Kong Wai Hsien and Others v. The Incorporated Owners of Tai Wai Glamour Garden and Others

Read the full judgment text of HCA 1442/2013 on BabelCite. This High Court CFI judgment was delivered on 15 August 2018.

1. The 1 st , 2 nd , 4 th , 5 th , 6 th , 8 th , 11 th , 12 th and 14 th plaintiffs (collectively, “ Ps ”) were the respective registered owners of Shops A, C, F, J, K, M&N, Q, R and T of the Ground Floor (collectively, “ Shops ”) of Tai Wai Glamour Garden, Nos 1-5 Chik Fai Street & Nos 22-26 Mei Tin Road, Tai Wai, Shatin, New Territories (“ Building ”) erected on Sha Tin Town Lot No 226 (“ Land ”). Ps acquired/purchased the Shops subject to and with the benefit of the Subject DMC (see paragraph

Cited by 4 cases · Cites 8 cases

Case No.HCA 1442/2013[2018] HKCFI 1887[2019] 5 HKLRD 672
Court
High Court CFI
Date15 Aug 2018
Judge
Case Document
100%Judiciary

HCA 1442/2013

[2018] HKCFI 1887

IN THE HIGH COURT OF THE

HONG KONG SPECIAL ADMINISTRATIVE REGION

COURT OF FIRST INSTANCE

HIGH COURT ACTION NO 1442 OF 2013

________________________

BETWEEN
  KONG WAI HSIEN AND FUNG LAI SHEUNG 1st Plaintiff
  SUNPARK LIMITED 2nd Plaintiff
  CIBA TECHNOLOGY LIMITED 3rd Plaintiff
(Discontinued)
  SHE KAM HING 4th Plaintiff
  FOCUS HONOUR DEVELOPMENT LIMITED 5th Plaintiff
  NICE JOY LIMITED 6th Plaintiff
  TUNG FONG HUNG LIMITED 7th Plaintiff
(Discontinued)
  MUI LAI SZE 8th Plaintiff
  D & S LIMITED 9th Plaintiff
(Discontinued)
  GLORY HOVER LIMITED 10th Plaintiff
(Discontinued)
  HUGE TIME INVESTMENT LIMITED 11th Plaintiff
  CHENG WING YAN ANITA and
CHENG KEI TSI DANIEL
12th Plaintiff
  HIT SMILE LIMITED 13th Plaintiff
(Discontinued)
  JOY FULL TRADING LIMITED 14th Plaintiff
  and
  THE INCORPORATED OWNERS OF TAI WAI GLAMOUR GARDEN 1st Defendant
  AVANTE COMPANY LIMITED 2nd Defendant
  CIBA TECHNOLOGY LIMITED 3rd Defendant
(Discontinued)
  TUNG FONG HUNG LIMITED 4th Defendant
(Discontinued)
  D & S LIMITED 5th Defendant
(Discontinued)
  GLORY HOVER LIMITED 6th Defendant
(Discontinued)
  HIT SMILE LIMITED 7th Defendant
(Discontinued)

________________________

Before: Deputy High Court Judge Marlene Ng in Court

Dates of Hearing: 18-19 and 21 July 2016

Date of Handing Down Judgment: 15 August 2018

________________________

J U D G M E N T

________________________


I. INTRODUCTION

1.The 1st, 2nd, 4th, 5th, 6th, 8th, 11th, 12th and 14th plaintiffs (collectively, “Ps”) were the respective registered owners of Shops A, C, F, J, K, M&N, Q, R and T of the Ground Floor (collectively, “Shops”) of Tai Wai Glamour Garden, Nos 1-5 Chik Fai Street & Nos 22-26 Mei Tin Road, Tai Wai, Shatin, New Territories (“Building”) erected on Sha Tin Town Lot No 226 (“Land”). Ps acquired/purchased the Shops subject to and with the benefit of the Subject DMC (see paragraph 3 below).

2.In 1984, the Land was granted to Gladforce Limited under a government lease registered in the Land Registry as New Grant No 11888 (“New Grant”). The Land and Building were governed by the New Grant. By an Assignment dated 28 March 1985, Gladforce Limited assigned the Land to Avante Company Limited (“Developer” or “D2”). The Developer developed the Land by erection of the Building being a single multi-storey building comprising 20 shops on the ground floor and 8 residential units on each of the 2nd to 25th floors (ie 192 residential units). The Developer was the sole registered owner of the Land and Building immediately prior to the sale of the individual shops and flats thereat.

3.The Developer, Hong Yip Service Company Limited (“Manager”) and Sin Mui (“First Purchaser”) executed a deed of mutual covenant (“DMC”) and management agreement dated 31 January 1986 (“Subject DMC”). The Manager was designated and appointed as manager of the Building since the date of the Subject DMC, and was still such manager at the time of trial.

4.Under the Subject DMC, the Land and Building were notionally divided into 2,320 equal undivided parts or shares with various shares allotted to shops on the Ground Floor and flats A-H on the 2nd to 25th Floors of the Building as stipulated in the Second Schedule of the Subject DMC.

5.I set out in the Annexure to this Judgment various provisions of the Subject DMC (“Annexure”). Unless otherwise stated, references to “Sections”, “Clauses”, “Second Schedule” and “Third Schedule” in this Judgment are references to Sections, Clauses, Second Schedule and Third Schedule in the Subject DMC. For convenience, references to “Common Areas”, “Common Facilities”, “Common Parts”, “Owners” and “Unit” in this Judgment are references to those areas, facilities, parts, owners and unit of the Building as defined in Section I. Whilst I will refer to skeleton extracts from the Subject DMC to explain/illustrate the discussions below, such extracts should be read together with the more detailed quotations of the relevant provisions of the Subject DMC in the Annexure.

6.The Developer sold/assigned all 20 shops and 192 residential units of the Building to individual owners leaving 20 equal undivided shares in the Second Schedule[1] held by the Developer. It appeared that an Owners Committee (“OC”) was formed prior to 13 March 2007 to supervise the management of the Building.[2]

7.On 31 March 2009, the Building Authority (“BA”) issued Order No D00442/NT/08/MS/TC (“1st Order”). By the 1st Order, BA formed the view that the common parts of the Building were liable to become dangerous, and ordered the Developer to carry out the following works to commence by 28 June 2009 and to complete by 26 September 2009:

For common areas and exterior of the building

(a) Remove loose cracked and otherwise defective concrete from the reinforced concrete structure of the Building, clean existing exposed steel bars of loose rust and foreign matter, provide and securely fix in place additional steel bars as necessary and reinstate. The [BA] will be notified prior to placing of new concrete and the [BA] may carry out audit checking in this regard.

(b) Remove all loose and defective rendering.”

8.The 1st defendant (“D1”) was the incorporated owners (“IO”) of the Building. D1 was incorporated on 10 July 2009 pursuant to the Building Management Ordinance Cap 344 (“BMO”).

9.Ps claimed the Developer wrongfully failed to comply with the 1st Order, and wrongfully failed to commence and complete the stipulated works by the deadlines imposed in the 1st Order or at all.

10.The Developer and D1 executed an Assignment dated 19 April 2010 (“Assignment”) whereby for a consideration of $1 paid by D1 to the Developer, the Developer as beneficial owner assigned to D1 all those 20 equal undivided 2,320th parts or shares of and in the Land and Building “TOGETHER with the sole and exclusive right and privilege to hold use occupy and enjoy ALL THOSE COMMON PARTS of the Building” on trust for the benefit of all the owners for the time being of the undivided shares in the Land for the residue of the term of years created by the New Grant subject to and with the benefit of inter alia the Subject DMC.

11.Ps claimed that by the Assignment the Developer also purportedly assigned to D1 “the exclusive right to use or grant the right to use all the external walls parapet walls canopies of the Building or any part or parts thereof” conferred on the Developer,[3] but such Assignment did not stipulate such exclusive right was held by D1 as trustee for the benefit of all owners for the time being of the undivided shares in the Land and Building.

12.Ps also complained D1 did not give notice of execution of the Assignment (whether before or after such execution) or of the “specific subject transactions involved” to Ps and/or other owners of the Building, and no legal advice was made available to them regarding their rights, obligations, risks and liabilities before or after such execution. Ps claimed they first became aware of the Assignment in the course of inspecting the minutes of meeting of D1’s Management Committee (“MC”) in/about early 2013.

