The Incorporated Owners of Gordon Terrace v. Shen Yang Lien and Another

Read the full judgment text of LDBM 291/2011 on BabelCite. This Lands Tribunal judgment was delivered on 27 August 2014.

1. This case is about the water seepage problem at the respondents’ flat. At issue is what was the cause of the seepage and who is responsible to repair the waterproofing layer on the roof above the flat.

Cited by 1 case · Cites 3 cases

Case No.LDBM 291/2011
Court
Lands Tribunal
Date27 Aug 2014
Judge
Case Document
100%Judiciary

LDBM 291/2011

IN THE LANDS TRIBUNAL OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

BUILDING MANAGEMENT APPLICATION NO 291 OF 2011

--------------------

BETWEEN

  THE INCORPORATED OWNERS OF GORDON TERRACE Applicant
  and
  SHEN YANG LIEN 1st Respondent
  TSAI CHU MEI 2nd Respondent

--------------------

Before : His Honour Judge Ko, Presiding Officer of the Lands Tribunal

Dates of Hearing : 30 April, 2, 3, 6 & 8 May, 6, 7 & 21 June, 21 November 2013 and 8 January 2014

Date of Judgment : 27 August 2014

---------------------------------------

JUDGMENT

---------------------------------------

1.This case is about the water seepage problem at the respondents’ flat. At issue is what was the cause of the seepage and who is responsible to repair the waterproofing layer on the roof above the flat.

A.    Background

2.Gordon Terrace at Nos 4-8 Carmel Road, Stanley was built in 1964.  The estate comprises three detached tenement buildings known respectively as Nos 4-4A, 6-6A and 8-8A Gordon Terrace.  Each building has three floors (namely, G/F, 1/F and 2/F) and there are two flats on each floor (eg 2/F of No 6 and 2/F of No 6A).  Each building is served by a central staircase leading from the G/F to the roof.  As the staircase rises above the roof level, it is capped by a staircase hood.

3.The applicant is the Incorporated Owners of Gordon Terrace.  They have engaged a professional manager, Burwell Properties Management Company Limited (“Burwell”), to manage the estate. 

4.The respondents own 2/F of No 6A Gordon Terrace.  According to the assignment respecting their flat, they also have “the sole and exclusive right and privilege to hold use occupy and enjoy … the Roof of the said 6A Gordon Terrace Carmel Road …” directly above their flat (“6A Flat Roof”). 

5.It is common ground that the estate is subject to, inter alia, a deed of mutual covenants dated 29 November 1978 (“the DMC”).[1]The DMC relevantly provides (at clause 12(h)(ii)) that:

“Each of the owners for the time being of the Top Floor Flats shall, subject to the provisions stated have the exclusive use, possession and enjoyment of that portion of the roof above their respective flats exclusively assigned to them and shall be solely responsible for the maintenance repair and renovation of such portion at his own expenses.”

6.The respondents have been behind in payment of management fees and have failed to pay their share of contribution towards the cost of maintaining the communal facilities at the estate as follows:

1 Management fees from May 2008 to April 2011 at $2,600 per month $93,600
2 Management fees from May 2011 onwards at $3,200 per month $3,200 per month
3 Contributions at $10,000 and $4,500 respectively $14,500

7.By this action, the applicant claims against the respondents for the above arrears plus interests and collection charge.[2]

8.In addition, the applicant complains (at §25 of the Re-Re-Amended Notice of Application) that:

“The 2/F Roof has been overloaded by additional building and construction materials which have increased the thickness of the Roof structure by 90 mm at one corner slanting to the opposite end of 145 mm thick. It has caused an additional load of 1.5kN/m2. This load amounted to about 70% of the permissible super imposed load 2.0kN/m2 as indicated in the Building Regulations.”

9.It is the applicant’s case that the respondents have been in breach of regulation 17 of the Building (Construction) Regulations (“Cap 123B”), regulation 3A of the Building (Planning) Regulations (“Cap 123F”) and the DMC in placing “additional building and construction materials” on 6A Flat Roof. The applicant applies for an injunction to oblige the respondents to remove those materials and to reinstate the affected areas.[3]

10.The respondents all along admit the monetary claim of the applicant.  At the trial, they also concede that they have constructed an elevated roof on top of the original roof on 6A Flat Roof (“the Elevated Roof”) which is the “additional building and construction materials” complained of by the applicant.

11.However, they complain about water seepage in their flat alleging (at §36 of the Amended Notice of Opposition and Counterclaim) that:

“By reason of the Applicant’s continued breaches of their duty to maintain and/or repair the aforementioned common parts of the Estate the water leaked into the Respondent’s Property continues to:

(a) constitute a nuisance to the Respondents affecting the use and enjoyment of the Property;

(b) cause physical damage to the Property requiring extensive repairs and to render the Property uninhabitable and un-leasable;

(c)             cause the Respondents to suffer loss and damage including but not limited to the amounts set out in the Schedule of Damage attached as Schedule 1 hereto.”

“[T]he aforementioned common parts of the Estate” is a reference to (i) the waterproofing system at the common staircase, the staircase wall and the concrete curb at the sides of the staircase hood, (ii) floor tiling and the waterproofing system on 6A Flat Roof, (iii) the external wall tiling system at the parapet wall of the roof and (iv) the old waterproofing system on the roof.[4]

12.They counterclaim for the following damages and seek a set-off against the monetary claim of the applicant:[5]

1 Lost rental for the period between May 2007 and August 2008[6] at $40,000 per month $600,000
2 Amount paid to Kingline Contractor Co (“Kingline”) in August 2009 $20,500
3 Loss of rent from September 2009 to April 2010 at the rate of $9,000 per month $72,000[7]
4 Loss of rent from May 2010 to October 2011 at the rate of $76,000 per month $1,368,000
  Total: $2,060,500

B.    The Trial

13.The applicant is represented by Ms Catherine Wong, counsel, and the respondents by Ms Janine Cheung, counsel, at the trial.  Through their effort, the issues that require determination have become more focused and refined.

14.In her closing submission, Ms Cheung confirms that the respondents admit liability over the applicant’s monetary claim and concedes that the Elevated Roof was constructed in contravention of Cap 123B, Cap 123F and the DMC as alleged by the applicant.  The respondents are agreeable to remove the Elevated Roof and to reinstate the affected areas but the parties have been unable to agree on the terms of the injunction.  This is because, as Ms Cheung puts it, “if the Respondent establishes that [the Elevated Roof] was installed to mitigate the damage caused by the leakage, and if the Respondent successfully establishes that the Applicant is liable to repair the original waterproofing layer, the costs of repair should be borne by the Applicant.” 

15.Counsel have jointly prepared a list detailing the issues that require determination.  These issues can be summarized under the following headings:[8]

(1)   What was the cause of the water seepage at the respondents’ flat?

(2)   Is the waterproofing layer on 6A Flat Roof a “common part” of Gordon Terrace?

(3)   Is the applicant liable for causing the water seepage at the respondents’ flat?

(4)   Whether the respondents are entitled to their counterclaim?

(5)   How should the respondents remove the Elevated Roof and reinstate the affected areas?

I shall deal with these issues in turn with reference to the evidence.

C.    The evidence

16.The following witnesses testified for the applicant:

(a)   Ms Chan Wing-lin (“Ms Chan”), an officer of Burwell who is currently responsible for the day-to-day management of Gordon Terrace. 

It should be noted that the officer (one Mr Woo) who actually dealt with the water seepage problem at the material time has already left the employment of Burwell and is not available at trial.

(b)   Mr Wong King-hung (“Mr Wong”), who was the chairman of the applicant between June 2003 and April 2010.

(c)   Mr Robert Collins (“Mr Collins”), who is the chairman of the applicant since April 2010.

(d)   The applicant’s expert Mr Yau Yiu-fong (“Mr Yau”).

17.In addition, the applicant called Mr Ngan Shiu-kin (“Mr Ngan”) to offer rebuttal evidence without objection from the respondents. [9]

18.I am given to understand that the respondents are an elderly couple residing in Taiwan.  They have asked Mr Wang Kah-Sze (“Mr Wang”) to look after their flat.  Aside from Mr Wang, the respondents called Mr Lawrence Lai (“Mr Lai”) of Vigers Building Consultancy Limited (“Vigers”) to offer expert evidence. 

19.The witnesses (both factual and expert) generally adopted their statement or report and were subjected to cross-examination.

20.In my view, I need to take the testimony of the factual witnesses with a pinch of salt.  This is because:

(a)  Ms Chan and Mr Collins became involved with this case relatively recently.  The scope of Mr Ngan’s evidence is confined to rebuttal.  As such, their evidence is of limited assistance.

(b)   The main protagonists are Mr Wong (whose chairmanship coincided with the respondents’ complaint) and Mr Wang (who have been looking after the respondents’ flat).  During the course of the trial, they were asked to recall specific events and conversations that happened several years ago.  They both excused that they had been dealing with the problem on a gratuitous basis.  It is understandable that they have to rely on contemporaneous documents to reconstruct the timeline.  For example, Mr Wang is unable to recall when precisely the water seepage problem began.  He can only refer to a letter dated 20 June 2005 (which is in evidence) that recorded his complaint to say that it must have occurred prior to that date.  On the part of Mr Wong, he is unable to recall the conversation put on record in Burwell’s letter dated 18 December 2007 (which was copied to the applicant).

Unfortunately, the contemporaneous evidence that is still available is lacking in material respects and at times confusing.  For example, some photographs are missing (eg Bundle 431) and some letters have been misdated (eg Bundle 432, 433 and 452). 

(c)   The factual witnesses, given their lack of expertise, are unable to offer much insight into the cause of the seepage.  At one stage, the parties argued over whether the applicant had admitted liability through Mr Wong or in correspondence.  In her oral closing submission, however, Ms Cheung has very fairly asked me to determine this case based on the available evidence.

21.With the above caveats, I find the factual witnesses to be generally honest although I do not necessarily accept their evidence at face value.  I attribute any inaccuracy in their evidence to human frailty to recollect clearly after a while.  I prefer to rely on the contemporaneous evidence, insofar as it is available, to find out what really happened.

22.Turning to the expert evidence, there is no challenge to the expertise of the experts.

(a)   Vigers had been advising the respondents on the water seepage problem prior to Mr Lai’s involvement.  Vigers rendered three reports dated 18 July 2008 (“Vigers 2008 Report”), 4 March 2010 (“Vigers 2010 Report”) and 18 April 2010 (“Vigers Infrared Report”) respectively. 

(b)   Mr Lai has adopted the above reports (see his statement dated 18 December 2012).

(c)   Mr Yau inspected 6A Flat Roof on 16 June 2012[10] and compiled a report dated 16 June 2012 (“Yau’s Report”).

(d)   Mr Lai and Mr Yau jointly inspected the premises on 19 March 2013 and held without prejudice meetings to discuss their differences.  They set out their agreements and disagreements in their joint report dated 30 April 2013 (“the Joint Report”).

