overloading issue due to additional partitions in the sub-divided units and raised floor cannot be resolved or rectified simply by removing the loadings and then by patch repairing the concrete members because affected building structures may have been overstressed for many years and their structural integrity has already been damaged. The overall structural integrity of the Building is in doubt due to the overloading in the sub-divided units (additional walls and raised floors) which renders the potential local failure of the affected building structures. As the nature and extent of structural strengthening works to the existing building are more complicated and substantial as compared with localized repair works, the implementation of a conventional repair and maintenance works package for the Building may not relieve the prevailing degradation problem.
26.According to Mr R Chan,
(a) pre-cast concrete roof railing was built at the perimeter of the main roof of the Building. The old pre-cast concrete railing was replaced by steel railing. Based on his site measurement, the gaps of the steel railing were around 150mm, which does not comply with the current statutory requirements (i.e. maximum width of 100mm).
(b) The two staircases in this building which is for means of escape purposes do not comply with the current statutory requirements in the following aspects:-
(i) Landings of the staircases are around 980mm wide only. The unauthorized sliding gates also reduce the effective width of staircase. They do not comply with the current requirement of S.41(l) of the Building (Planning) Regulations (“B(P)R”) and Clause B8.1 and Table B2 of the Code of Practice for Fire Safety in Buildings 2011 published by the Building Authority in 2011 (“Fire Safety Code”). In this Code, the minimum width of staircase required is 1050mm.
(ii) The residential units at each storey could access to the staircase directly from the entrances and the kitchens without passing through a protected lobby, which does not comply with the current requirement of S.41(l) of the B(P)R and Clause B10.4 of the Fire Safety Code. In this Code, access to the staircase at each storey should be through a protected lobby if the level of the highest floor of the building is more than 13m above ground level (According to the building plan approved by the Building Authority on 3rd March 1959 under the reference number 2/4847/58, the height of the Building is around 28.702m).
(iii) Height of balustrade along the staircase is approximately 900mm. This does not comply with the current requirement of S.8 of the Building (Construction) Regulations (“B(C)R”). The regulation requires the protective barrier shall be constructed with minimum height of 1100mm.
(iv) No handrail is provided at isolated locations of the staircases, which does not comply with the current requirement of S.41(l) of the B(P)R and Clause B14.6 of the Fire Safety Code. In this Code, handrail on each side of the staircase is required.
(v) Exit doors of all residential flats (including kitchen exit doors), from 1/F to 8/F directly open onto the staircase landing are of hardwood doors and metal gates. They were built in old style and are not up to current standard, for instance, they do not have door closer and intumescent seal. Besides, they do not comply with the current requirements of S. 90 of the B(C)R, Clause C9.3 and E5.1 of the Fire Safety Code. In this Code, door giving access to the escape staircase requires to have minimum -1601- Fire Resistance Rating and to be tested in accordance with BS EN 1634-1:2008, BS EN 1634-2:2008, BS EN 1634-3:2004 and BS EN 14600:2005.
(vi) The effective width of most of the sliding metal gates leading to the common staircases, which is the exit doors of the individual flats, is around 450mm. This does not comply with the current requirement of S.41(l) of the B(P)R and Clause B7.1 of the Fire Safety Code. The Code requires that the effective width of exit door should be 750mm.
(vii) Distance between the nearest points in the perimeter of the landings to the two required staircases connecting from roof to G/F is about 3000mm only, which does not comply with the current requirement of S.41(l) of the B(P)R and Clause B10.2 of the Fire Safety Code. In this clause, the minimum distance between the nearest points in the perimeter of the landings to the two required staircases should not less than 6m.
(viii) Width of the exit route connecting the two required staircases is 720mm only, which does not comply with the current requirement of S.41(l) of the B(P)R and Clause B8.1 of the Fire Safety Code. In this clause, the minimum width should be 1050mm.