13.On 28 October 2010, the BA issued Order No D00560/NT/08 MS/TC (“2nd Order”). The 2nd Order was in the same terms as the 1st Order save and except (a) it was addressed to D1 and (b) the required works were to commence by 26 January 2011 and to complete by 26 April 2011. The 2nd Order also stated it substituted the 1st Order, but Ps claimed the 1st Order was not discharged/satisfied by the 2nd Order.

14.D1 sought contributions from all owners of the Building (including Ps) for funding to comply with the 2nd Order. Requisite works to comply with the 2nd Order were carried out. Out of the contributions by the owners of the Building (including Ps) a total sum of $5,348,400 or thereabouts plus consultancy fee of $97,000.00 were paid by D1 for works in compliance with the 2nd Order, but Ds alleged such sums were spent on carrying out repair/maintenance works of the “Common Areas”,[4] “Common Parts”[5] and “Common Facilities” (collectively, “CCCs”), and were not restricted to works for the 2nd Order. On 25 July 2012, BA issued a Certificate of Compliance.

15.On 5 August 2013, Ps commenced the present action against inter alia D1[6] for breach of duties in relation to D1’s acquisition of the “Common Parts” (particularly the external walls of the Building, “External Walls”) from the Developer pursuant to the Assignment for nominal consideration of $1 based on misunderstanding that such External Walls were part of the common parts of the Building.

16.D1 disputed liability. There were essentially 3 issues raised by the pleadings:

(a) whether on proper construction/interpretation of the Subject DMC and BMO the External Walls formed part of the common parts of the Building (“External Walls Issue”);
(b) whether D1 as IO owed any duties to Ps as individual owners in relation to (i) the renovation works carried out in respect of the External Walls and (ii) taking up the “Common Parts” and “Common Parts Shares” by way of the Assignment, and if so, what duties were owed and whether such duties were breached (“Duty Issue”);
(c) whether Ps were entitled to the reliefs sought, and if so the scope of those reliefs (“Reliefs Issue”).

17.On the first day of trial,

(a) on the External Walls Issue, Ps confirmed they would not rely on the contra proferentum rule;
(b) on the External Walls Issue, Ps confirmed they would rely on interpretation/ construction of the Subject DMC and BMO, and would not rely on any contention that the Developer had actual use, occupation and enjoyment of the External Walls;
(c) Ps confirmed that if on the External Walls Issue they failed to show the External Walls were part of the common parts of the Building, then their claim would fail without going into the Duty and Reliefs Issues;
(d) on the Duty/Reliefs Issues, Ps sought to rely on sub-paragraphs (1), (4) and (5) of the particulars of loss and damage pleaded in paragraph 39 of the Amended Statement of Claim, but not sub-paragraphs (2) and (3) thereof;
(e) on the Duty Issue, Ps averred there were procedural irregularities in relation to the meetings of the OC and MC and Owners, but this was not a standalone complaint but subject to their success on (i) the External Walls Issue and (ii) proving the duty(ies) that IO allegedly owed to Ps under the Duty Issue;
(f) on the Reliefs Issue, Ps confirmed they would not seek to set aside the Assignment;
(g) on the Reliefs Issue, I directed the issue of assessment of damages to be split from and dealt with after the trial on liability;
(h) I granted leave for Ps to amend their Reply and to file/serve their Amended Reply.

18.I note a number of plaintiffs had dropped out of the present action by withdrawing their claims. On 17 February 2015, the claim by the 1st to 14th plaintiffs (including Ps) against D2 was dismissed with no order as to costs.

II.  EXTERNAL WALLS ISSUE

19.Issue Ps claimed (and D1 disagreed) that upon proper construction of the Subject DMC and BMO the External Walls did not form part of the common parts of the Building, so pursuant to section 34H of the BMO (“section 34H”)[7] all or part of the renovation, repair and maintenance expenses in respect of or pertaining to the External Walls ought to have been borne and paid by the Developer to the exclusion of other Owners of the Building (including Ps) and/or D1, and any inconsistent provision in the Subject DMC was void by operation of sections 34H and 34C(2) of the BMO (“section 34C(2)”).[8] Thus, the External Walls Issue was essentially a matter of construction/interpretation of the Subject DMC and BMO.

20.Ps’ stance  Ps averred the External Walls were “exclusive use areas” not intended for the common enjoyment of the co-owners and co-occupiers for the time being of the Building. It was said “exclusive use areas”[9] and “common use areas” (or “common parts”)[10] are mutually exclusive even though it does not follow they have to be physically separate from each other.[11] Ps averred the External Walls were “exclusive use areas” as the Developer had exclusive right to the use, occupation and enjoyment (“Exclusive Right”) over the same or any part(s) thereof until the Assignment in 2010:

(a) according to the Second Schedule, 20 equal and undivided shares (ie “Common Part Shares”) were allotted to the “Common Parts”;
(b) by virtue of Clause 8(b) of Section II (“Clause 8(b)”), the Developer had “the exclusive right to install in or affix to and use (or permit any person or corporation to install in or affix to and use) any part of the Building to which no Owner(s) has the exclusive right to occupy including the external walls such flues, pipes, conduits …… plant and machinery and other apparatus as the [Developer] shall think fit, together with the right to repair, maintain, service, remove or replace the same” (my emphasis);
(c) by virtue of Clause 8(c) of Section II (“Clause 8(c)”), the Developer had “the exclusive right to use or grant the right to use all the external walls parapet walls canopies of the Building or any part or parts thereof with the necessary right of support on any part of the flat roofs …… and the Main Roof and Upper Roof for advertising purposes and to display, install, erect, affix or permit to be displayed, installed, erected or affixed thereon and thereto such advertising signs or structures …… with the right to remove, repair, maintain, service or replace the same ……” (my emphasis)

Mr Ng, counsel for Ps, submitted Clauses 8(b)-(c) clearly showed the External Walls were outwith “common use areas” (or “common parts”) notwithstanding the definitions of “Common Areas” and “Common Parts” in Section I. In support of such contention, Ps claimed the Developer by the Assignment assigned the right to “use” the External Walls to D1 (see paragraph 11 above).

21.D1’s stance  D1 claimed the Developer by the Subject DMC had the Exclusive Right over all shops, flats and self-contained portions and other portions (not otherwise intended to be for the common enjoyment of the co-owners and co-occupiers for the time being of the Building) comprised in the Building other than the flat purchased by the First Purchaser (“FP Flat”).[12] So even though the Developer still held 20 equal undivided shares allocated to the “Common Parts” (ie the “Common Parts Shares”) after selling/assigning all other shops/flats in the Building to individual owners, it did not have the Exclusive Right over CCCs that were intended for the common enjoyment of co-owners and co-occupiers for the time being of the Building because:

(a) the Owner of each equal and undivided share of the Building had full right and liberty (in common with other persons having the like right) to go pass and repass over and along and use the “Common Areas” and “Common Facilities” “for all purposes connected with the proper use and enjoyment of his Unit ……”;[13]
(b) the Manager had powers/duties in relation to the CCCs under Clause B1 of Section VI;
(c) the definitions of “Common Areas”, “Common Parts”, “Common Parts Shares”, “Owners”, “Share” and “Unit” in Section I as well as the provisions in Clauses D1 and D2 of Section VI combined to show the “Common Areas” and “Common Parts” (including the External Walls) and the “Common Facilities” were not any Unit and did not have any saleable area, so the Developer had no obligation under the Subject DMC (i) to manage, maintain and repair the same and/or (ii) to pay or contribute to the management and/or repair/maintenance expenses of the same.

22.D1 averred that although Clauses 8(b)-(c) gave certain rights to the Developer as to use of the External Walls or part(s) thereof, such rights were subject to “necessary approvals or consents of the appropriate Government authorities having been had and obtained” and/or Special Condition no 6(l) of the New Grant (“SP6(l)”), and did not entitle the Developer to have Exclusive Right over the External Walls or part(s) thereof.

23.Mr Lam, counsel for D1, argued that a study of the provisions of the Subject DMC would show (a) the Developer did not have Exclusive Right over the External Walls, (b) all Owners shared the use, occupation and enjoyment of the External Walls, and (c) all Owners[14] were responsible for repairing/maintaining the “Common Parts” that would include the External Walls and for paying the costs therefor.

24.D1 claimed that for the above reasons sections 34C and/or 34H of the BMO had no application.