23.The expert evidence generally covers the water seepage problem since 2008.  As it turns out, the contemporaneous evidence (especially those prior to 2008) prove to be pivotal to the resolution of this dispute.  Notwithstanding their limitations (noted above), they offer a valuable glimpse of the circumstances at the material time.  Sadly in my view, the parties have not paid sufficient attention to the contemporaneous evidence.  Some of the documents, such as those from the architect (Vincent Lai & Partners (HK) Ltd, “VLP”) and the contractor (Man Shing & Co, “MSC”) for the major renovation in 2006, are difficult to understand.  The difficulty is compounded by the absence of Mr Woo or anyone from VLP or MSC at trial to explain the documents. 

D.    What was the cause of the water seepage at the respondents’ flat?

24.It is common ground that there is a layer of waterproofing material on the original roof (as opposed to the Elevated Roof) on 6A Flat Roof.  This is how Ms Cheung describes the waterproofing layer in her closing submission:

“(1) The waterproofing layer at the roof of the Flat was a 3-ply asphalt felt (which was a flexible elastic material) applied on top of the concrete roof slab (in 3 layers) and which covered the entire roof surface. Reference is made to the Flat Roof Plan (Exhibit A1) in which the roof surface is described thus: ‘One course of Canton tiles on cement and sand screed & 3-ply asphalt felt on RCC roof slabs.’

(2) The waterproofing layer curved upwards and extended some 18 inches up the sides of the parapet walls forming a ‘basin’-like structure, the intention of which was that it would hold water in and permit the same to be channeled along the roof gradient towards the drainage pipes at the rear of the roof. On top of the waterproofing layer was cement sand screeding and on top of the C/S screeding Canton tiles were laid for the protection of the waterproofing layer to mitigate the effects of temperature extremes by insulating the waterproofing from the heat of the sun. The underlying concrete roof slab, the C/S screeding and the Canton tiles were not impermeable to water and as such the 3-ply asphalt layer was the only layer that offered protection against water penetration.

(3) The waterproofing layer was laid as one continuous layer on top of the entire roof covering the roof slabs above both Flats 6 and 6A as well as the water tanks of the building to the rear center of the roof.

(4) In effect, the waterproofing layer acted as a giant basin covering the entire roof top of Block 6 & 6A.”

25.According to Ms Cheung, seepage occurred primarily in two locations inside the respondents’ flat:

(a)   “at the dining room ceiling and the dining room party wall”; and

(b)   “at the ceiling of the living room, master bedroom, master bathroom and the guest bedroom”.

For identification purposes, I shall call the first location “the Dining Area” and the second location “Other Area”.

26.In the end, both counsel accept that the original waterproofing layer has breached and water seeped down from the roof causing the damage in both locations.

27.According to the respondents:

(a)        Seepage in the Dining Area was primarily caused by leakage from the staircase hood which is adjacent to the Dining Area.  Despite their initial denial, they have come to accept at the end of the trial that water had seeped in through the roof by reason of the failure of the waterproofing layer.

(b)        Water had seeped into Other Area from the roof above (again by reason of the failure of the waterproofing layer) and through the external wall tiles of the building (particularly at the parapet walls).

28.The applicant takes a slightly different view.  Its case is that the whole seepage problem (covering both locations) was due to the failure of the waterproofing layer.  The applicant disagrees that leakage from the staircase hood had caused the damage in the Dining Area or that the damage in Other Area was caused by water that had seeped in through the external walls.

29.Thus, the dispute centers around:

(a)   whether seepage in the Dining Area was also caused by leakage from the staircase hood; and

(b)   whether seepage in Other Area was also caused by seepage from the external walls.

30.The following chronology, mostly taken from contemporaneous documents, provides a context for the ensuing discussion:

(a)   Gordon Terrace was completed in 1964.  The applicant has done nothing to maintain the waterproofing layer on the roofs over the years, as it has taken the view that such is the responsibility of the owners of the 2/F flats.

(b)   In about 2005, the applicant was contemplating major renovation and engaged VLP, an authorised architect, to advise them.

(c)   VLP inspected the buildings and reported at the owners’ meeting held on 21 May 2005 that:

“cracks running horizontally were found along the parapet walls on the edge of roof of each block. These cracks allow water to get into the concrete beams and brick structure below the parapet walls. If no remedial action was taken promptly, the present condition would deteriorate to a state that the plaster on the parapet walls may fall down causing property damage and human casualties.”

The owners resolved to take remedial action and commissioned VLP to implement the renovation.[11]

(d)  Major renovation of Gordon Terrace commenced in October 2006.  The works were undertaken by MSC under the supervision of VLP.  The works included retiling of the external walls and renovation of the common staircases. 

Mr Wong recalled at the trial that MSC had retiled the external walls first.  According to Mr Yau’s understanding, a metal mesh (雞仔網) with cement and sand rendering were applied before a layer of new wall tiles was laid on the external walls.  There had been delays, according to Mr Wong, due to shortage of the new tiles and the retiling works did not complete until after the Chinese New Year in February 2007.  MSC then worked on the staircases.

(e) The earliest surviving document that recorded the respondents’ complaint is Burwell’s letter dated 20 June 2005.  It is in these terms:

“本公司接到貴戶投訴,由於樓梯之公眾地方受天雨影響,故每逢天雨便長期積水,故引至滲水現象,導致梯間及其單位亦受到漏水影響。

公司已向 [the applicant] 反映事件,及提交有關相片。法團表示,由於現時本苑已進行商討大維修工程項目,及於二零零五年五月二十一日,業主大會上通過由[VLP]負責跟進及安排維修。法團並將於七月二日,再進行商討工程會議,歡迎貴戶出席查詢詳情。”

The photographs are no longer available.  It may be noted that the complaint at that time was leakage at the common staircase adjacent to the Dining Area.  The applicant dealt with the complaint as part of the major renovation.

(f) The respondents’ flat was let out to a tenant (one Mr James) between March 2005 and April 2007. According to Mr Wang, the tenant moved out in May 2007 without renewing the lease as a result of the water seepage problem.  He then engaged his own contractor to renovate the flat.  No document pertaining to that renovation (eg invoice or contract) survived. 

(g) On 11 August 2007, Mr Wang complained to Burwell that:

“我今日收到裝修該單位的裝修公司通知,由樓梯通往天台的樓道漏水,以導致到我個單位內牆漏水,我裝修公司已將此事通知了大廈管理處,為此,請速查修公眾地方的漏水情形,以免我個單位無辜再受影響!”

That was followed by a letter dated 14 December 2007 from the respondents’ former solicitors reiterating the complaint. 

In reply, Burwell wrote on 18 December 2007 that:

“有關天台漏水事宜,由於為大維修後工程缺點,公司已將情況報告[VLP]跟進事件,承辦商[MSC]已於十二月十五日進行執漏及修補,並已安排於稍後進行試水測試,確定完工後才進行樓梯油漆修補工程。

而法團主席亦即時致電王先生本人,並解答樓梯滲水工程,於兩星期內維修,如仍未動工,法團將交由其他工程公司維修,並交由律師跟進[MSC]之保固金為此工程費用。”

On 21 December 2007, Mr Wang replied as follows:

“貴司18/12/2007給[the respondents' former solicitors]的函,已轉給了我,內容盡悉,但十分遺憾的是,該函內容中有些地方是與事實有很大出入的:

1) 有關天台的樓梯通道漏水一事,我是在11/8/2007致函給貴管理公司胡先生的,要求貴司跟進維修,當時他回[覆]說“即行跟進,如果七天內維修公司不進行維修的話,管理公司會叫律師出信,並且再找另一家維修公司來做。”不但如此,貴公司在上述來函中亦說:已於十二月十五日進行了執漏工程,此點亦與事實不符:從我發信給貴司來算,已4個多月了,但至到今天12月21日我去看樓時卻一切如故,仍未見任何執漏及修補。請問:是怎麼一回事?”

So by the end of 2007, the parties were following up on the seepage at the staircase hood. There was no mention of other affected area.

(h) The next available document is MSC’s report to VLP dated 28 May 2008 in these terms:[12]

“… site inspections have been carried out on 25 April 2008 and 2 May 2008 with Mr Woo of management office and the process was verified & recorded as follows:

4. Staircase of House 6-6A

The water leakage of top ceiling will be handled by us. However, the owner of roof floor has carried out some private waterproofing works. Hence the damage of wall surface is not responsible by our company. (Attached Photos)

…”

The relevant photographs were produced.[13] Reading the report together with the photographs, it is clear that “top ceiling” was a reference to the ceiling of the staircase hood and “some private waterproofing works” was a reference to the Elevated Roof.  This is the first time the Elevated Roof was mentioned in correspondence although the document did not quite state its apparent age (eg whether it was recently installed).

(i) On 19 June 2008, the respondents’ former solicitors wrote to Burwell to complain that “water is still seeping from the roof to the ceiling of the [respondents’ flat]”, enclosing 15 photographs.  Only black and white photocopy of the photographs were produced.[14] Notwithstanding the markings thereon (circles and arrows), water damage is not quite discernable probably due to the poor quality of these photocopies.  All but one photograph were taken of the common staircase.  The remaining one captured a corner of the Dining Area.  This tallies with the findings in Vigers 2008 Report (see the next entry) that the water damage at that time was localized in the Dining Area.

(j) Vigers conducted their first inspection on 18 July 2008.  Thereafter, the respondents’ present solicitors wrote to Burwell on 25 August 2008 that:

“We are also instructed that our client has informed you on many previous occasions of the damage being caused to our client’s apartment at the captioned address due to the water leakage from the rooftop of the staircase and hood. The said staircase and hood is the common area of the building. It is the duty of the Management Company to manage, clean and keep in good repair the said common areas.

In these circumstances our clients have retained the services of [Vigers] to give a report on the said leakage and to [identify] the possible causes of water seepage to the premises.  They have by [Vigers 2008 Report] indicated that ‘the source of water leakage constituting signs of water seepage on the ceiling of the premises was the defective waterproofing system at the lower horizontal surfaces of the rooftop of the staircase hood.’…”

So, by the end of August 2008 the respondents were still complaining about leakage at the staircase hood and water damage in the Dining Area.

(k)   On 5 September 2008, Burwell replied that:

“Concerning the alleged water leakage on the rooftop, both the contractor of the external wall renovation project and the authorised person [VLP] informed us that it is an inherent problem found along the joint line of the concrete rooftop and the brick structure of the vertical walls of your property. These two materials (concrete and brick) are not subject to the same expansion coefficient. An ambient temperature change would result in cracks appearing on the joint line which is located within the boundary of your property. In this regard the Incorporated Owners have no responsibility to address this problem. As you may be aware, the renovation work only covered the common area, in your case, waterproofing and tiling works were carried out on the parapet walls of your roof. Following your complaint, the contractor has made further inspection and carried out remedial works on the parapet walls. However, it is outside the scope of the renovation project to carry out any remedial work on the joint line between the brick wall and concrete rooftop as it is located within the [perimeter] of your property.

Concerning the defect on the stairway landing, we would like to inform you that if weather permits, the contractor has undertaken to complete the repair works before the end of September.”