(ix) The width of each of the exit doors intercepting the exit route connecting the two required staircases is about 450mm and the single leaf doors in building approved plan are replaced by double leaf doors, which does not comply with the current requirement of S.41(l) of the B(P)R and Clause B13.4 of the Fire Safety Code. In this clause, exit door from a storey having an occupant capacity in excess of 3 persons should not be less than 750 mm in width and in case of double leaf doors, no leaf of such door should be less than 600 mm in width.
(x) Outward swinging metal gate swinging over the steps of staircase at some of the main entrance of the Building does not comply with the current requirement of S.41(l) of the B(P)R and Clause B5.8 of the Fire Safety Code. The Code requires that the gate should be installed at a distance of not less than the width of the exit route (i.e. 1050mm) away from the line of drop in level.
(xi) Inward swinging metal gate is used at the final discharge point of the staircase of some parts of the Building. This does not comply with the current requirement of S.41(l) of B(P)R and Clause B13.1 of the Fire Safety Code. The Code requires every door across an exit with the occupant capacity exceeding 30 should open in the direction of exit.
(xii) Water supply pipes are not protected by fire rated enclosure in the required staircases. This does not comply with the current requirement of S.90 of the B(C)R and Clause C9.3(d) of the Fire Safety Code. In this clause, any services other than emergency services should not be accommodate in all required staircase unless such services are enclosed by fire barriers having an FRR of not less than that of the walls separating the protected exit from the rest of the building.
(xiii) The means of escape from any of the flat is necessary to pass through the landing of one required staircase in order to reach another required staircase in case the first required staircase is not suitable for evacuating. This does not comply with the current requirement of S.41(l) of B(P)R and Clause B10.3 of the Fire Safety Code. The Code requires the means of escape from any part of a building should be so arranged that it is not necessary to pass through one required staircase enclosure or the landing of one required staircase, as the case maybe, in order to reach another required staircase.
(c) The exit doors intercepting the exit route connecting the two required staircases do not open in the direction of exit. The occupant capacity of each floor in the Subject Building does not exceed 30, however, in case of emergency, the total occupant capacity of the Building will exceed 30. When one of the required staircases is not suitable for evacuation, it will be difficult for evacuees to reach another required staircase.
(d) The staircases which are the means of escape of the building were in unsatisfactory condition and do not meet the current requirements under the B(P)R, B(C)R and Fire Safety Code. There is no accessible lift installed at the Subject Building for persons with physical disability or chronic illness to access to the flats on upper floors. The upper floors are served by only one staircase. Non-provision of the accessible lift is obviously a functional obsoleteness affecting the convenience and comfort in the use of the upper floors of the Building and do not meet the current requirements of the barrier free access under the S.72(l) of the B(P)R and the Design Manual: Barrier Free Access 2008 published by the Building Authority in 2008 ( “BFA Code”). In this Code, accessible lift shall be provided for domestic building which is more than 13 m in height above ground level and for separate occupation.
(e) According to the current requirement of S.90 of the B(C)R and Clause C13.3 of the Fire Safety Code, kitchen adjacent to exit door should be separated from the rest of the flat by walls having an FRR of not less than -/30/30. The walls enclosing the kitchen were built in old style and may not up to current standard and tested in accordance with BS EN 1364-1:1999.
(f) The doors of the kitchens in some of the flats have been removed. This does not comply with the current requirement of S.90 of the B(C)R and Clause Cl 3.3 of the Fire Safety Code.
(g) Some of the flats have been subdivided into small flats. No kitchen and toilet are provided within the subdivided flats. This does not comply with the current requirement of S.45 of the B(P)R and S. 4 of Building (Standards of Sanitary Fitments, Plumbing, Drainage Works and Latrines) Regulations.
(h) The headroom of the unauthorized cocklofts measured from the floor to the underside of any beam is about 1.75m, which does not comply with current requirements of S.24 of the B(P)R. In this regulation, the headroom of any room used or intended to be use for the purpose of an office or for habitation shall have a height of not less than 2.5 m from floor to ceiling and 2.3m measured from the floor to the underside of any beam.