25.Ownership and possession in multi-unit building  Cheung JA in Incorporated Owners of Shatin New Town v Yeung Kui explained the nature of ownership in a multi-unit development as follows:[15]

“1. When someone owns a flat or unit in a multi-unit development in Hong Kong, it means in legal terms that he holds a notional share (the amount of which is specified in the original assignment from the vendor to him or in the [DMC]) in the development as tenants in common with the other owners of the development but he is given ‘exclusive possession’ of his own flat to the exclusion of the other co-owners. In contrast to this specific unit, the common parts of the development such as entrance, passageways, garden, utility rooms and exterior walls are not within the exclusive possession of any of the owners but are to be used and enjoyed by all of them. The ambit of the common parts of the development is usually specified in the DMC. If not, the [BMO] will apply and defines the common parts.”

To put it in another way, DHCJ To (as he then was) in Incorporated Owners of Million Fortune Industrial Centre v Jikan Development Ltd & anor[16] said that unity of possession meant the co-owners of undivided shares in a multi-unit development have right of possession in common with other co-owners over the land and building upon it, but it does not carry with it the right to exclusive possession of any particular part of the land and building unless so provided by the DMC.[17]

26.This is consistent with the definition of “common parts” in section 2 of the BMO, ie (a) the whole of a building, except such parts as have been specified or designated in an instrument registered in the Land Registry as being for the exclusive use, occupation or enjoyment of an owner, and (b) unless so specified or designated, those parts specified in the First Schedule of the BMO (which schedule provides that “common parts” include inter alia external walls).

27.Interpretation/construction of DMC  It has been said that the statutory definition of “common parts” means the process of identifying what is a “common part” is by eliminating all those parts of a building that have been specified or designated in, say, a DMC[18] as being for exclusive use, occupation or enjoyment of an owner.[19] Ultimately, it is “a question of construction and application of each DMC or of the BMO or both”.[20]

28.Lord Hoffmann NPJ in Jumbo King Ltd v Faithful Properties Ltd & ors reminded that “…… [the] construction of a document is not a game with words. It is an attempt to discover what a reasonable person would have understood the parties to mean. And this involves having regard, not merely to the individual words they have used, but to the agreement as a whole, the factual and legal background against which it was concluded and the practical objects which it was intended to achieve”.[21] Cheung JA expressed similar sentiments in Incorporated Owners of Shatin New Town at p 246:

“…… One of the overriding objectives in the construction of a document such as the DMC is to give effect to that which a reasonable man (rather than a pedantic lawyer) would have understood the parties to mean. Therefore, if in spite of linguistic problems the meaning is clear, it is that meaning which must prevail: Jumbo King Ltd v Faithful Properties Ltd & Ors [1999] 4 HKC 707, (1999) 2 HKCFAR 279 per Litton PJ at 296.”

29.Mr Lam’s authorities  Before I deal with the Subject DMC, it is perhaps useful to first turn to the relevant authorities. In Incorporated Owners of Million Fortune Industrial Centre, the developer and first owner of a building assigned to the 1st defendant 7 undivided shares (allotted to 7 parking spaces) and 15 undivided shares (allotted to the common parts of the building) together with the “exclusive right and privilege to hold, use and enjoy [ie the Exclusive Right] the common parts, the external wall and all seven lorry parking spaces” even though under the DMC the developer was not given exclusive use of the common parts. The 1st defendant converted some of these common parts into parking facilities (ie the disputed area), and the 2nd defendant collected parking fees and paid them to 1st defendant. After the IO was formed, it demanded the 1st and 2nd defendants to account for such parking fees previously paid by the 2nd defendant to the 1st defendant. DHCJ To held the IO was entitled to recover such collected parking fees.[22] The 1st and 2nd defendants appealed by contending that the right to such recovery belonged to the owners at the time when such fees were collected, and the 1st defendant being one of such co-owners was entitled to retain the fees that had been paid to it. The Court of Appeal dismissed the appeal.[23] The relevant issue was whether the assignment by the developer (and first owner) in respect of inter alia 15 undivided shares for the common parts was effective in transferring (a) ownership of the common parts together with (b) Exclusive Right over the same to the 1st defendant to the exclusion of the other co-owners.

30.In that case, (a) clause 2 of the DMC defined “Common Parts” as certain itemised areas and all such other spaces/areas (if any) as might be designated by the developer (and first owner) as “Common Parts” or rights of way “[unless] otherwise designated by [the developer (and first owner)]” (my emphasis), (b) the disputed area that the 1st and 2nd defendants used for hourly-parking was a common part unless it had been designated otherwise by the developer (and first owner) (see (a) above), (c) the developer (and first owner) did not so “otherwise designate”, and (d) the developer (and first owner) by the DMC assigned the Exclusive Right and rents/profits of certain parts of the building set out in the first schedule of the DMC that expressly excluded such common parts.

31.DHCJ To (as he then was) held that since the developer as the first owner had not been given Exclusive Right over the disputed area and indeed over the entire common parts under the DMC,[24] and the developer had not re-designated the disputed area for its exclusive use, occupation and enjoyment, the assignment of 15 undivided shares allotted to the common parts to the 1st defendant (which assignment was expressly stated to be subject to and with the benefit of the DMC) could not make any difference (p 468):

“…… The assignment only gave the first defendant legal title, but not exclusive possession of any particular part of the Building. The first defendant has no more and no less right to the use of the common parts than any of the co-owners. However, this is not an ownership without substance. For example, after the first defendant has disposed of all its factory units, it still has the right to use the common parts by virtue of these 15 shares. Similarly, when the interest in the entire Building has to be disposed of, for example, for re-development or in case of compulsory acquisition, these shares give it a 15/17180th joint interest along with the other co-owners in the entire land and building.” (my emphasis)

DHCJ To (as he then was) therefore held that collecting income from use of the disputed area amounted to conversion of such income that belonged to all co-owners.

32.The Court of Appeal agreed. Rogers VP held that by virtue of the definition of “Common Parts” under the DMC the developer (and first owner) was not given Exclusive Right over the common parts. Although clause 5 of the DMC listed certain rights/privileges to which the developer (and first owner) was entitled, the developer (and first owner) was only given an absolute right to designate exclusive use of the passages, corridor-ways and landings “which were not for the common use of the premises and/or the Building”. Further (at p 459),

“…… If the matter were in any doubt, the First Schedule specifically lists those parts of the Building of which the First Owner had the exclusive use, and although car parking spaces and lorry parking spaces are referred to, there they were ‘as are more particularly described in the Fourth Schedule’ and the First Schedule makes clear that the areas specified for the exclusive use of the first owner do not include the common parts. The Fourth Schedule makes clear the distinction between the common parts and the car- and lorry-parking spaces. Moreover, under cl.9 of the Third Schedule the owners undertook to use the parts of the Building intended for common use for the purpose of access to and egress from their workshops and not otherwise. Furthermore, under the Third Schedule the owners of the shares relating to the common parts were absolved from any requirement to pay or contribute to the costs and charges relating to the management of the building to which all the other owners had to contribute. In contrast the owners of car and lorry parking spaces were not so exempt.”

Thus, Rogers VP concluded that whatever the effect of the assignment, it did not give the 1st defendant exclusive use of the common parts nor the right to use the common parts for its own private commercial purpose as a carpark where fees were charged.

