Eversound Investments Ltd v. Tai Cheung Chuen and Others
Read the full judgment text of LDCS 33000/2012 on BabelCite. This LDCS judgment was delivered on 21 May 2013.
1. This is an application for compulsory sale of all the undivided shares in Section J of Kowloon Marine Lot No. 52 ("the Lot"), known as Nos. 19 & 21 Wan King Street and Nos. 20 & 22 Wan Shun Street, ("the Building"), for the purposes of the redevelopment of the Lot pursuant to Section 3(1) of the Land (Compulsory Sale for Redevelopment) Ordinance, Cap. 545 ("the Ordinance").
Cited by 3 cases · Cites 8 cases
|
LDCS 33000 / 2012 IN THE LANDS TRIBUNAL OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION LAND COMPULSORY SALE APPLICATION NO. 33000 OF 2012 __________________
___________________
_______________ J U D G M E N T _______________ Background 1.This is an application for compulsory sale of all the undivided shares in Section J of Kowloon Marine Lot No. 52 ("the Lot"), known as Nos. 19 & 21 Wan King Street and Nos. 20 & 22 Wan Shun Street, ("the Building"), for the purposes of the redevelopment of the Lot pursuant to Section 3(1) of the Land (Compulsory Sale for Redevelopment) Ordinance, Cap. 545 ("the Ordinance"). 2.There is erected on the Lot an 8 storey composite building served by 2 common staircases. Originally altogether there are 59 units in the Building and each unit is allotted one share, except the Roof, the 4 units on the Ground Floor and the 6/F and 7/F of No. 21 Wan King Street, which are allotted two shares each with a total of 66 undivided shares for the Building and the Lot. Subsequently each paired Flat A and Flat B of all the units from 1/F to 7/F (inclusive), except Flat A and Flat B of 5/F and 7/F of No. 19 Wan King Street and of 1/F of No. 22 Wan Shun Street, have been assigned to the same owner as one unit. As a result, there are now 36 units in the Building. 3.The Applicant commenced the present proceedings on 18 April 2012. At that time, the 1st Respondents are the registered owner of Ground Floor (formerly G/F of House No. 6 Block C), No. 20 Wan Shun Street,
4.Since then, the Applicant has acquired the interests of the 1st Respondents, the 2nd Respondent, the 3rd Respondent, and the 5th Respondent and has discontinued the application against them by orders of the Tribunal. 5.As at the date of hearing, the 4th Respondent owns 2 equal undivided 66th parts or shares of and in the Lot ("the 4th Respondent’s premises") and the 6th Respondents own 2 equal undivided 66th parts or shares of and in the Lot ("the 6th Respondents’ premises"). All the remaining shares and units in the Building and the Lot are owned by the Applicant. Thus, the percentage of the undivided shares owned by the Applicant in the Lot is now 93.94%. 6.Both the 4th Respondent and the 6th Respondents did not file any Notice of Opposition. 7.An Order for dispensing with services on the 4th Respondent under section 3(4) of the Ordinance was granted by the Tribunal on 30th November 2012. The publication of notices in newspapers pursuant to the Order was duly complied with by the Applicant. Before the hearing, the solicitors for the Applicant have duly served all the papers of the Application to the address of the 6th Respondents made known to the solicitors. The 4th Respondent and the 6th Respondents were absent at the hearing and did not file any response or expert report. 8.In view of the absence of the 4th Respondent and the 6th Respondents, Mr C.Y. Li SC, Counsel for the Applicant, simply called the Applicant’s witnesses to confirm their evidence. The Applicant contends that all the requirements of the Ordinance have been satisfied and asks for an order for sale in terms of the draft order submitted. The Applicant also asks there be no order as to costs. Section 3 of the Ordinance – Ownership of the Applicant 9.Section 3(1) of the Ordinance requires the Applicant to have not less than 90% of the undivided shares in a lot before it can make an application. 10.Section 3(5) of the Ordinance also states that the Chief Executive in Council may, by notice in the Gazette, specify a percentage lower than the percentage mentioned in subsection (1) in respect of a lot belonging to a class of lots specified in the notice. 11.Pursuant to Section 3(5) of the Ordinance, the notice was gazetted on 22 January 2010 and tabled at the Legislative Council meeting on 27 January 2010. It came into operation on 1 April 2010. Section 3 of the notice lowered the threshold for compulsory sale from 90% to 80%. Section 4(1)(b) of the notice specified one of the classes for the purposes of Section 3, as "a lot with each of the building erected on the lot issued with an occupation permit at least 50 years before the relevant date (which is the date of the application)". The occupation permit of the Building was issued on 25 April 1960, which is more than 51 years before the date of application. The Building therefore is covered by the notice and the applicable percentage is 80%. 12.As at the date of application, the Applicant owns 86.36% of the shares in the Lot. The Applicant is clearly entitled to make the application.