27.Mr R Chan concludes that the Building is in obsolete design. The substandard in width of the escape staircase, nil provision of protected lobby to escape staircase and accessible lift for person with disability are not up to current legislative requirements.
28.I agree with the view of the Tribunal expressed in Top Sail (supra), that
“when the requirement of “the age” of the Building is considered, we should not restrict our consideration to just the physical age of the Building. There are many factors related to the age of a building which should also be considered” (para. 23);
and that
“the Tribunal has discretion to determine at what stage a building should be redeveloped after considering all the relevant factors concerning the age of the building in question” (para. 23);
and that
“the physical age of a building is clearly one of the considerations, but it would not be the only consideration. The physical conditions of a building and the amount that would be required to maintain the building are other factors that the Tribunal should consider, as they would affect the decision on whether the life of a building should be ended or prolonged. The obsolete design of a building should also be considered as it has an important impact on whether it is too old to serve a modern society.” (para .24).
29.Having considered all the evidence as aforesaid, I am satisfied that the redevelopment of the Building is also justified on the ground of the age of the Building due to the following factors:
(a) the Building is almost 53 years old;
(b) the Building is in very poor physical conditions and very substantial cost is required to repair or maintain the Building; and
(c) the obsolete design of the Building does not suit the present requirements of a building.
Reasonable Steps to Acquire All the Undivided Shares in the Lot
30.As required by s. 4(2)(b) of the Ordinance, the Applicant is under an obligation to negotiate for the purchase of the 5th Respondents’ undivided share in the Lot on terms that are fair and reasonable.
31.The evidence of the Applicant’s factual witness, Mr Alex Au-Yeung, shows that:
(a) Before launching the present .proceedings and with an intention to avert the same if possible, the Applicant had made offers to the 5th Respondents based on valuation done by professional valuer. The Applicant’s associated companies Easy Favour limited, Star Keen Limited and Sky Reach Group Limited (“the Applicant’s associated companies”) hadcommissioned Knight FrankPetty Limited ("Knight Frank'') to assess the value of the units in the Building on the existing use value basis (“EUV”) and the redevelopment value (“RDV”) of the Lot, The valuation date of the assessment is 18 October2011. Mr Alnwick Chan of KnightFrank (“Mr A Chan”) has duly prepared a report on EUV of all the units in the Building dated 10 January 2012 (“Knight Frank EUV Report”). The Knight Frank EUV Report is the statutory report attached to the Application. Mr A Chan has also prepared a letter of report dated 26 October 2011 stating the RDV of the Lot as at 18 October 2011 (“Knight Frank RDV assessment”).
(b) Based on the Knight Frank EUV Reportand Knight Frank RDV assessment, the Applicant's associated companies and the Applicant made offers to the 5th Respondents for acquiring the 5th Respondents’ premises prior to the commencement of the proceedings. According to the Knight Frank EUV report, the EUV of the Building as 18 October 2011 was $46,686,867. The EUV of the 5th Respondents’ premises was $497,665. It meant in term of percentage, the share of the 5th Respondents’ premises in the Building was 1.06596%. According to Knight Frank RDV assessment,the RDV of the Lot as at 18 October 2011 was $66,900,000. It meant that the reasonable offer to be made to the 5th Respondents would be $713,130 (i.e. $66,900,000 x 1.06596%).
(c) The Applicant's associated companies, through their solicitors, by letter dated26 October 2011 to the 5th Respondents offered to purchase the 5th Respondents’ premises at $770,000. There was no reply. Thenthe Applicant's associated companies through their solicitors, by letter dated 14 November2011 offered to the 5th Respondents to purchase the 5th Respondents’ premises at $880,000. There was no reply. By a letter in English and Chinese dated 25 November 2011 to the 5th Respondents, the Applicant's solicitors informed the 5th Respondents that the Applicant's associated companies had assigned the units in the Building to the Applicant and the Applicant would adopt the contents of the previous offer letters made by the Applicant’s associated companies. There was still no response. This was followed by a letter in English and Chinese dated 8 December 2011 from the Applicant's solicitors to the 5th Respondents by which the Applicant offered to purchase the 5th Respondents’ premises at $890,000. The offer was made after taking into consideration an apportionment letter dated 7 December 2011 prepared by Mr A Chan.