33.The 1st and 2nd defendants’ appeal to the Court of Final Appeal was dismissed,[25] and Litton NPJ made observations on distinguishing “common use areas” from “exclusive use areas” (at p.457):

“31. The expression ‘Common Parts’ as used by conveyancers in Hong Kong means those parts of premises designated for the common use of the co-owners, and persons deriving rights under them. But this is not the end of the story. The DMC in a particular case may contain provisions whereby areas constituting the common parts might lawfully be re-designated for the exclusive use of individual owners. But where parts of premises have been designated as Common Parts it goes without saying that they cannot be arrogated unilaterally to the exclusive use of a sole owner. The DMC in this case, as can be seen later on, so provides; this is no more than a reflection of the provisions of s.34I of the [BMO] which says :

34I. Common parts

(1) No person may -

(a) convert any part of the common parts of a building to his own use unless such conversion is approved by a resolution of the owners' committee (if any);” (my emphasis)

34.In Incorporated Owners of Goa Building v Wui Tat Co Ltd, the developer of the building retained ownership of the mezzanine floor and 3 shops on the ground floor. The IO made a claim to the Lands Tribunal (“Tribunal”) under section 34H against the developer for the maintenance cost of the external walls. The Tribunal gave judgment for the IO, and ordered the developer to bear costs of maintaining the whole of the external walls of the building.[26] The Court of Appeal allowed the developer’s appeal, and remitted the matter to the Tribunal.[27]

35.The Court of Appeal held the IO could maintain its claim against the developer only if it were shown it had the right to exclusive possession of the relevant part of the building or had Exclusive Right over that part. Such right would inevitably stem from the DMC. It is useful to refer to clauses 1.01 and 3.02 of the DMC in that case in full as follows:

“1.01 The Vendor shall for the residue of the term of years set out in the said Schedule have the sole and exclusive right and privilege (A) to the use occupation and enjoyment of all the said units of the said Building and the appurtenances thereto and the entire rents and profits thereof save and except the said Flat ‘A’ on the First Floor and Portion ‘A’ of the Flat Roof on the first floor level of the said Building and the appurtenances thereto and the entire rents and profits thereof and (B) Subject to any necessary approval of the Government Authority or Department to erect, construct, install, affix, fit up, paint and maintain any signs, signboards, advertisements, placards, posters or any other structures whatsoever of such size and design whether illuminated or otherwise and at to or on such position or positions of the external walls of the said Building and of any part of the said Building in common use as the Vendor shall in its absolute discretion think expedient or desirable and to remove replace or repair the same and to enter upon any unit at all reasonable times with or without workmen for the purpose of so doing and (C) Subject to any necessary approval of the Government Authority or Department to erect, construct, install, affix or fit up one or more flu pipes or smoke stacks or chimneys at to or on such part or parts of the open yard or yards and of the external walls of the said Building as the Vendor shall in its absolute discretion think fit and to remove replace or repair the same and to enter upon any unit at all reasonable times with or without workmen for the purpose of so doing.” (my emphasis)

“3.02 The person or persons either solely or between themselves in whom the sole and exclusive right and privilege to erect, construct, install, affix, fit up or maintain any sign, signboard, advertisement, placard, poster, other structure, chimney, flu pipe or smoke stack mentioned in Clause 1.01 hereof or the right to receive the rents and profits thereof is for the time being vested for the residue now to come and unexpired of the term of years as set out in the said Schedule shall at all times observe and comply with all the laws and regulations relating to the erection maintenance and dismantling thereof and shall be solely responsible for the repair, maintenance, upkeep, renewal and removal of any such sign, a signboard, advertisement, placard, poster, other structure, chimney, flu pipe or smoke stack and the part of the said Building in common use and the portion or portions of the external walls and the portion or portions of the open yard or yards of the said Building at which and/or to which and/or upon which such sign, signboard, advertisement, placard, poster, other structure, chimney, flu pipe or smoke stack shall be erected, constructed, installed, affixed, fitted up or maintained and such person or persons shall at all times indemnify and keep indemnified the owners and occupiers for the time being of the said Building against all loss, damage, injury, costs, expenses, actions, claims and demands arising out of or on account of or resulting from the installation, repair, renewal, removal, maintenance and upkeep of such sign, signboard, advertisement, placard, poster, other structure, chimney, flu pipe or smoke stack or any defect therein or any failure to maintain the same in proper repair and condition.”

36.Rogers VP held clause 1.01 of the DMC gave the developer various rights (that extended not only to the external walls but also to any part of the building that was in common use) such as erection of signs, signboards and flu pipes, but not exclusive possession or External Right of the external walls. As for clause 3.02 of the DMC, the developer was required to (a) comply with various laws/regulations that might be involved, (b) be solely responsible for repair/maintenance of any relevant item that might be so placed and also of “the part of the Building in common use and the portion or portions of the external walls and the portion or portions of the open yard or yards of the said Building at which and/or to which and/or upon which” any such item was placed, and (c) keep the other owners indemnified for any loss or damage which might be occasioned by exercise of the rights granted under clause 1.01 of the DMC.

37.Rogers VP concluded at p 351 that the rights accorded to the developer under clause 1.01 of the DMC did not comprise all rights that would amount to exclusive possession or Exclusive Right over the relevant part of the building, but were merely part of the rights that might be enjoyed by an owner but were not full/exclusive rights. The Tribunal was therefore wrong to rule the relevant clauses of the DMC had conferred on the developer such Exclusive Right. Rogers VP further held that since clause 1.01 of the DMC referred not only to the external walls but also to the parts of the building in common use, it would be contradictory and absurd to suggest the common parts of the building were thus either in the exclusive possession of the developer or the developer had Exclusive Right thereof.

38.In Incorporated Owners of Shatin New Town, the development (developed by 4 developers) had a commercial portion made up of 4 levels and a basement consisting of shops and carparks, and 8 high-rise blocks of 1,400 residential units. Resolutions were passed at an owners’ meeting to carry out maintenance works to the lobbies, entrance halls and exterior walls of the residential blocks (ie the disputed area), and to increase monthly management fees of the residential units for 24 months for carrying out such works. The respondent owner of a residential unit paid the increased management fees for a few months and thereafter refused to pay. The issue was whether the disputed area was within the exclusive possession of the developers who therefore should be solely responsible for their maintenance, or whether it was part of the common parts of the development the maintenance and expenses of which should be shared by contributions from owners of the residential units. At the Tribunal, HH Judge Wong dismissed the IO’s claim for recovery of the respondent’s unpaid monthly expenses on the basis that the disputed area was “owned” by the developers so maintenance thereof should be their sole responsibility and not that of the respondent.[28]

39.The first schedule of the DMC allotted 23 undivided shares for various itemised areas and “Exterior Walls”, and 7 undivided shares for various itemised areas and “all communal areas of the Estate and of each Block not hereinbefore mentioned”, which undivided shares were still retained by the developers. The disputed area came within such ambit, so the real issue was whether the disputed area was within the developers’ exclusive possession. Cheung JA decided it was not.[29]

40.The fact the developers reserved the common area (ie the 7 undivided shares that was inclusive of the disputed area) described in the first schedule of the DMC did not mean they had exclusive possession over it. After all, co-owners had full right and liberty under clause A1 of section II of the DMC to go, pass and repass over and along and use such of the entrance halls, lobbies, staircases, landing, passages, lifts and other common areas as formed part of the residential blocks. Cheung JA said at p 246 as follows:

“The consequence of any other interpretation would be unthinkable: it would mean that the owners of the 1,400 residential units would not have the right to use such essential facilities such as the entrance halls and lobbies, and could only do so at the whim and pleasure of the developers. ……”

Further, although the rights upon the developers in clause 7 of section I of the DMC inter alia to erect pipes on the exterior walls and to use the exterior walls for advertising purposes were described as exclusive rights, they were in fact qualified as (a) the developer required prior approval of the manager of the development before they could exercise these rights, and (b) 2 further conditions applied in respect of the advertising right, ie the approval of the government authorities, and the exercise of such right must not unnecessarily interrupt the enjoyment of the residential units. Taking into account the specific designation of exterior walls as a common area to be used by all owners, the conferring of these so-called “exclusive rights” over the exterior walls to the developers for some limited purpose did not provide them with exclusive possession of the exterior walls. Although the exact wording of the clauses in the DMC was different from those in Incorporated Owners of Goa Building,[30] Cheung JA found the construction of their effect “equally clearly applicable”, and further found the relevant clauses in the DMC did not confer exclusive possession of the disputed area to the developers, so section 34H was not applicable and the residential owners had to share the maintenance expenses of the disputed area.

41.In Incorporated Owners of Hong Leong Industrial Complex v HL Resources Ltd, the manager used the management fund to replace the waterproofing layer sandwiched within the floor slab of the roof. The IO and an individual owner alleged the developer was the owner of the roof and responsible for the relevant repair/maintenance expenses. Sakhrani J held the waterproofing layer was a common part of the building, so the cost of repairs had to borne by the owners generally, and the manager was entitled to use the management fund for repair/maintenance even though the developer owned the roof.[31] It was held that paragraph (j) of the fourth schedule to the DMC only gave the developer rights to exhibit advertisements or affix structures to (but not confer Exclusive Right over) the external walls, so section 34H had no application.