13.In determining the Applicant’s application, Section 4(2) of the Ordinance requires me not to make an order for sale unless, after hearing the objections, if any, of the 4th Respondent and the 6th Respondents, I am satisfied that:
14.Mr Li submits that the relevant tests on age and state of repair were set out in Top Sail International Ltd v. Cheng Kai Ming, executor of the estate of Chan Hue also known as Chan Sum Hiu, deceased (LDCS 18000/2010, 15 November 2011, unreported). Mr. Li further submits that the tests were also applied recently in the decisions of this Tribunal in Champion Success Limited & Another v. Leung Lai Lai the administratrix of the estate of Lai Yin King Deceased & Others (LDCS 41000/2011, 16 January 2013, unreported), Eversound Investments Limited v. Tung Chun Hung & Others (LDCS 5000/2012, 23 January 2013, unreported), Eversound Investments Limited v. Wu Lai Ho Fatima & Others (LDCS 36000/2012, 21 March 2013, unreported), Eversound Investments Limited v. Lee Yuk Fun & Others (LDCS 4000/2012, 17 April 2013, unreported) and Eversound Investments Limited v. Au-Yeung Ngan Siu & Others (LDCS 34000/2012, 23 April 2013, unreported). I am of the view that “the age” and “state of repair” are two separate grounds and even though there may be considerations common to both, I should still consider them separately. Since Mr Li relies primarily on “state of repair”, I shall deal with this ground first.
15.The Applicant’s expert, Mr Raymond Chan of Raymond Chan Surveyors Limited ("Mr R Chan"), in his Condition Survey Report, gives his opinion, inter alia, that:
16.For the internal conditions:
17.Based on the result of his condition survey, Mr R Chan concludes that the roof is generally in poor condition. The waterproofing of the main roof and upper roof should reach the end of its life expectance as serious water seepage, damp patches and peeling off paint are noted at the ceiling of topmost storey. This indicates that the waterproofing system has failed to function. Unauthorized structures on roof might have further weakened the waterproofing system of the main roof and also affect the roof structure. Although the external wall is newly painted, site evidence shows that some defects like abandoned bolts and nails, rust stains, poor workmanship of the patch repair works, bulging of render and defective drainage, etc are still noted. Moreover, the internal condition of the Building is totally different from the external walls with serious concrete spalling and cracks on the structural elements. It indicates that some defects of the building structure are hidden by cosmetic decoration only. Site evidence also shows that a lot of unauthorized drying racks, supporting racks/ frames and abandoned nails and bolts at various residential flats remain at the external walls. Subject to weathering, fixing bolts/nails of these metal frames are rusted which might expand and slowly push off the concrete cover and result in more serious concrete defects. Unauthorized building works (“UBWs”) are noted in the Building. They are not shown in the approved building plans and contravene the Buildings Ordinance. The corrugated canopies/sheets located at the external walls and the light wells are suspected to contain asbestos. Defective paint and plaster finishes are commonly identified at many internal locations. Cracks and concrete spallings are commonly found in the internal areas. Cracks and concrete spallings with corroded reinforcement bars greatly exposed are observed on the structural elements, such as beams and columns. This might affect the structural stability of the Building. Kitchen is a place with special hazard. Inadequate fire resistance rating on the walls and doors separating the kitchen with the rest of the flat will impose potential dangers to the people living inside the units in case of fire. 18.Mr R Chan is of the opinion that the Building is generally in a dilapidated and potentially dangerous condition. The structural stability of the Building is also affected by the defects and UBWs. The Building was built in 1960 and is more than 50 years old. Although extensive repair works may extend the Building’s life span, the continuous maintenance costs are expected to be increasingly high. Based on the result of his condition survey, in Mr R Chan’s opinion, the Building is in a state of disrepair with its structural frames in dilapidated condition. Some of the building components and finishes are at the end of their effective life span. Without substantial repairs, the Building is not up to tenantable standard. Indeed, putting aside the astronomical costs need to be incurred for the repair and maintenance of the Building, Mr R Chan is also of the opinion that it is not feasible or practical to undertake such a course as it would entail a closure of the Building for a substantial period of time. The Building is indeed in potentially dangerous condition and the only sensible solution is to rebuild. 19.The Applicant instructs another expert, Dr Sammy Chan of Wong & Cheng Consulting Engineers Limited (“Dr Chan”) to prepare Structural Assessment Report. Dr Chan has carried out a visual inspection with a team of engineers on the structural elements of the Building for recording and identifying structural defects, so that the general condition of these elements can be evaluated. He is able to inspect all structural elements within the accessible areas of the Building including staircases, corridors and roof, over 90% (26 out of 28) of flats are accessible and are also inspected.