(d) As the 5th Respondents did not makes any response to the offers, the Applicant has no alternative but to commence the present proceedings.
(e) With an intention of continuing to acquire the 5th Respondents’ premises so as to obviate the necessity of legal proceedings, the Applicant was ready to mediate with the 5th Respondents and did file a Mediation Certificate dated 12 January 2012 with the Tribunal. However, there was no response from the 5th Respondents. No mediation took place.
32.Although I do not have detailed evidence of the RDV assessment when the Applicant offered to purchase the 5th Respondents’ premises, Iam satisfied that, on the evidence available, the offers made by the Applicant and the Applicant’s associated companies “falls within the range of what may broadly be regarded as fair and reasonable” as said by Mr. Justice Ribeiro PJ in Capital Well Ltd v. Bond Star Development Ltd (2005) 8 HKCFAR 578 at para. 33. Thus, I conclude that the Applicant has taken reasonable steps to acquire all the undivided shares in the Lot.
Order for Sale
33.By reasons of the matters aforesaid, I am satisfied that an order for sale should be granted in favour of the Applicant. The remaining question is how much I should fix for the reserve price.
Reserve Price
34.In the Knight Frank EUV Reportdated 10 January 2012, Mr A Chan valued the EUV of all the units of the Building as at 18 October 2011.
35.Mr A Chan finds that according to the approved building plan of the Building, all units in the Building are marked "domestic". As such, Mr A Chan considers the permitted user of all the units is domestic. However, during Mr A Chan’s inspection of the Building, he finds that all the units on the Ground Floor are used as shops. Mr A Chan therefore has prepared his EUV valuation based on 2 scenarios, one assuming all units are domestic; and two, assuming all the units on the Ground Floor are shops.
36.In his valuation of the EUV of the ground floor units of the Building as shops, Mr A Chan adopted the following methodology:-
(a) He selected Ground Floor 13 Wan King Street as the reference unit (“the Reference Shop Unit”). He then took into account of 4 comparable transactions in three different buildings nearby.After making what he regarded as the necessary adjustments (for time, location, building age, frontage, return frontage, headroom, layout and size) for all these comparable transactions, he took the average of the adjusted unit rate of the comparables to come to the unit price of the Reference Shop Unit at $63,894/m², which was rounded to $64,000/m².
(b) He then used the unit rate of the Reference Shop Unit to assess the other ground floor units.
37.In his valuation of the EUV of the domestic units of the Building, Mr A Chan adopted the following methodology :
(a) He selected 4th Floor of No. 14 Wan Shun Street (“the Reference Domestic Unit”), which was situated on the middle floor of the domestic portion as the reference unit for the purpose of valuing its unit price.
(b) The unit price of the Reference Domestic Unit was first assessed by making reference to market comparables. He took into account of 6 comparable transactions in five different buildings nearby. After making what he regarded as the necessary adjustments (for time, location/accessibility, age, floor, size, building condition and view) for all these comparable transactions, he took the average of the adjusted unit rate of the comparables to come to the unit price of the Reference Domestic Unit at $36,668/m², which was rounded to $37,000/m².
(c) He further considered the floor difference and internal conditions of the Reference Domestic Unit and the remaining domestic units within the Building to arrive at the EUV of all the domestic units.
38.For the roof of the Building, Mr A Chan converted the saleable area of the roof as domestic by using a conversion factor of 1:8.
39.Mr Li submits that insofar as the statutory EUV report is concerned which is used for deciding the apportionment ratio under section 10(3) and Part 3 of Schedule 1 of the Ordinance, following Gilmerton Limited and Others v. PolywinHoldings Limited and Others(LDCS 2000 of 2004, 17 January 2005, unreported) at paras. 12, 13, 14 and 15), the valuation date of Mr A Chan’s report is 18 October 2011, which is within 3 months of the Application.