42.The Court of Appeal dismissed the appeal by the IO and individual owner.[32] Rogers VP held on proper consideration of the DMC, the developer’s exclusive right to use the external walls was not an exclusive right as normally understood, particularly under section 34H. The learned judge noted paragraph (k) of the fourth schedule of the DMC provided the owners had bound themselves not to put anything on the external walls or exterior of the building except with written approval of the manager and subject to such conditions as the manager might impose, so whatever right the developer had in relation to the external walls was necessarily subject to such conditions as the manager might permit. Further, clauses 12(a)-(b) of the DMC gave the manager power to absolve an owner from a restriction on placing signs, signboards or advertisements on the external walls. So whatever interest the developer might have had in the outer or external walls, it did not have exclusive possession and/or Exclusive Right over such parts of the building as the manager could permit others to make use of the external walls.

43.In 聯基新樓業主立案法團 v Yan Yan Motors Ltd,[33] the building comprised shops and domestic units. Clause 3 of the DMC stated there was reserved unto the developer and its assigns and all persons authorised by it/them “exclusive right to use” the main roof for the erection, installation and maintenance of a cooling tower or compressor “or for any other purpose”, and “to use” the external walls and flat roof:

“for the erection, installation and display of signboards, advertisements, decorations, lights, lanterns, articles and other display materials.  The above works shall be at the costs of [the Developer], its assigns or licensees who shall make good any damage to the said main roof, the said external walls or the flat roof occasioned thereby and, so long as the said erection installation or display shall remain, maintain and repair the part or parts of main roof, the external walls and of the flat roof so taken up by such erection installation or display.  But the cost for the maintenance and repair of the said main roof, the external walls and the flat roof not taken up by [the Developer] its assigns or licensees shall be part of the management expenses of the said premises and building payable by all co-owners under clause 9(f)(2) hereafter …”

The IO decided certain repair costs were to be borne by co-owners of the building, but the defendant co-owner objected on the basis that under the DMC the developer was given exclusive possession or Exclusive Right over the external walls and main roof so it should be solely responsible for relevant portions of the costs incurred in repair/maintenance of those parts of the building. The IO brought 7 claims in the Small Claims Tribunal against the defendant co-owner for recovery of the apportioned costs that were said to be due and payable. The Small Claims Tribunal found in favour of the IO, and the defendant appealed.

44.The main debate on appeal was whether, upon true construction of the DMC, the developer was entitled to exclusive possession or Exclusive Right over the external walls and main roof of the building. It was said that if the answer was yes, then notwithstanding any inconsistent provision in the DMC, the developer would have to maintain such parts in good repair/condition by operation of sections 34C(2) and 34H. Chow J referred to Incorporated Owners of Goa Building and Incorporated Owners of Shatin New Town, and concluded as follows:

“20. In the present case, the Developer’s exclusive right to use the External Walls under clause 3(b) and (c) of the DMC is limited to the erection, installation and display of signboards, advertisements, decorations, lights, lanterns, articles and other display materials.  Such right cannot be regarded as comprising all the rights which would amount to the exclusive possession or the exclusive right to the use occupation or enjoyment of the External Walls.

21. Support for this conclusion can also be found in clause 4(a) of the DMC, which confers on the Management Company the ‘exclusive right to use the external and internal walls …. for signboards, advertisements, decorations, lights, lanterns and other display material as the Management Company may think fit’.  Although this right is, as stated at the beginning of clause 4(a), “[s]ubject to the reservation in favour of [the Developer] under Clause 3”, it seems to me that if the Developer is to be regarded as having the right to the exclusive possession of the External Walls or the exclusive right to the use occupation or enjoyment thereof, the right given to the Management Company under clause 4(a) would be largely meaningless.  In my view, the two clauses ought to be read together such that, subject to the Developer’s right (which shall have priority) to use the External Walls for the limited purposes mentioned in clause 3(b) and (c), the Management Company is also entitled to use External Walls for some limited purposes.  Neither can be regarded as being entitled to the exclusive possession of the External Walls or the exclusive right to the use occupation or enjoyment thereof.

22.  In all, I am of the view that, upon the true construction of the DMC, the Developer does not have the exclusive possession, or exclusive right to the use occupation or enjoyment, of the External Walls for the purpose of section 34H of the BMO. Accordingly, the responsibility to maintain the External Walls in good repair and condition does not fall solely on the Developer.” (my emphasis)

45.Although each DMC may be worded somewhat differently, the above line of authorities is consistent in approach, and the ratio that fell from the Court of Appeal is binding on this court.

46.Mr Ng’s authorities  I now turn to the 2 first instance authorities cited by Mr Ng, ie Uniland Investment Enterprises Ltd v Incorporated Owners of Sea View Estate & anor,[34] and Green & Grace Ltd v Wang Lung Industrial Building (IO).[35]

47.In Uniland Investment Enterprises Limited, the plaintiff was the owner of the outer wall and flat roof of a building (ie the disputed area). In 1996, a building order was served on the IO requiring it to carry out repair works for the external areas and common areas of the building, including works on the disputed area. In 1998, the owner of the disputed area was served with a building order requiring it to carry out the same repair works over the disputed area. The owner claimed against the IO and manager for breach of the covenant to repair under the DMC.

48.It is useful to take a look at the relevant provisions in the DMC in that case (at p 143):

“Under recital (3) of the DMC the building is divided into 95,000 equal undivided shares. The outer wall and flat roof was allocated one share which was originally held by the developer and is now acquired and held by the plaintiff.

Under cl 1(i) of the DMC, the plaintiff has the full and exclusive right and privilege to hold, use, occupy and enjoy the outer wall and flat roof in so far as the same have not been assigned to any other owners. Hence, the outer wall and flat roof do not form part of the common areas of the building. However, under cl 3, the plaintiff's exclusive right is subject to the easements and rights set out in the second schedule. These easements and rights include ‘the free and uninterrupted passages and running of water, sewage, gas and electricity from and to the units’ and the right of the management company to enter upon to effect rebuilding and repairing, etc. Clause 17(i) also imposes other restrictions on the plaintiff's exclusive right to use and enjoy the outer wall and flat roof. The plaintiff has, in the enjoyment of its exclusive right, licensed parts of the outer wall and flat roof to others for various purposes.

Clause 7(a) of the DMC imposes on the management company the responsibility of repairing and maintaining the outer wall and flat roof. Clause 8 requires the management company to budget for the maintenance of the building, including specifically the outer wall and flat roof and to recover contributions from the owners. But cl 8(i) specifically exempts the owners of the dangerous goods stores, sub-terranean level tank and outer wall and flat roof from having to make such contribution. Thus in effect, the plaintiff as owner of that one share is entitled to exclusive possession, use and enjoyment of the outer wall and flat roof, subject to certain easements and rights of other owners, while the management company shall be responsible for its maintenance at no costs to the plaintiff. The costs are to be shared by the other owners of the building. This interpretation is not disputed by counsel for the first and second defendants.” (my emphasis)

49.On the basis of such common ground, the only remaining issue was whether the provisions in the DMC as to liability for maintenance of the disputed area were rendered void by sections 34H and 34C(2), and DHCJ To (as he then was) held section 34H imposed on the owner (as owner, occupier and user) the obligation to maintain the disputed area notwithstanding that under the DMC such obligation fell on the manager and hence the IO upon its incorporation. It was held the provision to such effect in the DMC was void as being inconsistent with section 34H.

50.As Mr Lam pointed out, Uniland Investment Enterprises Ltd was made on the common ground between the IO and the owner of the disputed area that under the DMC such owner had exclusive possession and Exclusive Right over the disputed area such that the disputed area was not part of the common areas of the building. This was recognised in Lily Tse Lai Yin & ors v The Incorporated Owners of Albert House (also known as the Owner Incorporation of Albert House) & ors.[36] In that case, the IO sought to rely on Uniland Investment Enterprises Ltd to submit that once there was an owner, occupier or user having the obligation to maintain, no other person would have the same obligation. Suffiad J did not share such view, and held Uniland Investment Enterprises Ltd (which was decided on very different facts) was clearly distinguishable. The learned judge said [so] it was upon those facts pertaining to Uniland’s case [ie the aforesaid common ground between the parties] that Deputy Judge To decided that Section 34H of the [BMO] applied and that since one of the terms of the [DMC], which provided for the management company to maintain the outer wall, was inconsistent with section 34H, that term was void as being inconsistent with Part VIA of the [BMO] as provided for in section 34C(2)” (my emphasis).