One should be careful in deciphering this letter.  It is not clear why, given the respondents’ complaint so far, Burwell had digressed into a discussion on “the joint line of the concrete rooftop and the brick structure of the vertical walls”. Burwell might have repeated the opinion of VLP as a preamble.  By the time of this letter, retiling of the external walls had completed and such defect should have been remedied.  That was perhaps why Burwell also wrote that “waterproofing and tiling works were carried out on the parapet walls of your roof”. 

On the other hand, it is quite clear that Burwell was contrasting “the joint line of the concrete rooftop and the brick structure of the vertical walls of [the respondents’] property” which was part of the major renovation with “the joint line between the brick wall and concrete rooftop [which] is located within the [perimeter] of [the respondents’] property” which went beyond the scope of the project.  The former was a reference to the defect identified by VLP in 2005, whereas the latter was a reference to the junction between the Elevated Roof and the parapet walls on the inside of the roof.    The letter did not state what “remedial work” was deemed necessary on the latter.

(l)  On 8 December 2008 and 3 March 2009 respectively, Burwell wrote to the respondents to express that MSC was remedying the leakage at the staircase hood.

(m)  MSC attempted to settle with the respondents directly but the effort was unsuccessful.  In the course of the negotiation, MSC pointed out in an open letter dated 6 August 2009 that:

“根據本公司記錄,貴單位近樓梯位牆身滲水有多原因:

i) 天台腳線嚴重爆裂(見附前相片,附件二),及貴單位已安排重新做腳線(見附現時相片,附件三);

ii) 根據管理公司修補樓梯電線過牆蘇位,發現有大量滲水現象;及

iii) 天台屋樓梯屋頂亦有滲水機會;…”

This is an important document.  First, MSC identified the junction between the Elevated Roof and the parapet walls as a possible source of water seepage.  Secondly, MSC compared the photographs taken in early 2008[15] with those taken in August 2009[16] and noted that the respondents had since applied a layer of waterproofing material to the junction between the Elevated Roof and the parapet walls (“6A天台腳線重做防水”).

(n)   On 7 August 2009, MSC reported to VLP and the applicant that:

“於07-08-2009由本公司連同業主立案法團顏先生、何先生及管理公司胡先生及6A號2/F代表王先生就[歌頓台6A號2/F天台]之圍牆結構作出開鑿檢查,發現圍牆結構已內部爆裂引致內外牆飾面、泥水批盪等崩裂,就上述事宜,依照01-08-2009與業主立案法團會議共悉,證明與本司施工及合約工程無關,現附上有關相片以資閣下記錄及參考。” [17]

That was followed by VLP’s own report to the applicant dated 20 August 2009 stating:

“We refer to [MSC] submitted report … concerning about the defective parapet at roof of No 6A.

The submitted report clearly shows the crack on exterior of parapet wall and the open up inspection photographs reveal the cracked brick wall and plaster to the bottom of parapet. As we previously clarified …, the cause of cracks to the parapet walls were [possibly] due to the different building materials between the parapet brick walls and the external concrete slabs immediately below. Another possible cause of crack was the thermal movement might also deteriorate the interlock of brick bonding and would create cracks between bricks and the junction in between the brick and concrete slab. We also explained that if the waterproofing work on the roof was defective, the water could possibly penetrate the concrete roof slab and external walls to enter into the interior of the premises.

As explained, we would suggest owner to repair the cracked parapet wall as soon as practical to alleviate the possibility of debonding wall tiles due to the cracking of parapet wall physically.  In addition, we would also recommend the issue of Certificate of Making Good Defects to [MSC] for the long time expiry of the Defect Liability Period under the main contract work.”

On 24 August 2009, Burwell wrote to the respondents in these terms:

“(1) We refer to the wall water seepage problem and have sent our maintenance team to check and process some tests. Finally, we found the water seepage problem due to the revised of the electrical circuits and damaged the roof waterproofing membrane by your fitting-out decoration contractor. The water going through the roof [underneath] to the public corridors/walls/staircase. We have rectified the above defects immediately as this period is rainy seasons in Hong Kong even the responsibilities are not from the owner’s committee. And we believe the water seepage problem is solved.

(2) The master bedroom ceiling seepage problem.  We found the problem is related to the building structure issue.  The owner’s committee and the solicitor are following up the above case.  And we will periodically report and updated the progress for your reference.”

The above documents are confusing.  Although they were issued within a few days of each other, they do not speak in unison.  First, MSC noted that the parapet wall had cracked through (“圍牆結構已內部爆裂引致內外牆飾面、泥水批盪等崩裂”).  The photographs annexed to their report suggested that the crack was located just below the coping of the parapet wall near the corner of 6A Flat Roof.[18] VLP did not attend the open-up inspection but relied on MSC’s report and photographs.  They however commented that the crack was located “to the bottom of parapet”.  Secondly, Burwell talked about causes that were not mentioned by MSC or VLP.  Anyway, this letter was the first correspondence recording seepage in Other Area.

(o)   On 4 September 2009, the respondents’ solicitors replied that:

“3. … our clients also wish to inform you that you have failed to maintain and keep in good repair the roof and the outer walls of the captioned building, thereby causing water to seep into our client’s premises. We are informed, and your own contractors have informed you, that water has seeped into the space between the waterproofing material and the ceiling of our clients premises due to cracks on the outer wall and on the inside of the parapet on the roof. The crack on the inside of the parapet has been caused by you or your agents/contractors/representatives affixing some electrical switches on the inner parapet.

Accordingly, our clients now request you to have the roof of the building completely repaired and waterproofed and the outer surface of the walls be completely repaired so that no cracks remain.”

This was the first time the respondents complained about causes other than leakage from the staircase hood.

(p)  On 21 September 2009, the applicant put the following on record:

“2.To put it on record, the matter raised in your letters was discussed at the last Management Committee meeting on 1 August 2009. Mr Wang was invited to attend and put his case to the contractor ([MSC]). To our disappointment neither Mr Wang nor his representative turned up, as it has always been the case when specific complaints lodged by Mr Wang were discussed. The Committee regrets that Mr Wang has refused to use this forum to resolve his complaints amicably.

3.In his absence, the Committee went into length to discuss the matter and came to the following decisions:

(a) the contractor should reopen a small part of the external parapet wall that Mr Wang complained about for the purpose of carrying out an inspection and tracing the source of water leakage;

(b) the inspection must be done in the presence of your client, the authorised person ([VLP]), Burwell and members of the Committee. After the inspection the contractor should reinstate the wall;

(c) Burwell should seek a legal opinion on the responsibility for the maintenance of the parapet wall designated for the exclusive use of your client.

5.The inspection was carried out in the following week. It is clear from the photographs (attached to the contractor’s note of 7 August 2009) taken at the scene that large cracks were found at the interior part of the parapet wall. These cracks are so large that it could not have been possibly caused by the lightweight communal TV aerial tubing affixed shallowly onto the tiles of the parapet wall. I am sure that Mr Wang can testify that the leakage existed long before the renovation work was carried out. As far as I am aware, your client’s tenants have been moving in and out frequently because of the same leakage problem long before the works on the external wall. Furthermore your client had tried to remedy the problem by adding layers of water-proof materials onto his roof. The additional depth and weight of these materials may have caused a loading problem and concern for other owners/occupants.

6.Following the inspection in early August, [MSC] and [VPL] produced separate reports indicating that it is your client’s responsibility to fix the problem.  This is reaffirmed in the advice furnished by Hui and Lam.  Copies of these documents are attached for your information…”

(q)   On 16 and 21 October 2009, Hui & Lam (the applicants’ former solicitors) wrote to the respondents’ solicitors confirming their opinion that it was the respondents’ responsibility (as the owner of 6A Flat Roof) to repair the roof and the interior parapet wall.

(r) The circumstances of the seepage thereafter had been documented in the reports.  The parties basically reiterated their stance in subsequent correspondences. 

D1. Seepage in the Dining Area

31.According to Ms Cheung:

“55. … Wang’s evidence is that there had been serious water leakage from the ceiling at the master bedroom, master bath, guest bedroom and parts of the living room near the master bedroom. He stated that whenever there was serious rainfall the leakage was of such an extent that water could be seen dripping from the ceiling. This had occurred since 2005.

59. Wang’s evidence was that he had installed a new waterproofing and tile layer (“the New WP Layer”) in 2007 after Burwell reneged on an earlier promise to him to deal with the leakage problem. His evidence was that, seeing that the IO was not going to deal with the issue, he instructed contractors and they had installed new tiling and waterproofing. He did not know the specifics of the works but was concerned that the roof should look neat and tidy.

60. In 2007, after James refused to renew the lease and moved out in April 2007, and after the Estate tiling works were completed, the New WP Layer was installed. This was on top of the existing Canton tile and original waterproofing layer (“the Old WP Layer”)…

61. Notwithstanding the New WP Layer, there continues to be leakage problems to the master bedroom, the guest bedroom and the master bathroom in the Flat. By way of further mitigation of the problem, Wang had in 2009 installed plastic troughs under a newly installed false ceiling at the master bedroom for the purpose of collecting and channeling water to a pipe installed in the master bathroom and outside the Flat. Nonetheless water leakage persisted and in 2010 the continued problem was confirmed in infra red tests carried out by the Respondents’ expert and also documented in [Vigers 2010 Report].

62.    Wang’s evidence is that to date, there is still leakage at the aforementioned areas but the system of water troughs and piping under the false ceiling has served to prevent serious water leakage from penetrating beyond the false ceiling.”

32.Water damage in the Dining Area can be seen clearly in the photographs taken by Vigers in 2008 and 2010. 

(a)   The damage documented in 2008 was far worse.  It was most severe “in the areas in proximity to the junction of the suspended ceiling and party wall of the staircase.” [19]

(b)   The situation was much improved in 2010.  Sign of seepage was observed only “at the vertical surface and soffit of the plastered board bulkhead of windows adjacent to the balcony of Living and Dining Room.”[20]

33.Mr Yau was not allowed access to the respondents’ flat during his inspection on 16 June 2012.

34.When Mr Yau and Mr Lai conducted their joint inspection on 19 March 2013, Mr Yau observed that:

“There are no signs of water seepage or damp patches at the ceiling or the soffit and vertical surface of the bulkhead of the balcony or the Living Room or the Dining Room or Bed Rm 1 or the suspended ceiling during the course of inspection. See photos 8(a)-(b), 9(a)-(d), 11 and 12 of Appendix 1.”

Mr Lai disagreed to the extent that he “visually found signs of water seepage at the interior wall surfaces above windows of Bedroom 1 and 3”.  Mr Lai did not otherwise challenge Mr Yau’s observations concerning the Dining Area.  I take it that the experts are on common ground that no seepage was found in the Dining Area during their inspection.  This is confirmed by the photographs at Bundle 660-662.

35.As this is more or less common ground, I accept that there was water seepage in the Dining Area as documented in 2008 and 2010.

36.Given the respondents’ concession at trial, both sides now accept that the failure of the waterproofing layer on 6A Flat Roof was a cause of the water damage in the Dining Area. 

37.Nonetheless, the respondents insist that the seepage problem was primarily caused by the leakage at the staircase hood.  Their case appears to be based on:[21]

(a)   the findings in Vigers 2008 Report, as elaborated by Mr Lai at the trial; and

(b)   the alleged admission of the applicant.