40.Mr Li also submits that the EUV Report gives 2 EUV figures depending on whether the use of the ground floor of the Building is domestic or non-domestic. On the first scenario, the total EUV is $46,635,558 and the EUV of 5th Respondents’ premises is $497,622 giving rise to a ratio of 1.067%. In the second scenario, the total EUV is $49,903,556 and that 5th Respondents’ premises is still $497,622 giving rise to a ratio of 0.997%. Mr Li submits that the Applicant is happy to adopt the higher ratio which is to the benefit of the 5th Respondents.
41.Having considered Mr A Chan’s valuation, I agree with Mr Li’s submission and hold that the EUV of the Building should be determined on the assumption that all the units are for domestic use.
42.As a result, the EUV of all the units in the Building are:
Floor |
11 Wan King St |
12 Wan Shun St |
13 Wan King St |
14 Wan Shun St |
G/F |
$1,370,628 |
$1,370,628 |
$1,345,453 |
$1,345,453 |
1/F |
$1,365,248 |
$1,365,248 |
$1,358,581 |
$1,358,581 |
2/f |
$1,339,489 |
$1,339,489 |
$1,332,947 |
$1,332,947 |
3/F |
$1,313,729 |
$1,313,729 |
$1,307,314 |
$1,307,314 |
4/F |
$1,287,970 |
$1,287,970 |
$1,281,680 |
$1,281,680 |
5/f |
$1,262,211 |
$1,262,211 |
$1,230,413 |
$1,256,046 |
6/F |
$1,236,451 |
$1,236,451 |
$1,230,413 |
$1,230,413 |
7/F |
$1,210,692 |
$1,210,692 |
$1,204,779 |
$1,179,146 |
8/F |
$1,211,824 |
$1,211,824 |
$1,179,146 |
$1,179,146 |
Roof |
$497,622 |
43.The 5th Respondents have not filed any expert report. I am satisfied that the EUV valuation of Mr A Chan is fair and reasonable. I hold that the proceeds are to be apportioned on the basis of the EUV as determined by me above.
44.In his valuation report dated 9 January 2013, Mr A Chan states the RDV of the Lotas at 4 January 2013 to be $75,700,000.
45.Mr A Chan’s valuation method can be summarized as follows:
(a) The valuation is conducted on the assumption that the existing building erected thereon is vacant and to be demolished and redeveloped into certain beneficial usages reasonably reflecting its redevelopment potential. He takes into consideration the Government policies and measures announced on 13 October 2010 intended to reduce the gross floor area concessions which would also reduce the building bulk and the marketable gross floor area as well as the relevant Joint Practice Notes (issued by Building Department, Lands Department and Planning Department) and Practice Notes issued by Building Department or Lands Department in January to March 2011 to that effect.
(b) Mr A Chan also takes into consideration the two new measures announced by the Government on 26 October 2012 to address the overheated residential property market, the amendment to Special Stamp Duty, and the introduction of Buyer’s Stamp Duty. Mr A Chan opines that since the actual impact to the price level cannot be objectively assessed at the date of valuation, he maintains the ‘Profit on Land’ and ‘Profit on Cost’ at 10% in his residual valuation.
(c) In assessing the RDV, residual method of valuation is adopted by deducting development costs (including construction costs, professional fees, finance costs, etc.) and developer's profit from the estimated gross development value of a completed development. Mr A Chan has carried out the valuation with reference to market comparable sale evidence assuming that vacant possession of the Lot would be readily available upon completion. Time adjustment is applied with reference to the Private Domestic Price Indices by Class and Private Retail Price Indices prepared by Rating and Valuation Department as in December 2012.
(d) Taking into account the Building (Planning) Regulations, the restrictions of the Outline Zoning Plan affecting the Lot and the comparatively higher residential value in the vicinity and the limited retail potential on upper floors, Mr A Chan is of the opinion that a composite building with shops on ground floor and first floor and residential units on upper floors should be erected.