20.In order to obtain general information on the existing structural conditions of the Building, an approved laboratory Qualitech Testing & Consultancy Ltd. which is accredited by the HOKLAS is instructed to carry out in-situ and laboratory tests on selected locations.
21.From the test results, in Dr Chan’s opinion:
22.In conclusion, Dr Chan confirms that a total of 105 defects are observed on the structural elements of G/F, 1/F to 7/F exhibiting signs of structural defects including concrete cracking/spalling, spalling with exposure of corroded reinforcing bar and water seepage. Over 95% (101 nos. out of 105 nos.) of observed defects are concrete cracking/ spalling. Spalling with exposure of corroded reinforcing bar, large areas (from 0.16 sq. m. to 2 sq. m.) of serious spalling with exposure of corroded reinforcing bar could be observed on the structural beams. Severe/thorough corrosion also could be observed on those exposed reinforcing bars. The cracking/spalling, spalling with exposure of corroded reinforcing bar, are caused by concrete carbonation due to natural deterioration/degradation which reduces the alkalinity of the concrete pore solution leading to corrosion of the embedded steel reinforcing bars. The corroded reinforcement would cause the concrete to crack/spall due to the expansive forces of the corrosion products. Water seepages could be also observed on the slab soffit of lavatories or kitchens indicating defective waterproofing works which would allow water to penetrate into the concrete structures. UBWs cause concerns on structural danger to the Building such as fire risks and overloading. The results of carbonation test indicate that the passivation layer which protects the reinforcing bars from corrosion is destroyed as 100% of the tested concrete elements are considerably carbonated. The results of chloride content test indicate that the average percentage of chloride content (1.43%) of tested concrete elements is obviously higher than the specified limit (0.35%). When a sufficient amount of chlorides reaches the steel reinforcement it permeates the passivating layer and increases the risk of corrosion. The resistivity of concrete can also be reduced, affecting the corrosion rate of the steel. The results of cement content test indicate that the average percentage of cement content (11.1%) of tested concrete elements is lower than the estimated mix (14.3%). Too low a cement content may cause inadequate structural capability or more frequently may not provide a durable protective environment for the steel reinforcement, permitting rapid carbonation and subsequent loss of the protective alkaline environment for the steel. The results of sulphate content test indicate that the average percentage of sulphate content (1.54%) of tested concrete elements. Higher sulphate content decreass the durability of concrete by changing the chemical nature of the cement paste, and of the mechanical properties of the concrete. The result of cover meter scan indicates that the overall concrete covers for beam (23.3 mm) are lower than the estimated minimum design of concrete cover (25 mm). Insufficient thickness of concrete cover decreases the durability by providing proper protection to the steel reinforcement and also the required fire protection to the structural elements. The results of open up survey indicate that the embedded steel reinforcements are extensively blistered, corroded and pitting. Corrosion of steel reinforcing bars would cause deterioration in concrete structures due to (i) reduction in strength as a result of reduction in cross-sectional area of the reinforcing bar, (ii) cracking and spalling of cover concrete due to the expansive forces of the corrosion products and (iii) loss of structural bond between the reinforcement and cracked concrete. The results of infrared thermography survey identify there are extensive suspected void/water seepage areas (16 nos. with total area of 56.2 sq. m.) on the concrete structures of external wall. These void areas would induce deterioration in concrete structures caused by natural deterioration/degradation of the Building due to improper maintenance and ageing problem. 23.Based on the findings of Mr R Chan and Dr Chan, I am satisfied that redevelopment of the Building is justified on the ground of state of repair. Age of the Building 24.As to the age of the Building, there is no dispute that the Building is now 53 years old. The relevant occupation permit was issued on 25 April 1960. 