38.According to Vigers 2008 Report, visual inspection carried out on 18 July 2008 revealed that: (i) the rooftop of the staircase hood was coated with a grey-coloured coating; and (ii) the concrete curbs at both sides of the rooftop of the staircase hood were discontinued at the lower horizontal surface of the staircase hood.  The report went on to state that:

“According to our visual inspection, the exposed grey-coloured coating was peeling off, chalked and cracked with water stains. There were signs of water leakage at the ceiling and wall surfaces of the staircases sourced from the lower horizontal surfaces of the rooftop of the staircase hood to the areas directly underneath due to the defective waterproofing system.

Rainwater penetrated through the defective waterproofing system at the rooftop of staircase hood and seeped via the underlying [cement/sand] screeding and porous concrete substrate to the ceiling of staircase. The leaked rainwater then soaked the plastering system of the staircase and exposed the signs of water seepage at the ceiling and wall surfaces, which were in proximity of the ceilings.

Meanwhile, having checked with the latest approved building plans from the Buildings Department, it was revealed that the staircase wall was the party wall of the staircase and the premises. The leaked rainwater was believed to [have] seeped through the porous concrete substrate of the party wall and leaked via the weakest joint of party wall and ceiling slab of the premises and constituted serious signs of water seepage at the suspended ceiling at the premises.

The origin of signs of water leakage, therefore, was believed to be caused by the defective waterproofing system at the lower horizontal surfaces of the rooftop of the staircase hood.”

39.The applicant does not dispute that the staircase hood was leaking at that time.  Ms Cheung appears to think that [t]here is no dispute that there has been leakage of water from the staircase hood area into the interior of the [respondents’ flat] since 2005.” (my emphasis)  This is not entirely correct as (i) the applicant disputes whether leakage from the staircase hood could have caused the water damage in the Dining Area; and (ii) Vigers reported seepage in the Dining Area in 2010 but did not attribute that to leakage from the staircase hood, and no seepage was reported in the Dining Area during the joint inspection in 2013.

40.The applicant challenges whether water from the staircase hood could have entered the respondents’ flat through the party wall adjacent to the Dining Area.  Mr Yau illustrated by means of Exhibits A2 and A3 that the party wall sits on an edge beam at the ceiling of the respondents’ flat.  He said that water travelling down the party wall would have to seep through the edge beam in order to come inside the flat.  In Mr Yau’s experience, he has not seen water soaking through such a 9-inch thick concrete beam.

41.Vigers 2008 Report was signed by one Mr Fung who was a Chartered Building Surveyor of Vigers.  Although the report recorded that Mr Fung had inspected the relevant building records and plans, there was no mentioning of the edge beam or its impact on the water seepage problem.

42.Nonetheless, Mr Lai adopted the conclusion of the report and theorized at the trial that rainwater had entered the building (i) through an opening for electrical box on the party wall above the surface of the roof and/or (ii) by reason of the failure of the waterproofing on the rooftop of the staircase hood, and in either case water travelled down the party wall to the ceiling level of the respondents’ flat.  He indicated in green on Exhibit A3 the possible courses of water ingress.  He explained that if water was collected or trapped between the waterproofing layer and the concrete roof slab for a period of time, it would flow through weak points or cracks in the edge beam and/or the concrete ceiling slab into the flat.  He said he has encountered many prior instances where water had flowed underneath the waterproofing layer of the roof.  He disagreed with Mr Yau and opined that water could indeed seep through a 9-inch concrete edge beam. 

43.I begin by commenting on the respondents’ concession.  The respondents have lately conceded that breach of the waterproofing layer on 6A Flat Roof was an effective cause for the water damage in the Dining Area. 

44.In my view, the concession was fairly made having regard to the following evidence:

(a)   The whole basis of Vigers 2008 Report was visual inspection.  I agree with Mr Yau that visual inspection as a test is not sufficiently reliable to exclude the possibilities of a leaking roof.  Proper water seepage test such as dye colour test should have been carried out.

(b)   Vigers still reported water damage in the Dining Area in 2010 (albeit to a much lesser extent) but did not attribute the problem to leakage from the staircase hood. 

45.However, the concession has effectively destroyed the thrust of Vigers 2008 Report. 

46.One of the crucial findings of the report was (at §5.2A(1)) that:

“The general condition of the roof of the premises was sound and no sign of water leakage was found during our visual inspection. (Photo 1) We believed that the waterproofing system of the premises were in good condition.”

So, water had to enter through another channel and the report identified the party wall as the conduit.  The concession has contradicted the clear finding of Vigers and provides an explanation for the water damage inside the respondents’ flat. 

47.The respondents have offered nothing further in terms of evidence to confirm the existence of a second source. Mr Lai did not perform any test to substantiate his theory.

48.More importantly, I have some doubts about Mr Lai’s theory.  It took a lot of water to produce the kind of damage shown in the photographs in Vigers 2008 Report.  Mr Lai suggested that water had come (i) from an opening on the party wall above the surface of the roof; and/or (ii) through the defective waterproofing of the horizontal surface of the staircase hood. 

49.On the face of it, Mr Lai’s first suggestion is supported by Burwell’s letter dated 24 August 2009 in which it was stated “the water seepage problem due to the revised of the electricity circuits”.  Prior to that, MSC had quoted Burwell to say that “根據管理公司修補樓梯電線過牆蘇位,發現有大量滲水現象” (see MSC’s letter dated 6 August 2009).  However, neither MSC nor VLP attributed that to be a cause after the open-up inspection on 7 August 2009. 

50.More importantly, I note from Exhibit A3 and photographs 2 and 3 in Vigers 2008 Report[22] that the lower horizontal surface of the staircase hood actually protrudes outward forming a cover over the vertical surface of the party wall.  The cover should enable water to flow off the staircase hood onto the roof and away from the party wall.  Whilst I do not

rule out the possibility illustrated by Mr Lai on Exhibit A3 that water may drip around the entire surface of the cover (even its underside), the cover should channel most of the water away from the surface of the party wall especially during heavy downpour.  It is rather unlikely that so much water could have entered the respondents’ flat through this covered opening on the vertical surface of the party wall.

51.Turning to the horizontal surface of the staircase hood, whilst the parties agree that it was leaking at the time, there was no attempt to identify where the/those leak(s) was/were.  It appears from photographs 5-8 in Vigers 2008 Report that all three walls surrounding the staircase (including the party wall to the right) had signs of water seepage.  The paints on the walls in the middle and to the left had clearly peeled off (see photographs 6[23] and 7) but peeling paint was not too apparent on the party wall (see photograph 8[24]).  That suggests that the other two walls were more affected by water seepage from the staircase hood than the party wall.  Water generally flows from a high point to a low point and the walls around the common staircase are porous.  It is unlikely that water that had seeped into the middle and the left walls would have traveled sideways onto the party wall to the right.  It took a lot of water to produce the damage documented in Vigers 2008 Report.  However, there was no obvious sign of water collecting or accumulating on the party wall.[25]  If so much water had collected or accumulated at the ceiling, it would have flowed down the suspended ceiling and lights inside the flat but that was not apparent from photograph 10.[26]  The argument that the applicant might have admitted liability does not advance the respondents’ cause any further.  I am not convinced by Mr Lai’s theory.

52.Before leaving this area, I should briefly comment on (i) the discontinued concrete curb and (ii) the missing 2.5 inch cast iron drain pipe which featured prominently in Mr Lai’s evidence.  In my view, they do not quite point to a second source. 

53.The point of the discontinued curb, as explained in §6.0 of Vigers 2008 Report, was that it would allow “large amount of rainwater flowing from the staircase hood to the floor surfaces of roof level of the premises and possibly caused the accumulation of rainwater at the roof.”  Likewise, Mr Lai explained that the purpose of the drain pipe was “to channel water onto the roof (where it would flow along the roof gradient towards the watercourse at the rear of the roof where there were drainage pipes).”[27] The absence of the drain pipe would mean that water would flow directly onto the roof surface.

54.If the waterproofing layer on 6A Flat Roof was functioning properly, water flowing off the staircase hood onto the roof surface would have flowed along the roof gradient to the drainage at the rear of the roof and be drained away.  So, the discontinued curb and the missing drain pipe is no evidence of a second source.  The effective cause of the water seepage problem was still the failure of the waterproofing layer.

55.All in all, the respondents have not convinced me that the water damage in the Dining Area was due to leakage from the staircase hood.

56.I therefore find that the damage in the Dining Area as documented in 2008 and 2010 was caused by the failure of the waterproofing layer on 6A Flat Roof.

D2. Seepage in Other Area

57.Vigers 2008 Report only reported damage in the Dining Area.  There was no mentioning of other damage inside the respondents’ flat.  Seepage inside the master bedroom was first noted in Burwell’s letter dated 24 August 2009.  Seepage in Other Area was also reported in 2010 (in Vigers 2010 Report and Vigers Infrared Report) and 2013 (in the Joint Report).

58.Both experts agree that seepage in Other Area was also due to failure of the waterproofing layer on 6A Flat Roof. What divides them is whether there was a second cause as contended by the respondents, namely, that water had also penetrated through the external wall tiles of the building particularly at the parapet walls.

59.The respondents rely on the findings in Vigers 2010 Report and Vigers Infrared Report for their contention.

60.In terms of Vigers 2010 Report, visual inspection on 4 March 2010 revealed amongst other defects: [28]

(a)   “Blister at waterproofing layer of parapet wall at Roof was detected. (Photo 4)”;

(b)   “Cracked external wall tiles were detected. (Photo 6)”; and

(c)“Signs of efflorescence were found at tile grouts of external wall. (Photo 6-7)”.  

Vigers then offered this explanation:

“Meanwhile, rainwater might be punched into the external wall substrate through the minor crack and tile grouts at the external wall tile to constitute the signs of water seepage, which was originated from the junction of roof slab and wall, at the ceiling and wall surfaces above the windows of the Bed [Room] 1 and Living and Dining Room. In addition, the penetrated rainwater was partly accumulated behind waterproofing layer in forming blister at the parapet wall and returned to the external wall surface carrying soluble salts of cementitous substrate to form efflorescence.”

61.Infra-red thermographic inspection conducted on 18 April 2010 identified some debonded and water-trapped areas on the external walls.[29]

62.Based on the above, Mr Lai opined that, “migration of rainwater from the defective areas of the external side of the parapet wall seeping via the substrate of the external wall downward to the interior of the Premises causing sign of water seepage at the junction of ceiling and wall or ceiling of the interior of the Premises.”  He added that, “lack of proper external wall maintenance to the defective external wall tiling system exaggerated the problem of water leakage to the interior ceiling and wall surfaces adjacent to the external wall.”

63.Mr Yau’s reading of the reports was that:

“7.9 Having read [Vigers Infrared Report], Mr Yau opined that it only indicated some areas on the external wall below the horizontal line of the parapet wall showed some signs of irregularities which could either be a wet zone or a spalling concrete zone. Spalling concrete means honey comb that might exist in a patch of concrete, resulting from carbonation of cement based materials from air with years. Moisture plays a major role in the spalling of concrete. Water seepage sources can only be identified after water test applied at suspected areas. According to [Vigers Infrared Report], it did not show such water spraying test had been carried out.