51.In my view, bearing in mind that the ratio of Uniland Investment Enterprises Ltd concerned the issue/determination set out in paragraph 49 above which was premised on the aforesaid common ground between the parties referred to in paragraphs 48 and 50 above, such ratio did not address the disputed External Walls Issue in the present action, ie whether the Developer had exclusive possession or Exclusive Right over the External Walls. Further, when such disputed issue was debated before DHCJ To (as he then was) in the subsequent case of Incorporated Owners of Million Fortune Industrial Centre, the learned judge came to a view consistent with the line of authorities cited by Mr Lam (see paragraph 31 above). Further, when DHCJ To (as he then was) decided Uniland Investment Enterprises Ltd, he did not have the benefit (as I now do) of the guidance by the Court of Appeal in the line of authorities cited by Mr Lam. I am not persuaded Uniland Investment Enterprises Ltd would provide helpful assistance in the construction of the Subject DMC as it turned on particular provisions of the DMC in question (which I find to be quite different from those in the Subject DMC) and on the aforesaid common ground between the parties (which was absent in the present action).

52.In Green & Grace Ltd, an owner of a workshop in a building failed to pay contributions towards the cost of maintenance/renovation works for the building including its external walls that had been carried out. Clause 7 of section I of the DMC provided the developer had exclusive use and enjoyment of the external walls, but no corresponding obligation to repair and maintain them. The owner of the workshop argued sections 34C(2) and 34H were applicable, so the developer and not the other owners should pay the costs of the works. The IO asserted inter alia the other clauses in the DMC restricted the developer’s exclusive right to use the external walls by requiring the manager’s prior permission. DDJ Angela Kot (as she then was) concluded clause 7 of section I of the DMC was inconsistent with section 34H and therefore void, so the developer (and not other owners) should shoulder the obligation to repair/maintain the external walls and also the costs/expenses for the same.

53.In that case, no undivided share was allocated to the external walls, so the developer did not own the external walls. Turning to the relevant provisions in the DMC, common area was defined in clause 1(1)(a) but the external walls were not amongst it.[37] Clause 7(c)-(d) of section I of the DMC provided as follows (at pp 173-174):

“7. Notwithstanding any provision to the contrary herein, there is reserved unto the Registered Owner its successors and assigns the following rights and privileges :-

……

(c) the exclusive right and privilege to hold use occupy and enjoy or otherwise dispose of or deal with the external walls of the Building.

(d) the exclusive right and privileges to, and to permit its or their licensees to, display, install, erect, affix, attach, dismantle, remove, repair, service and maintain to, in, on or from the Upper Roof … and/or the external walls of the Building or any part or parts thereof (i) signboards, neon signs … Provided Always that the Registered Owner and its successors and assigns having such exclusive right and privilege shall not be required to repair and maintain the … external walls of the Building or any part or parts thereof … save as provided in the following proviso and Provided that in displaying, installing … or maintaining any such signboards, neon signs … as aforesaid, the Registered Owner … shall at its or their own costs and expenses:

(A) obtain the requisite approval of the Director of Buildings and Lands and other Government Authorities concerned,

(B) observe and comply with all the laws and regulations for the time being in force and applicable thereto,

(C) make good all damage done to the Building occasioned thereby,

(D) remove, dismantle or replace the same if and whenever the same shall constitute any danger or hazard to the safety of the other Owners and/or occupiers of the other parts of the Building and/or any other person, and

(E) indemnify and keep indemnified the other Owners and occupiers for the time being of the other parts of the Building against all loss, damage, injury, costs, expenses, actions, claims and demands whatsoever arising out or on account thereof or of any defects therein or of the failure to maintain the same in proper repair and condition.”  (my emphasis)

54.The learned judge also considered other clauses of the DMC, eg clauses 16-18 and 25 of section IV[38] and clause B1(4) of section V.[39] It was held that clause 7(c) of section I of the DMC unreservedly conferred on the developer exclusive use and enjoyment of the external walls, which right was not affected by other provisions in the DMC that were either irrelevant[40] or expressly/specifically “subject to” the developer’s right under clause 7 of section I of the DMC.[41] The learned judge distinguished Incorporated Owners of Hong Leong Industrial Complex based on different wording of the DMC as it was unclear but unlikely that the clauses in the DMC in that case had any proviso similar to “subject to cl.7 of Section I”. So “[it] is beyond argument that cl.7(c) of Section I of the DMC had specifically provided that the external walls are to the exclusive use and enjoyment of the Developer”. Further, “from the assignment produced in this case, such an exclusive right towards the external walls was also specifically reserved in the Schedule of the assignment” (at p 183).

55.In the circumstances, the learned judge followed the ratio in Uniland Investment Enterprises Ltd in paragraph 49 above, and held the developer (who had Exclusive Right over the external walls) to be responsible for maintenance of the external walls in accordance with sections 34C(2) and 34H, and clause B1(4) of section V of the DMC that imposed on the manager a duty to paint and white-wash the external walls was void as being inconsistent with section 34H of the BMO.

56.Mr Lam submitted Green & Grace Ltd was distinguishable on the facts as it turned on particular provisions of the DMC in that case, and Mr Ng fairly accepted provisions in such DMC were somewhat different from those in the Subject DMC. I note particularly that the Subject DMC did not have any express provision like clause 7(c) of section I of the DMC in Green & Grace Ltd, so the Subject DMC did not give similar rights in respect of the External Walls to the Developer. Given the emphasis laid by the learned judge on clause 7(c) of section I of the DMC in Green & Grace Ltd in coming to her conclusion, I find this authority to be of limited assistance.

57.Discussion Turning to the Subject DMC, there were a few obvious and indisputable matters:

(a) the definition of “Common Areas” in Section I included (and “Common Parts” by virtue of its definition in Section I also included) “all those areas of the Land and the Building which comprises …… (k) External Walls of the Building; and (l) Those other parts of the Building the right to use of which is given and/or reserved by this Deed to more than one Owner” (my emphasis), so the External Walls were expressly/specifically identified as a “Common Area” and “Common Part” under the Subject DMC without need to resort to the definition of “common parts” under section 2 of the BMO;
(b) the “Common Parts” were allocated 20 undivided shares under the Third Schedule being the “Common Part Shares” as defined in Section I;
(c) the Developer held the Common Part Shares as legal owner up until the Assignment in 2010.

58.The fact the Developer reserved the Common Part Shares (see paragraph 57(c) above) did not ipso facto mean it had exclusive possession over the “Common Parts” as defined in the Subject DMC (see paragraphs 31 and 40 above). But I have no doubt the definitions of “Common Areas” and “Common Parts” in the Subject DMC insofar as they related to the External Walls were to designate the External Walls as common parts of the Building. This is borne out by:

(a) the nature of the areas itemised in sub-paragraphs (a)-(i) in the definition of “Common Areas” in Section I[42] (which were plainly “common use areas” as explained in footnote 10 above);
(b) sub-paragraph (l) in the definition of “Common Areas” in Section I (which suggested the areas in the preceding sub-paragraphs that included the External Walls were those areas of the Land and Building with “right to use” given or reserved to more than one Owner, ie which no Owner(s) had exclusive “right to use”);
(c) consistency with the definition of “common parts” under the BMO as explained above.

59.Ps’ contention that Clauses 8(b)-(c) expressly gave or reserved Exclusive Right over the External Walls to the Developer (and thereby excluded the same from the common parts of the Building since “exclusive use areas” and “common use areas” were mutually exclusive – see paragraph 20 above) appeared to directly contradict the express and specific identification of the External Walls as common parts of the Building under the definitions of “Common Areas” and “Common Parts” in section I as explained above.

60.Mr Ng made 2 submissions in this respect, which I do not accept. First, Mr Ng argued sections 38C(2) and 34H required the definitions of “Common Areas” and “Common Parts” in Section I insofar as and to the extent they suggested the External Walls were common parts of the Building (such that all Owners except the Developer had to bear the repair/maintenance expenses) to be read down as subject to Clauses 8(b)-(c) (which (as Ps contended) gave or reserved Exclusive Right over the External Walls to the Developer). I disagree as such argument mixed up 2 issues:

(a) The anterior issue was the interpretation/construction of the Subject DMC to ascertain its true meaning, ie whether it designated the External Walls as common parts of the Building or as areas which the Developer had exclusive possession and/or Exclusive Right. It is only when a view was formed on such anterior issue that one could proceed to the posterior issue as to whether any provision in the Subject DMC infringed sections 34H and 34C(2).
(b) For the anterior issue, one cannot say because 1 particular provision in the DMC suggests grant or reservation of exclusive possession or Exclusive Right to the Developer and other provisions suggest otherwise, the former provision must be struck down as void pursuant to sections 34H and 34C(2). Rather, the proper approach on the anterior issue is to consider the DMC as a whole and to read the provisions together to ascertain its true meaning.[43]
(c) I disagree with Ps’ construction of Clauses 8(b)-(c). This is discussed in further detail below, but suffice to state here I do not consider Clauses 8(b)-(c) gave or reserved exclusive possession or Exclusive Right over the External Walls to the Developer.