25.Mr Li submits that I should not consider just the physical age of the Building, but should also consider the physical conditions of the Building. He relies on the remarks of Mr R Chan and Dr Chan that it would cost respectively $7,793,217 and $12,556,170 to properly repair the Building, and that it is more cost effective to demolish and rebuild the Building. I agree with Mr Li’s submission that the figure of 44.4%, being the total repair cost of $20,349,387, over the higher of the EUV of the Building, which is $45,825,185 as assessed by the Applicant’s valuer (see the discussion below), is a very substantial percentage. 26.In Dr Chan’s opinion, according to the results of in-situ/laboratory tests, the embedded steel reinforcements of the Building are extensively blistered, corroded and pitted. Moreover, the protective concrete cover is considerably carbonated. Excessive carbonation of concrete indicates that the concrete cover has lost its function to protect the embedded reinforcement of the reinforced concrete members. This proposition is supported by the finding of substantial corrosion of reinforcement as observed from the open-up survey of structural elements. As a result, the overall stability of the Building may be adversely reduced for such degradation of structural members. In respect of the chemical test result, low cement content recorded shows that the structural members could have low concrete strength and could not provide a durable protective environment for the steel reinforcement. High sulphate content also decreases the durability of concrete. The resistivity of concrete is also low, increasing the corrosion rate of the steel bars. As the stability of the Building is provided by frame action of the reinforced concrete frame, the extensive poor condition of the embedded steel reinforcement identified could cause local structural failure of the building members. For the considerable extent in terms of area and degree of defects in the premises concerned, Dr Chan considers that normal concrete repair work may not be a cost-effective solution to restore the overall integrity of the Building. Also, the overloading issue due to additional partitions in the sub-divided units and raised floor cannot be resolved or rectified simply by removing the loadings and then by patch repairing the concrete members because affected building structures may have been overstressed for many years and their structural integrity has already been damaged. 27.In Dr Chan’s opinion, The Building has already undergone severe degradation which renders it not worthwhile to be rectified by conventional repair and maintenance measures. The overall structural integrity of the Building is in doubt due to the overloading in the sub-divided units (additional walls and raised floors) which renders the potential local failure of the affected building structures. As the nature and extent of structural strengthening work to the existing building are more complicated and substantial as compared with localized repair work, Dr Chan considers the implementation of a conventional repair and maintenance work package for the Building may not relieve the prevailing degradation problem. 28.According to Mr R Chan:
29.Mr R Chan concludes that the Building is in obsolete design. The substandard in width of the escape staircase, nil provision of protected lobby to escape staircase and accessible lift for persons with disability are not up to current legislative requirements. 30.I agree with the view of the Tribunal expressed in Top Sail (supra), that
and that
and that
31.Having considered all the evidence as aforesaid, I am satisfied that the redevelopment of the Building is also justified on the ground of the age of the Building due to the following factors:
Reasonable Steps to Acquire All the Undivided Shares in the Lot 32.As required by Section 4(2)(b) of the Ordinance, the Applicant is under an obligation to negotiate for the purchase of the 4th Respondent’s and the 6th Respondents’ undivided shares in the Lot on terms that are fair and reasonable. 33.The evidence of the Applicant’s factual witness, Mr Alex Au-Yeung, shows that:
34.Although I do not have detailed evidence of Knight Frank’s assessments when the Applicant offered to purchase the 4th Respondent’s premises and the 6th Respondents’ premises, I am satisfied that, on the evidence available, the offers made by the Applicant fall "within the range of what may broadly be regarded as fair and reasonable" as said by Mr Justice Ribeiro PJ in Capital Well Ltd v. Bond Star Development Ltd (2005) 8 HKCFAR 578 at para. 33. Thus, I conclude that the Applicant has taken reasonable steps to acquire all the undivided shares in the Lot. Order for Sale 35.By reasons of the matters aforesaid, I am satisfied that an order for sale should be granted in favour of the Applicant. The remaining question is how much I should fix for the reserve price. Reserve Price 36.Mr Alnwick Chan, a Fellow Member of the Royal Institution of Chartered Surveyors in the General Practice Division as well as the Hong Kong Institute of Surveyors, of Knight Frank (“Mr A Chan”) prepared a report dated 18 April 2012 valuing the EUV of all the units in the Building as at 21 February 2012 (“Knight Frank EUV Report”). The Knight Frank EUV Report is the statutory report attached to the Application. 37.In Mr A Chan’s valuation, where pairs of sub-divided flats within one typical unit are acquired by the same owner, he considers these units as one typical unit, as if it has not been sub-divided. 38.Mr A Chan finds that according to the approved building plan and the occupation permit of the Building, all units in the Building are marked "domestic". As such, Mr A Chan considers the permitted user of all the units is domestic. However, during Mr A Chan’s inspection of the Building, he finds that all the units on the Ground Floor are used as non-domestic. Mr A Chan therefore has prepared his EUV valuation based on 2 scenarios, one assuming all units are domestic; and two, assuming all the units on the Ground Floor are non-domestic. 39.Mr A Chan has also prepared a Supplemental Report dated 13 March 2013 valuing the EUV of all the units in the Building as at 21 February 2012 taking into account the further inspection of units in the Building and the available updated price index (“Knight Frank Revised EUV Report”). 40.In his valuation of the EUV of the ground floor units of the Building as non-domestic, Mr A Chan adopted the following methodology:-
41.In his valuation of the EUV of the domestic units of the Building, Mr A Chan adopted the following methodology :
42.For the roof of the Building, Mr A Chan converted the saleable area of the roof as domestic by using a conversion factor of 1:8. 43.Mr Li submits that insofar as the statutory EUV report is concerned which is used for deciding the apportionment ratio under section 10(3) and Part 3 of Schedule 1 of the Ordinance, following Gilmerton Limited and Others v. Polywin Holdings Limited and Others (LDCS 2000 of 2004, 17 January 2005, unreported) at paras. 12, 13, 14 and 15, the valuation date of Mr A Chan’s Knight Frank EUV Report is 21 February 2012, which is within 3 months of the Application. 44.Mr Li also submits that Mr A Chan’s Knight Frank Revised EUV Report gives 2 EUV figures depending on whether the use of the ground floor of the Building is domestic or non-domestic. In the first scenario (the use of the ground floor of the Building is domestic), the total EUV of all the units in the Building in the Knight Frank Revised EUV Report is $41,334,389 and the EUV of the 4th Respondent's premises and the 6th Respondents’ premises is respectively $1,218,691 and $586,371 giving rise to a ratio of respectively 2.948% and 1.419%. In the second scenario (the use of the ground floor of the Building is non-domestic), the total EUV is $45,825,185 and the EUV of the 4th Respondent's premises and the 6th Respondents’ premises remains the same giving rise to a ratio of respectively 2.659% and 1.2796%. Mr Li submits that the Applicant is happy to adopt the higher ratio in the first scenario which is to the benefit of the 4th Respondent and the 6th Respondents. 45.Having considered Mr A Chan’s valuation, I agree with Mr Li’s submission and hold that the EUV of the Building should be determined on the assumption that all the units are for domestic use, as shown in the first scenario of the Knight Frank Revised EUV Report. 46.In Best Insight Limited (勤正有限公司) v. the Estate of Tin Hing Lin (田興蓮) (deceased) & Others (LDCS 5000/2011, 5 September 2011, unreported), when the expert for the applicant has revised his EUV valuation, the Tribunal holds that under
47.The 4th Respondent and the 6th Respondents have not filed any expert report. I am satisfied that the EUV of Mr A Chan is fair and reasonable. I hold that the proceeds are to be apportioned on the basis of the first scenario of the Knight Frank Revised EUV Report determined by me as follows:
| ||||||||||||||||||||||||||||||||||||||||||||||||||
| 2/F | Flat A | $1,345,638 | $1,294,859 | $1,345,638 | $1,345,638 | |||||||||||||||||||||||||||||||||||||||||||||
| Flat B | ||||||||||||||||||||||||||||||||||||||||||||||||||
| 3/F | Flat A | $1,294,859 | $1,294,859 | $1,294,859 | $1,320,249 | |||||||||||||||||||||||||||||||||||||||||||||
| Flat B | ||||||||||||||||||||||||||||||||||||||||||||||||||
| 4/F | Flat A | $1,269,470 | $1,269,470 | $1,269,470 | $1,269,470 | |||||||||||||||||||||||||||||||||||||||||||||
| Flat B | ||||||||||||||||||||||||||||||||||||||||||||||||||
| 5/F | Flat A | $534,428 | $1,218,691 | $1,244,081 | $1,244,081 | |||||||||||||||||||||||||||||||||||||||||||||
| Flat B | $619,713 | |||||||||||||||||||||||||||||||||||||||||||||||||
| 6/F | Flat A | $1,218,691 | $1,218,691 | $1,218,691 | $1,218,691 | |||||||||||||||||||||||||||||||||||||||||||||
| Flat B | ||||||||||||||||||||||||||||||||||||||||||||||||||
| 7/F | Flat A | $499,574 | $1,193,302 | $1,193,302 | $1,193,302 | |||||||||||||||||||||||||||||||||||||||||||||
| Flat B | $592,170 | |||||||||||||||||||||||||||||||||||||||||||||||||
| Roof | $586,371 | |||||||||||||||||||||||||||||||||||||||||||||||||
48.In his valuation report dated 13 March 2013, Mr A Chan states the RDV of the Lot as at 21 February 2013 to be $60,700,000.
49.Mr A Chan’s valuation method can be summarized as follows:
(a) The valuation is conducted on the assumption that the existing building erected thereon is vacant and to be demolished and redeveloped into certain beneficial usages reasonably reflecting its redevelopment potential. He takes into consideration the Government policies and measures announced on 13 October 2010 intended to reduce the gross floor area concessions which would also reduce the building bulk and the marketable gross floor area as well as the relevant Joint Practice Notes (issued by Building Department, Lands Department and Planning Department) and Practice Notes issued by Building Department or Lands Department in January to March 2011 to that effect.
(b) Mr A Chan also takes into consideration the two new measures announced by the Government on 26 October 2012 to address the overheated residential property market, the amendment to Special Stamp Duty, and the introduction of Buyer’s Stamp Duty. Mr A Chan opines that given the new measures are in place, the entry cost and exit cost are very significant for buying and selling residential properties. It would deter purchasers, investors and in particular speculators. The risk to developers in acquiring development land has increased drastically since the new measures came into effect. The rules nowadays are very different and the potential profit from property investment is virtually eliminated by the hefty levies by Government. Since the actual impact to the price level cannot be objectively assessed at the date of valuation, he maintains the "Profit on Land" and "Profit on Cost" at 10% in his residual valuation.
(c) In assessing the RDV, residual method of valuation is adopted by deducting development costs (including construction costs, professional fees, finance costs, etc.) and developer's profit from the estimated gross development value of a completed development. Mr A Chan has carried out the valuation with reference to market comparable sale evidence assuming that vacant possession of the Lot would be readily available upon completion. Time adjustment is applied with reference to the Private Domestic Price Indices by Class and Private Retail Price Indices prepared by Rating and Valuation Department as in February 2013.
(d) Taking into account salient points concerning the use and development of the Lotpursuant to the Government Lease,the Building (Planning) Regulations, the restrictions of the Outline Zoning Plan affecting the Lot and the comparatively higher residential value in the vicinity and the limited retail potential on upper floors, Mr A Chan is of the opinion that a composite building with shops on ground floor with cocklofts and residential units on upper floors should be the optimum development upon redevelopment.
(e) He then uses the residual valuation method to assess the land value of the intended development.
(f) Retail and domestic comparables are identified and analysed, applying relevant adjustments as appropriate.