7.10  There was no solid evidence that the wet zone (if it was not spalling concrete area) would let external water penetrated through the external wall into the interior of the flat unit or R’s premises.  At least, [Vigers Infrared Report] did not show any infra-red testing results from both interior and exterior of the same area of the Premises.  This would eliminate the possibility that water could penetrate from the external wall into the inner wall of the premises.”

7.11  The Applicant’s Expert used a metal rod to tap on the alleged debonded wall tiles but none of them emitted any hollow sound which is a sign of debonding. Moreover, the Applicant’s Expert has been informed by the IO that a metal mesh (雞仔網) and cement and sand rendering were added on the external wall before the new wall tiles were laid.  It is very unlikely that rainwater can penetrate through the wall tiles and the cement coating into the interior wall of R’s premises.  I did not observe any signs of water marks in those areas identified in Photo R1 of Mr Lai’s statement.”

64.Mr Lai disagreed and said that:

“… [Vigers Infrared Report] recorded the existing condition of the external wall. The water spraying test would distort the actual condition of the parapet wall.

Thermographic testing showed that those parts of the ceiling inside the Premises that exhibited lower temperatures corresponded to those areas of external wall where signs of irregularity were recorded (See IR 6-22 of [Vigers Infrared Report].)

There is wide range of defects causing areas of debonding such as spalling concrete or debonded render or debonded tiles. [Vigers Infrared Report] did not identify and specify the specific type of defects. However, as revealed by the joint inspection, cracks and efflorescence were visually found on the external wall above the Premises that might cause signs of water leakage to the Premises.

… The Respondent’s Expert observed 3 nos of areas with signs of water seepage at the interior of the Premises in which the external wall of outside 2 nos of which were found symptoms of efflorescence and cracks were found on the external wall.”

65.I am not surprised that there are cracks on the parapet walls.  VLP reported cracks on the external walls of all buildings back in 2005.  At that time, VLP warned that if no remedial action was taken, the plaster on the parapet walls might fall off causing personal injury and/or property damage.  That prompted the owners to undertake the major renovation in 2006.

66.What was done in terms of the major renovation was to cover the external walls with a layer of new wall tiles with metal mesh and cement and sand rendering.  It is apparent from the photographs in evidence that the protective layer was extended to the coping of the parapet walls[30] and covered the external surface of the party walls.[31]  Mr Wong explained that the applicant had decided to cover the party walls as well to prevent water from seeping into the common staircase.[32]  So, this new protective layer should have some water resistant function.  This was confirmed by Burwell’s letter dated 5 September 2008[33] and the captions Mr Yau inserted on his photographs 7(a)-(c) in the Joint Report.[34]

67.Mr Wong also explained that since the applicant had taken the view that it was the responsibility of the 2/F owners to maintain the parapet walls on their flat roof, nothing was done in 2006 to repair the cracks in the parapet walls.  That explains why cracks could still be observed during the open-up inspection in August 2009. 

68.I understand from the experts that the parapet walls are constructed of bricks and are porous.  As such, water can indeed penetrate the parapet walls even though they may be in pristine condition (ie without cracks).  Since 2006, the external walls (and the coping of the parapet walls) have been covered by a protective layer which is water resistant. What is more pertinent is whether water had broken through this protective layer of wall tiles, metal mesh and cement and sand rendering.

69.As I have noted above, the contemporaneous evidence from August 2009 is confusing.  I can only look at the photographs annexed to MSC’s report to try to appreciate the circumstances.  MSC opined that the parapet wall had “cracked through” and the photographs suggested that the crack might be located below the coping of the parapet wall near the corner of the roof.  Mr Ngan confirmed that the photographs depicted the location of the open-up inspection which was on the inner side of the parapet wall and no open-up inspection had been done on the external wall.  Photograph 6[35] in Vigers 2010 Report captured a grayish zigzag line on the external wall running diagonally across the corner and infra-red scan no 5[36] in Vigers Infrared Report revealed a debonded area in or around that area.  However, infra-red scan no 30[37] did not reveal any irregularity on the inner side of the parapet wall near that area.  In my view, the evidence does not quite confirm that the parapet wall had cracked through.

70.It is true that Vigers Infrared Report has indentified some debonded areas and water-trapped areas on the external walls.  However, some of these defects were located below the ceiling level of the respondents’ flat.  Water could not have entered through these defects and then travelled upward to produce the damage documented.

71.The infra-red scans also revealed long strips of debonded area on the inner side of the parapet walls near the curb.[38]  Unlike the external walls, the inner surface of the parapet walls is exposed below the coping and not covered by any protective layer.  The defects on the inner surface of the parapet walls appear to be more extensive than those scattered around the external walls.  Strangely, Mr Lai only tried to match the water damage with the defects on the external walls.  I am puzzled as to how he could rule out the possibility that water had entered through the defects on the inner surface of the parapet walls.

72.I do not think one can really tell by merely looking at these infra-scans whether water had entered through any of the debonded areas and water-trapped areas identified in Vigers Infrared Report.  Mr Lai has come to accept that there may be several explanations for such defects and the report did not quite specify what they were.  Further tests should have to be done to determine if any of these defects would permit water to enter the building.  That was not done by the respondents.  On the part of the applicant, Mr Yau checked on the debonded areas on the external walls by means of a metal rod and found no irregularity.  He also observed that “[t]he efflorescence of the sealant between the external wall tiles (as shown in photo A2, Appendix of Mr Lai’s statement) flowed out onto the wall tiles.  It does not indicate rain water can penetrate into the interior wall of R’s premises.”

73.All in all, the respondents can only point to some cracks and efflorescence on the surface of the external walls.  Bearing in mind that there is a protective layer of wall tiles, metal mesh and cement and sand rendering on the external walls, there is insufficient evidence to establish that water had in fact penetrated these materials.

74.Furthermore, I suspect that the damage around the windows might have something to do with the windows.  

75.There is an invoice in evidence recording the following works at the respondents’ flat in September/October 2009:

“檢查客廳及各房間室內天花及牆身,窗門頂與外牆夾縫,木窗帘殼因颱風期間豪雨出現漏水而損壞及有嚴重水漬情況並與現租客Ms Paloma解釋維修[程]序及進度(日期:09年9月17日晚上)”

“大雨後維修客廳及主人房室內天花及牆身;窗門頂與外牆夾縫漏水,木窗帘殼水漬;主人房天花批灰及牆身,木窗帘殼翻油乳膠漆(日期:09年10月8日)”

76.Vigers discovered water damage near the windows in March/April 2010.[39]  The respondents then changed the windows in the living room and the master bedroom.[40]  By the time of the joint inspection in 2013, Mr Yau found:

“6.1 There are no signs of water seepage or damp patches at the ceiling or the soffit and vertical surface of the bulkhead of the balcony or the Living Room or the Dining Room or Bed Rm 1, or the suspended ceiling during the course of inspection. See photos 8(a)-(b), 9(a)-(d), 11 and 12 of Appendix 1.

6.4 Some peeling off paints and damp patches observed at the soffit near the top of the window casing and beneath the curtain rods of Bed Rm 3 which could be caused by a faulty installation of a drip edge of the window frame.  See photo 10 of Appendix 1.”

77.Mr Lai said he “visually found signs of water seepage at the interior wall surfaces above windows of Bedroom 1 and 3.”  The applicant’s photographs annexed to the Joint Report clearly support Mr Yau’s observations[41] whereas the respondents’ photographs are of such a poor quality that they do not reveal any sign of seepage in the master bedroom (or Bedroom 1).[42]  It does appear that the changing of the windows in the living/dining room and the master bedroom has alleviated the water seepage problem there.

78.Both experts still observed signs of seepage around the window in Bedroom 3 at the back of the respondents’ flat.  This was captured by photograph 10 taken by Mr Yau.[43] It can be seen from the photograph that the respondents have retained the original brownish window in that bedroom and seepage around the window has continued.

79.Since the parties have not debated this aspect fully, I shall refrain from expressing any conclusion.  The respondents may want to follow up on this if they want to rid their premises of water seepage.[44]

80.On the existing evidence, I find that the damage in Other Area was also caused by the failure of the waterproofing layer on 6A Flat Roof.

D3. The importance of reading the above findings in context

81.It is important to appreciate that the above findings are based on Vigers 2008 Report, Vigers 2010 Report, Vigers Infrared Report and the Joint Report.  These reports are all post-2008.

82.Whilst I accept (based on Burwell’s letter dated 20 June 2005) that there was water seepage in 2005, there is nothing for me to appreciate the circumstances prior to 2008.  Mr Wang did not engage any expert at that time to investigate the seepage and/or document the damage. The earliest photographic evidence was dated June 2008.[45]

83.Given VLP’s assessment in May 2005, the seepage in 2005 might have something to do with the horizontal cracks along the parapet walls.  It might also have something to do with the windows as discussed above.  There is now no means of finding out the real cause of the seepage at that time.

84.Furthermore, it is Mr Wong’s evidence that the respondents had repeatedly renovated their premises over the years.  Mr Wong’s evidence is not challenged by the respondents and is indeed confirmed by other evidence.

(a)   Mr Wang insisted that there was seepage in Other Area back in 2005.  Mr Collins also recalled that Mr James had told him that there had been seepage in the bedrooms during his tenancy between March 2005 and April 2007.  

Mr Wang engaged his own contractor to renovate the premises after Mr James had moved out.  When the respondents’ former solicitors and Vigers tried to document the damage in June/July 2008, they only found water damage in the Dining Area.      

(b)   The respondents’ claim for the renovation cost in 2009 is clear evidence of renovation between Vigers’ inspections in 2008 and 2010.

(c)   One can also observe from the photographs annexed to Vigers 2010 Report and the Joint Report that the respondents have changed the windows in the living/dining room and the master bedroom between the inspections in 2010 and 2013.

85.Consequently, one cannot rely on the photographs taken in 2008 to postulate as to the circumstances prior to that, and the water damage captured in the reports respectively dated 2008, 2010 and 2013 are not necessarily connected.

86.To be precise, I find that:

(a)   The water damage in the Dining Area as documented by Vigers 2008 Report in 2008 was caused by the failure of the waterproofing layer on 6A Flat Roof.

(b)   The water damage located in the Dining Area and Other Area as documented by Vigers 2010 Report and Vigers Infrared Report in 2010 was caused by the failure of the waterproofing layer on 6A Flat Roof.

(c) The water damage in Other Area as documented by the Joint Report in 2013 and which is continuing according to Mr Wang is also caused by the failure of the waterproofing layer on 6A Flat Roof.

D4. What was the cause of the failure of the waterproofing layer?

87.I now come to the most pertinent question: What has caused the waterproofing layer on 6A Roof to fail?