61.Secondly, Mr Ng submitted Incorporated Owners of Million Fortune Industrial Centre helpfully pointed out that even though a DMC defined certain parts of the land and building as common parts, it might “contain provisions whereby areas constituting the common parts might lawfully be re-designated for the exclusive use of individual owners”, so here Clauses 8(b)-(c) clearly “re-designated” exclusive use of the External Walls to the Developer notwithstanding inclusion of the External Walls in the definitions of “Common Areas” and “Common Parts” in the Section I. I disagree.

62.Careful study of Incorporated Owners of Million Fortune Industrial Centre showed the definition of “Common Parts” in the DMC was expressly subject to the proviso “[unless] otherwise designated by [the developer and first owner]” (see paragraph 30 above). So the DMC itself contemplated the areas expressly defined as “Common Parts” could (if re-designated by the developer and first owner) cease to be such. This was why Litton NPJ said “[the] DMC in a particular case may contain provisions whereby areas constituting the common parts might lawfully be re-designated for the exclusive use of individual owners” (see paragraph 33 above). Here, there was no such or similar proviso in the definitions of “Common Areas” and “Common Parts” in the Subject DMC which essentially were unqualified, and one must read such definitions together Clauses 8(b)-(c) in light of the Subject DMC as a whole to elicit the proper construction. In carrying out such exercise, an obvious question would arise as to why, if (as Ps contended) Clauses 8(b)-(c) granted or reserved Exclusive Right over the External Walls to the Developer, the External Walls were expressly identified as “Common Areas” or “Common Parts” in Section I. The specific designation of the External Walls as a common part in the DMC was something that Cheung JA took into account in Incorporated Owners of Shatin New Town (see paragraph 40 above).

63.Before I deal with Clauses 8(b)-(c), I turn to Clause 1 of Section II that provided that the Developer was entitled to “full right and privilege to the exclusive use occupation and enjoyment and this rents and profits” in respect of parts of the Land and Building against its name in the Third Schedule, ie all shops, flats and self-contained portions and other portions (not otherwise intended to be used for the common enjoyment of the co-owners and co-occupiers for the time being of the Building) other than the FP Flat which the First Purchaser had exclusive use, occupation and enjoyment.

64.As seen in the Second Schedule, shops and flats referred to shops A to T on the ground floor and the flats A-H on the 2nd to 25th floors of the Building. Where the context permitted or required, “Unit” was defined in Section I to include “Flat, Shop or self-contained portion of the Building intended for separate use and occupation”. Plainly, the External Walls were not shops, flats or self-contained portions. By virtue of the definitions of “Common Areas” and “Common Parts” as explained above, the External Walls were identified as common parts of the Building and not for “separate use and occupation”,[44] so the External Walls were also not Units. Whilst on the matter of “Units”, I digress to note that whilst the Developer was the legal owner of 20 undivided shares being the “Common Parts Shares” (that comprised the External Walls), it did not have to pay management fees in relation thereto.[45]

65.But were the External Walls “other portions (not otherwise intended to be used for the common enjoyment of the co-owners and co-occupiers for the time being of the Building)”? Given the definitions of “Common Areas” and “Common Parts” in Section I, and for reasons set out in paragraph 58 above, the Subject DMC essentially defined “Common Areas” and “Common Parts” (which included the External Walls) as for the common enjoyment of co-owners/co-occupiers for the time being of the Building. As the areas specified for exclusive use by the developer in Clause 1 of Section II and the Third Schedule did not include the “Common Areas” and “Common Parts”, such provisions did not grant or reserve unto the Developer Exclusive Right over the External Walls. I bear in mind that Mr Ng suggested the process of identifying “common parts” is by eliminating the “exclusive use areas” (see paragraph 27 above), and the External Walls were plainly not an “exclusive use area” under Clause 1 of Section II and the Third Schedule.

66.But Mr Ng submitted Clause 1 of Section II and the Third Schedule were not exhaustive as to portions of the Land and Building in respect of which the Developer had Exclusive Right because Clauses 8(b)-(c) gave or reserved unto the Developer Exclusive Right over the External Walls. I have the following observations:

(a) As alluded above, I am not with Ps in their interpretation/construction of Clauses 8(b)-(c). But more of this below.
(b) There was a provision similar to clause 1 of section II in the first schedule of the DMC in Incorporated Owners of Million Fortune Industrial Centre (see paragraphs 30(d) and 32 above), which DHCJ To (as he then was) and Rogers VP took into account (see paragraphs 31-32 above) in concluding that the 1st and 2nd defendants did not have Exclusive Right over the disputed area notwithstanding the assignment of such area to the 1st and 2nd defendants expressly assigned such Exclusive Right to them.
(c) Lord Hoffmann and Cheung JA admonished that construction of a DMC is to give what a reasonable man would have understood the parties to mean (see paragraph 28 above). Thus, so long as the meaning is clear, any unreasonableness or absurdity in construction is to be avoided (see paragraphs 28 and 40 above). But in my view, Ps’ construction would require this court to conclude that within the same Subject DMC, the External Walls were on the one hand expressly stated to be “common use areas” (see definition of “Common Areas” and “Common Parts” in Section I) and on the other hand expressly stated to be “exclusive use areas” (see Ps’ contention as to the meaning of Clauses 8(b)-(c) in Section II), which areas should be mutually exclusive (see paragraphs 20 and 62 above). Careful consideration is required before this court can conclude this was intended by the provisions of the Subject DMC.

67.It is convenient to now turn to Clauses 8(b)-(c). I start with Clause 8(b). Mr Ng emphasised the word “use” in the reservation of “…… the exclusive right to install in or affix to and use (or permit any person or corporation to install in or affix and to use) …… the external walls ……” (my emphasis) unto the Developer to say it was an “unqualified right” that gave the Developer final say as to who could use the External Walls and how the External Walls would be used, so the Developer had Exclusive Right over the External Walls that would bring in section 38H. I disagree.

68.First, it is necessary to properly understand what right was actually reserved under Clause 8(b). When pared down to the essentials and ignoring for the time being the proviso, Clause 8(b) could be summarised as follows:

(a) Right (i) “exclusive right to install in or affix to and use”;
(ii) “exclusive right to …… permit any person or corporation to install or affix to and use”; and
(iii) “the right to repair, maintain, service, remove or replace the same [ie the objects in (c) below]”
(b) Location for (c)(ii) below, “any part of the Building to which no Owner(s) has the exclusive right to occupy including the external walls
(c) Object (i) “install in or affix to” “such flues, pipes conduits, chimneys, aerials, plant machinery and other apparatus, as the [Developer] shall think fit” AND “use” “any part of the Building to which no Owner(s) has the exclusive right to occupy including the external walls” (Mr Ng’s submission); or (ii) “install in or affix to and use” “such flues, pipes, conduits, chimneys, aerials, plant machinery and other apparatus, as the [Developer] shall think fit” at the location in (b) above (alternative construction).

69.From paragraph 68(b) above, Clause 8(b) clearly recognised the External Walls were part of the Building to which no Owner(s) had exclusive right to occupy. So the remaining question was whether the right granted or reserved under Clause 8(b) amounted to Exclusive Right to use and enjoy the External Walls. I prefer the construction in paragraph 68(a), (b) and (c)(ii) above which, in my view, made natural reading and logical sense. The construction in paragraph 68(c)(i) above suggested by Mr Ng had inherent difficulties:

(a) The construction in paragraph 68(c)(i) above in relation to machinery/apparatus required the reader of Clause 8(b) to jump/skip the italised words in brackets below to reach such understanding: “the exclusive right to install in or affix to [and use] (or permit any person or corporation to install in or affix [and use]) [any part of the Building to which no Owner(s) has the exclusive right to occupy including the external walls] such flues, pipes conduits, chimneys, aerials, plant machinery and other apparatus, as the [Developer] shall think fit ……” I find this made strained reading.
(b) Such construction that purported to give “unqualified right” to install or affix “such flues, pipes conduits, chimneys, aerials, plant machinery and other apparatus, as the [Developer] shall think fit” (in contra-distinction to “use” of the External Walls that no Owner(s) had the exclusive right to occupy) did not give the location where these objects were to be installed/affixed, which cannot be right.
(c) If the Developer had “unqualified” right to “use” the External Walls for any purpose and in any way it wished,[46] which would have included advertising rights (eg installing/affixing advertising signs and signboards), it appeared strange for such advertising rights to be subject to the provisions of SC6(l) and subject to the requirement to “not unnecessarily interrupt the enjoyment of any unit in the Building” under Clause 8(c) but other rights under the Exclusive Right were not.