(e) He then uses the residual valuation method to assess the land value of the intended development.
(f) Retail and domestic comparables are identified and analysed, applying relevant adjustments as appropriate.
(g) Mr A Chan uses 7 Ground Floor shop transactions in five buildings nearby as his Ground Floor retail comparables. For 1st Floor shop and upper floor domestic comparables, he uses a total of 4 1st Floor shopping arcade transactions in two developments and 33 flat transactions in five developments nearby respectively.
(h) The following unit rates are adopted by Mr. A. Chan in assessing the gross development value:
Ground Floor Retail: $180,000/m²;
1st Floor shop: $68,000/m²; and
Typical Domestic Unit: $130,000/m².
(i) Mr A Chan then deducts the development costs from the gross development value. Allowing for developer’s profit and discounting for the development period, Mr A Chan determines the land value of the Lot on redevelopment basis.
46.Mr A. Chan confirms his RDV valuation at $75,700,000. I am satisfied that the valuation made by Mr A Chan is fair and reasonable, reflecting the current redevelopment value of the Lot. Thus, the reserve price of the Lot should be fixed at this value.
Conclusion
47.In the circumstance, I make the following determination:
Upon This Tribunal being satisfied that the existing use value of the 5th Respondents’ one equal undivided 37th part or share of and in the building known as Nos. 11 and 13 Wan King Street and No. 12-14 Wan Shun Street Kowloon (“the Building”) erected on Section H of Kowloon Marine Lot No. 52 (“the lot”) together with the right of possession of the Roof of the Building is $497,622 is fair and reasonable and is fair and reasonable when comparing with the existing use value of the other units, the undivided shares of which belong to the Applicant as assessed in this application (and with the total existing use value of all the units of the Building being $46,635,558) and
Upon This Tribunal also being satisfied that the redevelopment of the Building is justified due to the age or state of repair of the Building and that the Applicant has taken reasonable steps to acquire all the undivided shares in the Lot held by the 5th Respondents
I order that
(a) That all the undivided shares in Section H of Kowloon Marine Lot No. 52 (“the Lot”), the subject of the Application, be sold by way of public auction for the purposes of redevelopment of the Lot under section 4(1)(b) of the Land (Compulsory Sale for Redevelopment) Ordinance Cap. 545 (“the Ordinance’);
(b) That Mr Ho Chi Kit and Mr Cheung Chi Yu nominated by the Applicant be appointed trustees (“the Trustees”) to discharge the duties imposed on trustees under the Ordinance in relation to the Lot, and the Trustees be authorized to charge such remuneration for their services in accordance with the terms set out in the letter from Messrs. Katherine Y.W. OR & Co. dated 8 January 2013;
(c) For the purposes of the sale of the Lot by public auction under section 5(1)(a) of the Ordinance:
(i) The sale of the Lot be sold on the particulars and conditions as to be initialed and approved by the Tribunal;
(ii) The reserve price be set at $75,700,000; and
(iii) Subject to further extensions that the Tribunal may subsequently allow upon the application of the purchaser of the Lot in the auction sale or successor in title, the redevelopment of the Lot shall be completed and made fit for occupation within a period of 6 years after the date on which the purchaser of the Lot becomes the owner of the Lot as specified by section 9 and Schedule 3 of the Ordinance; and
(d) Liberty to the Applicant, the 5th Respondents and the Trustees to apply to the Tribunal for further directions under the Ordinance.
Costs
48.The Applicant has indicated its position on costs. Thus, I make a costs order nisi that there be no order as to costs for the Application herein. If the parties do not make any further application for costs within 14 days from today, the costs order nisi shall become absolute.
|
|
(Kenneth KWOK)
Temporary Member
Lands Tribunal
|
Mr. CY LI, SC, instructed by M/S So, Lung & Associates, for theApplicant
The 5th Respondents, absent
|