88.Notwithstanding their initial denial,[46] the respondents have come to admit that they have installed the Elevated Roof.  Mr Yau offers the following opinion on the effect of imposing the Elevated Roof on the original roof surface:

“The only conclusion of Mr Yau is that the R’s Roof has been filled up with new floor finishes or materials including waterproofing membrane, cement and sand screeds. According to Mr Yau, the extra loads of the patching up works could have adversely affected the serviceability and durability of the Premises and the whole Block because the building is too old to be able to sustain heavy additional loads which are over 50% of the original overall loads. Mr Yau is of the view that further cracking will be expedited as a result of such continuous overloading and the damage to the water proofing system of the floor surface level of the R’s Roof will occur again.”

89.In her closing submission, Ms Cheung accepts that “there is some evidence that the imposition of an additional load would cause the roof slab and the Old Layer to bend or wrap to a greater degree”.  However, she argues that, “the Old WP layer was ALREADY defective before the NEW WP Layer was installed in 2007”.  (her emphasis)

90.But, where is the evidence that the Elevated Roof was (i) installed in 2007 and (ii) after seepage had occurred?

91.The evidence that the Elevated Roof was installed in 2007 came from Mr Wang’s oral testimony at trial.  He said that it was installed after the retiling of the external walls and after the applicant had reneged on its promise to remedy the seepage problem.

92.The respondents initially denied having done anything to the roof.  It was also not admitted in Mr Wang’s witness statement dated October 2012.  Mr Wang only lately owned up to the respondents’ expert (Mr Lai) of having installed the Elevated Roof.  This is how Mr Lai recorded his instruction in the Joint Report dated April 2013:

“[Mr Wang] recalled that the repair works to the Roof had been completed before Vigers’ 1st inspection on 18th July 2008 in which new bitumen felt, c/s screeding and floor tiles were laid on top of the existing roof finishes.”[47] (my emphasis)

Even then, Mr Wang did not tell their own expert that the Elevated Roof was installed in 2007.

93.Mr Wang’s complaint letter dated 11 August 2007 made no mentioning of any work on the roof.  When he was cross-examined as to how he could suddenly remember the timing, he was unable to say much.  He could not tell how soon after Mr James had moved out that he embarked on such works.  He could only say that he had paid a deposit to Burwell for such works.  Given that the respondents had renovated the interior of their premises at about that time, the payment of the deposit may not be a reliable pointer to help Mr Wang to recall the timing of the Elevated Roof. 

94.As such, the respondents’ case that the Elevated Roof was installed in 2007 remains a bare assertion without supporting evidence.  It is also unreliable as Mr Wang only recalled the timing at the trial without reasonable explanation.  Most importantly, there is evidence contradicting the allegation.

95.If the respondents had only been complaining about leakage from the staircase hood in correspondence between 2005 and 2009,[48] what was the incentive to construct the Elevated Roof over the entire roof in 2007?

96.Mr Wang and the respondents’ former solicitors were still pressing the applicant to resolve the seepage problem towards the end of 2007 (see the solicitors’ letter dated 14 December 2007 and Mr Wang’s letter dated 21 December 2007).  There was no mentioning of any work done by the respondents themselves on the roof or any plan for such works.

97.Mr Wang claimed that he had only decided to install the Elevated Roof after the applicant had reneged on its promise to remedy the seepage problem.  But Burwell was still promising the respondents that it would pressurize MSC to resolve the problem at the end of 2007 (see Burwell’s letter dated 18 December 2007). 

98.Major renovation at Gordon Terrace started in October 2006.  According to Mr Wong, MSC completed retiling the external walls in February 2007 and thereafter renovated the staircases.  During that time, Mr Wang and the respondents’ solicitors persisted in their complaints.  The applicant had instructed MSC (and VLP) to follow up.  According to the contemporaneous correspondence, MSC did not stop dealing with the problem until 2009.

99.Therefore, Gordon Terrace was under renovation all through 2007.  The renovation work towards the second half of 2007 concentrated on the staircases of the estate and included investigation and remedial works to address the respondents’ complaint.  With all these works going on and MSC focusing on the respondents’ complaint, it is rather unlikely that the respondents could have installed the Elevated Roof without anyone noticing. Furthermore, if the respondents had only just installed the Elevated Roof themselves but failed to resolve the seepage problem, it would have been natural for them to ask their contractor to follow-up with MSC (which was on-site working on the problem) but that is not the respondents’ case. 

100.I reject the respondents’ case that the Elevated Roof was installed in 2007.

101.If the respondents did not install the Elevated Roof in 2007, when did they do it?  There is no direct evidence establishing the timing of such works.  Mr Wong’s suggestion (in §13 of his witness statement) that the Elevated Roof was installed in the summer of 2006 is apparently without basis.  Given that the respondents’ flat was let out between March 2005 and April 2007 and it is not the respondents’ case that they installed the Elevated Roof during Mr James’ tenancy, the respondents must have installed the Elevated Roof before the commencement of Mr James’ tenancy in March 2005 and I so find. 

102.In my view, the finding that the respondents installed the Elevated Roof before March 2005 provides the key to unlock the mystery over the water seepage problem. 

103.As Ms Cheung has recounted, the original waterproofing layer curved upward along the edges of the parapet walls to form a basin-like structure to keep water on the roof from entering the building.  The imposition of the Elevated Roof, as opined by Mr Yau, has the effect of overloading the roof and cracking the waterproofing layer.

104.The Elevated Roof itself is a continuous layer covering the entire 6A Flat Roof.  According to Mr Wang, it has some waterproofing function.  As such, the most likely places where cracks would first develop would be along the edges of the Elevated Roof.

105.Mr Yau has noted from the photographs taken by MSC in April/May 2008 that “no waterproofing coating was laid on the edge of the parapet wall and the floor surface level of the roof”.  In other words, the contractor who installed the Elevated Roof for the respondents did not bother to waterproof the edges.  If cracks developed along the edges, the basin-like structure of the original waterproofing layer would breach.  Water could then enter the building through the non-waterproofed edges.

106.There is indeed evidence that water had in fact entered the respondents’ flat through the edges.  It is apparent from photographs 10-12 in Vigers 2008 Report[49] that water damage was most severe near the junction between the ceiling and the party wall.  One can appreciate from Exhibits A2 and A3 that the party wall extends upwards onto the roof and borders with the Elevated Roof.  In my view, the location of the damage is consistent with water entering through the non-waterproofed edges.  The respondents’ invoices (quoted below) confirmed that there were cracks along the edges in 2009.  That explains why the correspondences in 2008 and 2009 referred to the junction between the Elevated Roof and the parapet walls (eg Burwell’s letter dated 5 September 2008 and MSC’s letter dated 6 August 2009).

107.The respondents subsequently remedied such defect by applying waterproofing coating to the edges of the Elevated Roof.[50] There is an invoice dated 8 September 2009 recording the following:

“修補天台向內圍牆(Parapet Wall)牆腳裂痕及損毀牆面(約1呎高)並番油防水物料連工包料(日期:09年6月1日)”

There is another invoice for the following works:

“天台向內圍牆(Parapet Wall)及牆腳裂痕...翻油防水物料連工包料(日期:09年9月18日)”

108.Thereafter, Vigers’ inspection in March 2010 revealed significantly improved condition in the Dining Area and water damage was no longer localized in the vicinity of the junction between the ceiling and the party wall.[51]

109.I therefore find that the imposition of the Elevated Roof sometime before March 2005 had cracked the waterproofing layer along the edges (especially along the edge above the junction between the ceiling and the party wall) allowing water to flow down and into the respondents’ flat (and without the need to go through the edge beam) causing the damage documented in Vigers 2008 Report.

110.Water damage in 2008 was most severe at the corner because large amount of water had slanted from the staircase hood onto the roof through the discontinued curb and by reason of the missing drain pipe.  That does not mean that the discontinued curb or the missing drain pipe had contributed to the water damage.  But for the cracking of the waterproofing layer, water on the roof surface would have followed the gradient of the roof to the other side and drained off.

111.The respondents waterproofed the edges in 2009.  However, by the time of Vigers 2010 Report “cracked tiles and signs of efflorescence at tile grout” were noted on the Elevated Roof indicating that the Elevated Roof had by then aged and become defective.  The Elevated Roof must have produced further cracks in the waterproofing layer underneath. As noted above, both experts agree that the water damage documented in 2010 was caused by breach of the waterproofing layer on 6A Flat Roof. 

112.Mr Wang’s remedial efforts over the years (such as changing the windows and installing plastic troughs) without removing the Elevated Roof (which continues to impose undue pressure on the waterproofing layer) and mending the original waterproofing layer (which is leaking) did not really resolve the seepage problem.  Water continues to seep from the roof into the respondents’ flat as documented in the Joint Report and testified by Mr Wang.

E. Is the waterproofing layer on 6A Flat Roof a “common part” of Gordon Terrace?

113.Both parties accept that the waterproofing layer on 6A Flat Roof has breached.  They, however, are in dispute over who has the responsibility to repair it.

114.In her closing submission, Ms Wong advanced the following arguments:

(a)   The Assignment and the DMC (both instruments have been registered in the Lands Registry) have specified/designated the waterproofing layer to be for the exclusive use, occupation or enjoyment of the respondents together with 6A Flat Roof.

(b)   The DMC provides that the owner having the exclusive use of a flat roof should be responsible to maintain and repair the waterproofing layer embedded therein.

(c)   The waterproofing layer on 6A Flat Roof only serves the respondents’ flat below and does not constitute a “common part” as defined in BMO.

(d)   It is practically impossible for the applicant to maintain and repair the waterproofing layer.  As the waterproofing layer is sandwiched between the ceiling of the respondents’ flat and the surface of the respondents’ roof, the applicant is unable to access the waterproofing layer without trespassing on the respondents’ property.  Furthermore, the respondents have kept 6A Flat Roof under lock and there is no right for the applicant to access the roof.

115.In the event that I find that the waterproofing layer is a common part of Gordon Terrace, her fallback argument is that:

(e)   The respondents’ installation of the Elevated Roof constitutes novus actus interveniens so much so that the applicant ceased to be liable.

(f)   The DMC provides that the owners of each building should be responsible to maintain and repair the common facilities of that building.  As such, the respondents should have gone after the owners of Nos 6-6A Gordon Terrace (as opposed to the applicant) for the maintenance and repair of the waterproofing layer on 6A Flat Roof.

116.In my view, it is imperative to appreciate the important function of the waterproofing layer.  It is there to keep water (eg rain) from entering the building through the roof. 

117.Ms Wong tries to confine the benefit of the waterproofing layer to the flat below.  She prays in aid Mr Yau’s comment that concrete should be water-resistant under normal wear and tear and argues that the concrete ceiling slab on each floor should already provide adequate protection against water seepage from above.  She submits that the 2/F flats need extra protection (in terms of the waterproofing layer) because the roof is exposed to ambient temperature changes which may cause the concrete ceiling slab to crack. 

118.I do not understand Mr Yau to be saying that concrete as a building material is impermeable to water.  What he is saying is that concrete given its density is more water-resistant than other building materials (eg bricks) and he has not seen water permeating a 9-inch concrete beam before.  In any event, it is common ground that concrete may crack and water actually seeped through the concrete roof slab into the respondents’ flat below in this case.  Indeed, Ms Wong’s argument on the need for extra protection for the 2/F flats is also premised on the fact that water may percolate through cracks in the concrete ceiling slab.