(g) Mr A Chan uses 5 Ground Floor shop transactions in 4 buildings nearby as his Ground Floor retail comparables. Mr A Chan assumes the cockloft value to be ¼ of the Ground Floor shops. For upper floor domestic comparables, he uses a total of 38 transactions in 4 developments nearby.
(h) The following unit rates are adopted by Mr A Chan in assessing the gross development value:
Ground Floor Retail: $167,000/m²;
Cockloft: $41,750/m²; and
Typical Domestic Unit: $121,000/m².
(i) Mr A Chan then deducts the development costs from the gross development value. Allowing for developer’s profit and discounting for the development period, Mr A Chan determines the land value of the Lot on redevelopment basis.
50.At the hearing, Mr A Chan opines that there is no material change in the RDV between the intervening periods. He confirms his RDV valuation at $60,700,000. I am satisfied that the valuation made by Mr A Chan is fair and reasonable, reflecting the current redevelopment value of the Lot. Thus, the reserve price of the Lot should be fixed at this value.
Conclusion
51.In the circumstance, I make the following determination:
Upon This Tribunal being satisfied that the existing use value of
(i) the 4th Respondent’s two equal undivided 66th parts or shares of and in the building known as Nos. 19 & 21 Wan King Street, Nos. 20 & 22 Wan Shun Street, Kowloon (“the Building”) erected on Section J of Kowloon Marine Lot No. 52 (“the Lot”) together with the right of possession of Flat A & Flat B on 6th Floor (formerly Flat A and Flat B on 6/F of House No. 5 Block C), No. 19 Wan King Street, Kowloon, Hong Kong is $1,218,691; and
(ii) the 6th Respondents’ two equal undivided 66th parts or shares of and in the Building erected on the Lot together with the right of possession of The whole Roof (formerly the roof of House 5 & 7 Wan King Street 6 & 8 Wan Shun Street), Nos. 19 & 21 Wan King Street, Nos. 20 & 22 Wan Shun Street, Kowloon, Hong Kong is $586,371
are fair and reasonable when comparing with the existing use value of the other units, the undivided shares of which belong to the Applicant as assessed in this application (and with the total existing use value of all the units of the Building being $41,334,389) and
Upon This Tribunal also being satisfied that the redevelopment of the Building is justified due to the age or state of repair of the Building and that the Applicant has taken reasonable steps to acquire all the undivided shares in the Lot held by the 4th Respondent and the 6th Respondents respectively
IT IS HEREBY ORDERED that:
(1) That all the undivided shares in Section J of Kowloon Marine Lot No. 52 ("the Lot"), the subject of the Application, be sold by way of public auction for the purposes of redevelopment of the Lot under Section 4(1)(b) of the Land (Compulsory Sale for Redevelopment) Ordinance Cap. 545 ("the Ordinance");
(2) That Mr Ho Chi Kit and Mr Cheung Chi Yu nominated by the Applicant be appointed trustees ("the Trustees") to discharge the duties imposed on trustees under the Ordinance in relation to the Lot, and the Trustees be authorized to charge such remuneration for their services in accordance with the terms set out in the letter from Messrs. Katherine Y.W. OR & Co. dated 3 May 2013;
(3) For the purposes of the sale of the Lot by public auction under section 5(1)(a) of the Ordinance:
(a) The sale of the Lot be sold on the particulars and conditions as to be initialled and approved by the Tribunal;
(b) The reserve price be set at $60,700,000; and
(c) Subject to further extensions that the Tribunal may subsequently allow upon the application of the purchaser of the Lot in the auction sale or successor in title, the redevelopment of the Lot shall be completed and made fit for occupation within a period of 6 years after the date on which the purchaser of the Lot becomes the owner of the Lot as specified by Section 9 and Schedule 3 of the Ordinance; and
(4) Liberty to the Applicant, the 4th Respondent and the 6th Respondents and the Trustees to apply to the Tribunal for further directions under the Ordinance.
| (Kenneth KWOK) | |
| Temporary Member Lands Tribunal |
Mr. C Y Li, SC, instructed by M/S Tony Kan & Co., for the Applicant
The 4th Respondent, absent
The 6th Respondents, absent
Cases cited in this judgment
Other judgments that cite this case