119.Once water has breached the waterproofing layer and “entered” the building, it can seep through cracks and pores to other parts of the building.  It is not just the flat immediately below that would be affected.  That explains why the waterproofing layer has to be, according to its original design, a continuous layer covering the entire roof and not just the two flat roofs.

120.Thus viewed, the waterproofing layer serves an important function to protect the whole building from water seepage although it is partly embedded in the flat roofs belonging to individual owners.  It is a separate fixture and has nothing to do with the use, occupation and enjoyment of the flat roofs.

121.Section 18(1)(a) of the BMO provides that the applicant shall maintain, inter alia, the “common parts” of the estate in a state of good and serviceable repair and clean condition. 

122.Section 2 defines “common parts” to mean: (i) the whole of a building, except such parts as have been specified or designated in an instrument registered in the Land Registry as being for the exclusive use, occupation or enjoyment of an owner; and (ii) unless so specified or designated, those parts specified in Schedule 1 of that ordinance.

123.Two items in Schedule 1 are of particular relevance:

(a)   Lighting apparatus, air conditioning apparatus, central heating apparatus, fire fighting equipment and installations intended for the use and benefit of all of the owners generally and any room or chamber in which such apparatus, equipment or installation is fitted or installed. (item 10)

(b)   Fixtures situated in a flat which are used in connection with the enjoyment of any other flat or other portion of the building. (item 11)

124.In my view, the waterproofing layer falls squarely within the terms of item 11.  It is a fixture situated in a flat[52] (ie the respondents’ flat roof) which is used in connection with the enjoyment of other flat or other portion of the building (namely, to protect Nos 6-6A Gordon Terrace from water seepage).[53]

125.Ms Cheung initially relied on item 10 as well.  However, the particular setting of Gordon Terrace (ie detached tenement buildings) is such that the waterproofing layer of one building cannot be intended for the use and benefit of the owners in the other buildings.

126.Ms Wong tries to argue that the waterproofing layer embedded in the 6A Flat Roof had been assigned to the respondents along with the flat roof by means of the Assignment and the DMC. 

(a)   In terms of the Assignment, the respondents were assigned “the sole and exclusive right and privilege to hold use occupy and enjoy … the Roof of the said 6A Gordon Terrace”. (my emphasis)

(b)   Clause 5 of the DMC similarly provides that: “The owner or owners of the 2nd floor flats of the said building shall be entitled to the exclusive use occupation and enjoyment of the corresponding part of the Roof thereof…”. (my emphasis)  The First Schedule to the DMC also referred to the fact that the Second Owner (defined therein) had the exclusive use, occupation and enjoyment of, inter alia, “SECOND FLOOR and ROOF of Nos 6, 6A, 8 and 8A Gordon Terrace.” (my emphasis)

Clause 12 (h)(ii) also provides that: “Each of the owners for the time being of the Top Floor Flats shall, subject to the provisions stated have the exclusive use, possession and enjoyment of that portion of the roof above their respective flats exclusively assigned to them and shall be solely responsible for the maintenance repair and renovation of such portion at his own expense.” (my emphasis)

127.With respect, I think Ms Wong has failed to acknowledge the important function of the waterproofing layer when construing these instruments. 

128.Let me begin by examining the terms of the DMC.  Ms Wong has assumed all references to “roof/Roof/ROOF” in the DMC to necessarily include the waterproofing layer.  Her interpretation appears to be arbitrary.  The term is actually not defined in the DMC.  Ms Wong’s reasoning would pose difficulty in construing clause 4(l)(7) which provides power and authority to the Manager “[t]o repair and keep in good repair and condition the main structure, roof and fabric of the said building its equipment, apparatus, services, facilities and common areas and when necessary to replace any part or parts thereof which require replacement.” (my emphasis)

129.It is not viable to confine the responsibility of the Manager to maintain and repair the “roof” (in terms of clause 4(l)(7)) to that strip of the roof behind the staircase landing that connects the two flat roofs as well as the rooftop of the staircase hood.  According to the building plans, the waterproofing layer should be a continuous layer covering the entire surface of the roof.  It is impracticable to carve up the waterproofing layer and require different entities to maintain and repair different parts.  As Godfrey Lam J recently explained:

“…water is a fluid that percolates through cracks and pores, and once there is a breach in the waterproofing membrane, it is not only the spot directly below that will be affected. I am unable to accept the contention that the waterproofing membrane should be notionally carved up and the part that is located directly above the Workshop should be regarded as being there for the exclusive use and benefit of the Workshop.” [54]

130.There is no dispute as to the general principles on the interpretation of a deed of mutual covenants such as the DMC. They have been succinctly summarized by Lord Hoffmann NPJ in Jumbo King: [55]

“The construction of a document is not a game of words. It is an attempt to discover what a reasonable person would have understood the parties to mean. And this involves having regard, not merely to the individual words they have been used, but to the agreement as a whole, the factual and legal background against which it was concluded and the practical objects which it was intended to achieve. Quite often this exercise will lead to the conclusion that although there is no reasonable doubt about what the parties meant, they have not expressed themselves very well. Their language may sometimes be careless and they may have said things which, if taken literally, mean something different from what they obviously intended. In ordinary life people often express themselves infelicitously without leaving any doubt about what they meant. Of course in serious utterance such as legal documents, in which people may be supposed to have chosen their words with care, one does not readily accept that they have used the wrong words. If the ordinary meaning of the words makes sense in relation to the rest of the document and the factual background, then the court will give effect to that language, even though the consequences may appear hard for one side or the other… But the overriding objective in construction is to give effect to what a reasonable person rather than a pedantic lawyer would have understood the parties to mean. Therefore, if in site of linguistic problems the meaning is clear, it is the meaning which must prevail.”

131.Although the waterproofing layer is not expressly referred to, the DMC does make reference to it by means of its important function and its existence is implied.

(a)   Clause 3(c) provides that the owners shall hold their parts of the building with the benefit of “[t]he right … to shelter and protection from the other portions of the said building.”  In my view, this includes the right to be sheltered and protected from water seepage from above and ultimately from the roof.

(b)   As we have seen, clause 4(l)(7) specifically provides the Manager (ie Burwell) with the power and authority to maintain and repair the “roof” together with the main structure, fabric, equipment, apparatus, services, facilities and common areas of “the said building”.  That term “the said building” is defined in the preamble to mean all three buildings of Gordon Terrace collectively.  Since the flat roofs have been assigned to individual owners, what is for the Manager to maintain is the waterproofing layer.

(c)   To facilitate the maintenance and repair of the waterproofing layer embedded in the flat roofs, clause 3(f) specifically gives “[f]ull right and privilege for the agent of the said building with or without surveyors workmen and others at all reasonable times on notice (except in case of emergency) to enter into and upon each part of the said building for the purpose of … repairing, … maintaining, … the said building or any part or parts thereof…” and clause 12(g) also requires that “the owners of the Top Floor Flats … not to change the lock on the door leading to the roof…”. 

132.In addition, clause 4(d) generally entrusts the Manager with the duty to repair and maintain “the common parts services and facilities” of Gordon Terrace.  And clause 4(g)(v) provides that the cost of maintaining and repairing the “common areas or any part or parts thereof and all equipments facilities and amenities therein and thereon … and all the apparatus equipment and conveniences thereof” is to be shared amongst the owners.  So, the cost of maintaining and repairing the waterproofing layer is catered for.

133.Thus viewed, the DMC provides a comprehensive scheme for the applicant (through Burwell) to maintain and repair the waterproofing layer on the flat roofs.  In my view, a reasonable person would have distinguished between the waterproofing layer and the flat roof when construing the term “roof”.  Those provisions charging the 2/F owners with the general responsibility to maintain and repair their “roof” (eg clauses 9, 12(g) and 12(h)(ii)) should refer to their flat roof and not the waterproofing layer.

134.In relation to the Assignment, Ms Wong invokes sections 2 and 16 of the Conveyancing and Property Ordinance in her bid to argue that since the waterproofing layer is attached or permanently fastened to the flat roof, it should form part of “the land” assigned to the respondents.  I do not agree.

135.Section 16(1) provides that:

“Unless the contrary intention is expressed in the assignment, an assignment shall operate to assign, with the land, all rights, interests, privileges, easements or appurtenances in, over, belonging or appertaining to that land or at the time of the assignment used, held, occupied or enjoyed with that land and things attached to the land or permanently fastened to anything attached to the land.”

And the term “land” is defined in section 2 to include “things attached to land or permanently fastened to anything attached to land”.

136.The respondents’ assignment is expressed to be subject to the DMC.[56] As I have endeavoured to explain above, the DMC does distinguish between the flat roof (which is assigned to the 2/F owner) and the waterproofing layer (which remains a common part).  Thus the Assignment does carry a contrary intention disapplying the general proposition under section 16(1).

137.For the above reasons, I find that the waterproofing layer on 6A Flat Roof is a “common part” and the applicant is responsible for its maintenance and repair under the BMO.

138.In the course of the above discussion, I have touched upon Ms Wong’s concern that it is impossible for the applicant to maintain and repair the waterproofing layer.  The fact that part of the waterproofing layer is sandwiched between the respondents’ flat and their flat roof does not make it impossible for the applicant to carry out maintenance and repair.  Clauses 3(f) and 12(g) of the DMC, as we have seen, obliges the 2/F owners who also own the flat roof above to give access.  Clause 3(e) correspondingly provides that the right of the owners (which may be collectively exercised by the applicant) to enter other parts of the building or common area to carry out necessary maintenance and repair should cause as little disturbance as possible and make good any damage.

139.Given my finding that it was the respondents who had damaged the waterproofing layer, Ms Wong’s fallback arguments are not engaged.

F.    Is the applicant liable for causing the water seepage at the respondents’ flat?

140.It is the applicant’s case that it has taken timely and reasonable steps to address the respondents’ complaint. That may be so in relation to the leakage at the staircase hood. 

141.The applicant has taken the view that it is the responsibility of the 2/F owners who also own their flat roof to maintain the waterproofing layer embedded therein.  That explains why it has not done anything over the years to maintain the waterproofing layer on the roofs of Gordon Terrace and has so far refused to repair the waterproofing layer on 6A Flat Roof.

142.As I have determined above, the waterproofing layer on 6A Flat Roof forms part of the common parts of Gordon Terrace and the applicant is responsible to maintain it in a state of good and serviceable repair under the BMO.

143.Ms Wong tries to argue with reference to clause 9 of the DMC that the respondents should nonetheless have gone after the owners of Nos 6-6A Gordon Terrace as opposed to the applicant. 

144.Clause 9 provides that:

The owner or owners for the time being of any one of the three blocks (ie “Nos 4 & 4A”, “Nos 6 & 6A” or “Nos 8 & 8A”) shall be responsible for keeping the common entrance hall, staircases and landings and the exterior of that particular block in good repair and condition and shall bear and pay the costs and expenses therefor in the proportion of one sixth thereof by the owner of each Flat of and in the said block (except the main roof thereof the costs and expenses for keeping in repair of which main roof shall be borne wholly by the owner or owners for the time being entitled to the exclusive use and enjoyment of such main roof).”

That clause only provides that the owners of each block should be responsible for keeping “the common entrance hall, staircases and landings and the exterior of that block” in good repair and condition and share the related costs and expenses.  It does not cover the waterproofing layer on the roof. 

145.On the other hand, section 18(1) of the BMO generally charges the applicant with the responsibility to maintain all common parts which, as I have determined, include the waterproofing layer.

146.Although the applicant may not have done what is required of it in terms of maintaining the waterproofing layer on 6A Flat Roof, that was not the effective cause of the water seepage at the respondents’ flat as I have found.

147.Although the experts agree that the service life of the original waterproofing layer on 6A Flat Roof has long expired, it is not their evidence that the waterproofing function of the layer would necessarily fail.

148.It is true that Mr Wong has said that other 2/F owners had encountered water seepage problem, we do not know the cause of those seepages.  On the other hand, we have Mr Yau’s evidence that at least the original waterproofing layer on the roof of No 8A of Gordon Terrace is still holding and require no remedial action.[57]

149.There is insufficient evidence to support the respondents’ contention that lack of maintenance of the waterproofing layer on 6A Flat Roof was a contributing cause to the water seepage problem.  The responsibility for the repair of the waterproofing layer falls on the respondents who have damaged it by the imposition of the Elevated Roof.

G.    Whether the respondents are entitled to their counterclaim?

150.Although the applicant have failed to maintain the waterproofing layer on the roofs of Gordon Terrace, that has not caused the water seepage problem at the respondents’ flat.  The true cause of the seepage at the respondents’ flat, as I have found, is the respondents’ own act of installing the Elevated Roof that had damaged the waterproofing layer. 

151.As explained in §3-44 in Clerk & Lindsell on Torts, 20th Edition (2010):

“Where it is found that the sole, effective cause of the relevant damage is the claimant’s own conduct he recovers nothing because he fails to establish causation.”

In my view, the respondents are not entitled to their counterclaim. 

H.    How should the respondents remove the Elevated Roof and reinstate the affected areas?

152.Regulation 3A(1) of Cap 123F provides that “Every opening placed on an external wall above the ground floor of any building shall be protected by a barrier which shall be not less than 1100 mm high…”.  Mr Yau took measurement of the height of the parapet wall plus the railing at different locations on 6A Flat Roof to confirm that the statutory minimum has not been achieved by reason of the Elevated Roof.[58]

153.Mr Yau further confirmed with reference to regulation 17 of Cap 123B that the Elevated Roof has overloaded the original roof.[59]

154.Given the above, Mr Yau opined that “the present situation is not in accordance with the approved building structural plan and it is not acceptable by the Building Regulations.  This is also regarded as unauthorized building works under the Building Ordinance…”.

155.Turning to the DMC:

(a)   Clause 5 provides that the 2/F owners, who have exclusive use occupation and enjoyment of their corresponding flat roof, “shall not cause suffer or permit the erection thereon or any part thereof of structures of any kind which contravenes the provisions of the Building Ordinance of Hong Kong and all other Ordinance.”

(b)  Clause 12(a) enjoins owners “[n]ot to make any structural alterations in his part of the said building which may damage the other parts thereof or cause any inconvenience to the other occupiers … or do any thing whereby the structural strength thereof may be affected.”

(c) Clause 12(j) also provides that owners shall not “make any structural alteration to any flat … nor cut, maim, injure, damage, alter or interferes with any part or parts of the said premises or buildings in common use or any of the … fixtures, equipment, apparatus or services of the said premises and building.”

156.The respondents concede that the Elevated Roof was installed in breach of Cap 123B, Cap 123F and the DMC.  The respondents are agreeable to remove the Elevated Roof and to reinstate the affected areas (including the waterproofing layer).

157.The foregoing discussion of the water seepage problem is premised on the respondents’ counterclaim which is monetary.  No one has actually prayed for an order for the repair of the waterproofing layer and the experts have not gone into the nitty-gritty of how that may be done. 

158.Whilst the respondents should primarily be responsible to reinstate the affected areas and to repair the damaged waterproofing layer, it remains the general responsibility of the applicant to maintain the waterproofing layer in the long run.  Bearing in mind that the waterproofing layer atop Nos 6 & 6A Gordon Terrace spans the entire roof, the applicant may want to use the opportunity to do what is necessary to ensure that the waterproofing layer as a whole is in a state of good and serviceable repair.  What is required is cooperation between the parties and they should be guided by professionals in their respective works.  After all, proper maintenance and repair of the entire waterproofing layer will not only benefit the respondents but other owners as well.  It is beyond the scope of this judgment and my expertise to say any more than this.

I.     Conclusion

159.By reason of the above, I enter judgment in favour of the applicant against the respondents on the monetary claim as well as the claim for an injunctive relief. 

160.I previously directed the parties to agree on the calculation of interests for the purpose of entering judgment but the respondents have failed to respond.[60] The parties will now also have to agree on the terms of the injunction.  I direct the parties to lodge in an agreed draft order for approval within 21 days from the date of this judgment.  Should the respondents fail to respond again, the applicant will be at liberty to submit its own draft for approval (including an injunction in terms of prayers (4) and (5) of the prayers in the Re-Re-Amended Notice of Application) and the respondents will be taken to have raised no objection.

161.The respondents’ counterclaim is dismissed.

162.There be a costs order nisi that the respondents do pay the applicant the costs of the application and the costs of defending the counterclaim to be taxed on the District Court scale if not agreed with certificate for counsel.

(Justin Ko)
Presiding Officer
Lands Tribunal

Ms Catherine WONG instructed by Simon C W Yung & Co, for the applicant.

Ms Janine CHEUNG instructed by Dissanayake & Associates for the 1st and 2nd respondents.



[1] According to the respondents’ assignment, the estate is also subject to a deed of partition registered by Memorial No 980931 and another deed of covenant registered by Memorial No 126758.  The parties have not referred to these deeds in evidence and I assume they are irrelevant for present purposes.

[2] Pursuant to clauses 4(k) and 4(o) of the DMC.

[3] The applicant has not pursued its claim for “costs and damages suffered by the Applicant arising from the breach of the DMC in respect of the unauthorized structures/alterations” (see prayer (6) of the Re-Re-Amended Notice of Application).

[4] See §§29, 34, 34A and 35 of the Amended Notice of Opposition.

[5] The respondents agree that the claim for the cost of the expert reports should more appropriately be dealt with as costs.

[6] The respondents have taken the period to be 15 months.

[7] This was adjusted by the respondents at the trial to tailor with the evidence.

[8] Ms Cheung confirms that the respondents are not pressing ahead with their counterclaim based on nuisance.

[9] At one stage, Mr Wang alleged that Mr Ngan had told him that the applicant would be responsible for the defects on the parapet walls which were more than 3 feet above the surface of the roof.  Mr Ngan was called to refute the suggestion.  In the end, Mr Wang’s allegation was not relied upon in the respondents’ closing submission.

[10] He was not allowed access into the respondents’ flat on that occasion.

[11] Whilst the owners resolved at that meeting to construct a cladding over the external walls, they eventually adopted a different mode of renovation. 

[12] There is a Chinese version of this report at Bundle 441-442.

[13] At Bundle 444(a).

[14] At Bundle 445(a)-(g).

[15] At Bundle 457.

[16] At Bundle 458.

[17] The photographs are at Bundle 460-461.

[18] See Bundle 460-461

[19] See §5.2C of Vigers 2008 Report [Bundle 175] and photographs 10-14 [Bundle 186-188].

[20] See §5.2C(3) of Vigers 2010 Report [Bundle 209] and photographs 14-16 [Bundle 224-225]; and infrared scan Nos 17-22 [Bundle 253-258].

[21] See Section (3) of Ms Cheung’s closing submission.

[22] At Bundle 182-183.  The enlarged photographs are at Exhibit R7.

[23] The enlarged photograph is at Exhibit R7.

[24] The enlarged photograph is at Exhibit R7.

[25] See the enlarged photograph 8 at Exhibit R7.

[26] See the enlarged photograph at Exhibit R7.

[27] This is taken from Ms Cheung’s closing submission.

[28] I have looked at the coloured photographs in the filed report which are much clearer.

[29] See Bundle 232-234 and 237-241.

[30] See, for example, the photographs at Bundle 651.

[31] See, for example, the photographs at Bundle 182.

[32] The photographs at Bundle 182 show that the entire party wall was covered by new wall tiles.

[33] Containing the statement: “waterproofing and tiling works were carried out on the parapet walls of your roof.”

[34] At Bundle 657-659.

[35] There is an enlarged photograph at Exhibit R8.

[36] At Bundle 241. 

[37] At Bundle 266.

[38] See Bundle 259-268.

[39] In terms of Vigers 2010 Report and Vigers Infrared Report.

[40] Compare the brownish window frames in the photographs annexed to Vigers 2010 Report and Vigers Infrared Report with the white window frames in the photographs taken by Mr Yau during the joint inspection.

[41] See Bundle 660-662 and 664.

[42] See Bundle 698 and 701-702.

[43] At Bundle 663.

[44] See also §6.4 of Mr Yau’s comment and §4.3 of Mr Lai’s comment in the Joint Report.

[45] In terms of the photographs enclosed in the respondents’ former solicitors’ letter dated 19 June 2008.

[46] See Answer 1 in the respondents’ reply to the applicant’s interrogatories [Bundle 71].

[47] At §4.3 of Joint Report.

[48] The letter dated 4 September 2009 was the first time the respondents complained about causes other than leakage from the staircase hood.

[49] At Bundle 186-188.

[50] See comment no 2 in MSC’s comments dated 6 August 2009 [at Bundle 455] and the related photographs [at Bundle 458].

[51] See the findings (eg §5.2C(3) of the report) and the photographs in Vigers 2010 Report.

[52] Defined in section 2 of the BMO to mean “any premises in a building which are referred to in a deed of mutual covenant whether described therein as a flat or by any other name and whether used as a dwelling, shop, factory, office or for any other purpose, of which the owner, as between himself and owners or occupiers of other parts of the same building, is entitled to the exclusive possession”.

[53] Similar conclusion was reached in Incorporated Owners of Hong Leong Industrial Complex v HL Resources Ltd [2009] 4 HKLRD 692 at §§28-60 (upheld on appeal, see [2010] 4 HKC 463 at §§7-10); and Wing Ming Garment Factory Limited v The Incorporated Owners of Wing Ming Industrial Centre, unreported, HCCT 60/2006, 23 June 2014, at §§84-109.

[54] Wing Ming, ante, at §95.

[55] Jumbo King Ltd v Faithful Properties Ltd (1999) 2 HKFAR 279 at 296D-I.

[56] At the end of clause 1 of the Assignment at Bundle 391.

[57] See §8.3 of Joint Report and the photographs at Bundle 666.

[58] See §§8.3-8.4 of the Joint Report.

[59] See §§5.5 and 6.3 of Yau’s Report and §§8.4-8.6 and Appendix 4 of the Joint Report (as elaborated at trial).

[60] See the applicant’s letter dated 22 January 2014.

Other Judgments in This Case

Further hearings and rulings under LDBM 291/2011