70.Thus, notwithstanding Ps’ contention that the Developer had Exclusive Right and corresponding obligation over the External Walls, I am of the view the rights reserved under Clause 8(b) were limited rights that gave the Developer exclusive ability to put up and use (or allow others to put up and use) the objects in paragraph 68(c)(ii) above at inter alia the External Walls over which it had no exclusive right to occupy.

71.Clause 8(b) is similar to clause 1.01(C) of the DMC in Incorporated Owners of Goa Building (see paragraph 35 above) although the wording was not exactly the same:

“The Vendor …… have the sole and exclusive right and privilege …… (C) Subject to any necessary approval of the Government Authority or Department to erect, construct, install, affix or fit up one or more flu pipes or smoke stacks or chimneys at to or on such part or parts of the open yard or yards and of the external walls of the said Building as the Vendor shall in its absolute discretion think fit and to remove replace or repair the same and to enter upon any unit at all reasonable times with or without workmen for the purpose of so doing.” (my emphasis)

Rogers VP held such provision did not give exclusive possession of the open yard(s) and external walls of the building to the first owner (ie the developer), and it only gave part but not all of the full/exclusive rights that might be enjoyed by the developer and first owner (see paragraphs 36-37 above). This, in my view, lent weight to my construction of Clause 8(b) that the rights granted or reserved thereunder were not all but only some of the rights over the External Walls.

72.Mr Ng submitted Incorporated Owners of Goa Building could not assist because clause 1.01 of the DMC in that case gave Exclusive Right for “units” (Clause 1.01(A)) but only gave the right to erect/ maintain signboards, flu pipes, smoke stacks or chimneys etc at the external walls (Clauses 1.01(B)-(C)), which led Rogers VP to conclude that the developer was not given exclusive possession or Exclusive Right over the External Walls, but such provisions were fundamentally different from Clauses 8(b)-(c). I disagree.

73.It was true that Clause 8(b) gave “exclusive right to install in or affix to and use (or permit any person or corporation to install in or affix to and use) ……” (my emphasis), and clause 1.01(B)-(C) of the DMC in Incorporated Owners of Goa Building did not refer to right to “use”. But the label “exclusive rights” for erecting pipes on the exterior walls and using exterior walls for advertising purposes did not aid the respondent in Incorporated Owners of Shatin New Town when those rights were in truth qualified (see paragraph 40 above). Indeed, even though Cheung JA found the wording of the relevant clause in the DMC in Incorporated Owners of Goa Building different from that in Incorporated Owners of Shatin Town Lot, construction of the effect of the former clause was equally applicable to the latter clause (see paragraph 40 above). Likewise, the developer was given exclusive right to use the external walls in the DMC in Incorporated Owners of Hong Leong Industrial Complex, but Rogers VP held such right was not an exclusive right as normally understood as it was qualified by the manager’s powers in relation to the external wall (see paragraph 42 above). In Yan Yan Motors Ltd, the DMC drew a distinction between “the exclusive right to use” the main roof and the right “to use” the external walls and flat roof that was reserved to the developer, but Chow J considered/discussed the latter right on the basis that it was “the Developer’s exclusive right to use the External Walls under clause 3(b) and (c) of the DMC …… limited to the erection, installation and display of signboards, advertisements, decorations, lights, lanterns, articles and other display materials” (see paragraph 44 above). This did not dissuade the learned judge from finding such right did not comprise all rights amounting to exclusive possession or Exclusive Right over the external walls, especially when such right was qualified by the manager’s powers over the external walls for some limited purposes (see paragraph 44 above).

74.As seen in paragraph 78 below, a host of powers/obligations in relation to the External Walls was given to the Manager (not the Developer) under the Subject DMC. Whilst other relevant clauses in the Subject DMC will be discussed in further detail in paragraph 97 below, it is useful to highlight here Clause B1(4) of Section VI which provided inter alia the Manager had full/unrestricted authority to manage the Building with a duty “[to] paint white-wash tile (or otherwise treat as may be appropriate) and put in hand any other necessary maintenance of the exterior wall and Common Areas ……”.

75.Mr Ng submitted such segregation of the exterior walls (ie External Walls) from the “Common Areas” in such provision reflected an intention to carve out the External Walls from “Common Areas”, and by imposing a mandatory duty on the Manager to be responsible for maintaining the External Walls such provision was void for contravening sections 34C(2) and 34H. I disagree:

(a) I do not see any “segregation” or carving out of the External Walls from the “Common Areas”. Although “exterior walls” and “Common Areas” were individually mentioned in Clause B1(4) of Section VI, the Manager was given the same duty over both of them, “[to] paint white-wash tile (or otherwise treat as may be appropriate) and put in hand any other necessary maintenance ……”, so reference to “exterior wall” as well as “Common Areas” in this provision could only be for emphasis and avoidance of doubt.
(b) Mr Ng referred to clauses 7(a) and 8 of the DMC in Uniland Investment Enterprises Ltd which he said were similar to Clause B1(4) of Section VI (see paragraph 47 above), and submitted that just as those clauses did not aid the plaintiff owner of the disputed area in that case, Clause B1(4) of Section VI also would not advance D1’s case.
But the DMC in Uniland Investment Enterprises Ltd was wholly different from the Subject DMC. Clause 1(i) of the DMC in Uniland Investment Enterprises Ltd expressly provided the plaintiff had full/exclusive right and privilege to hold, use, occupy and enjoy the outer wall and flat roof in so far the same have not been assigned to any other owners, so such disputed area did not form part of the common areas of the building (see paragraph 48 above). Also, the plaintiff had not assigned the 1 share allocated for the disputed area. So the only proper interpretation was “the plaintiff as owner of one share is entitled to exclusive possession, use and enjoyment of the outer wall and flat roof” even though the manager was responsible for their maintenance at no cost to the plaintiff. In my view, such particular provisions of the DMC were the reason why the 1st and 2nd defendants did not dispute such interpretation (see paragraph 48 above).
The Subject DMC did not have any provision similar to clause 1(i) of the DMC in Uniland Investment Enterprises Ltd. Rather, the definition of “Common Areas” and “Common Parts” in Section I expressly included the External Walls (see paragraph 57(a) above), and Clause 1 of Section II and the Third Schedule ousted the External Walls from its description of the Developer’s “exclusive use areas” (see paragraphs 63-66 above). In any event, for reasons set out in paragraphs 47-51 above, Uniland Investment Enterprises Ltd were premised on common ground between the parties (but here it was a matter of debate), and its ratio turned on a different issue that would not aid the construction in question.
(c) Mr Ng submitted clause B1(4) of the DMC in Green & Grace Ltd (see paragraph 54 above) did not favour the interpretation that D1 contended in the present action. But the DMC in that case was very different from the Subject DMC. Clause 7(c) of section I in such DMC specifically reserved unto the developer “exclusive right and privilege to hold use occupy and enjoy or otherwise dispose of or deal with the external walls of the Building”, which was akin to the DMC in Uniland Investment Enterprises Ltd, and it was due to such unequivocal reservation of Exclusive Right over the external walls (which was absent in the Subject DMC) that the learned judge in Green & Grace Ltd concluded it was unaffected by other provisions (see paragraphs 54-56 above).
(d) In my view, neither Uniland Investment Enterprises Ltd nor Green & Grace Ltd was of assistance in construing the Subject DMC.

76.Further, irrespective whether or not the construction of Clause 8(b) should be as set out in paragraph 68(c)(i) above (as Mr Ng suggested) or 68(c)(ii) above, the rights reserved thereunder were restricted/qualified and not any Exclusive Right envisaged in section 34H. After all, such rights were not absolute but were “subject to all necessary approvals or consents of the appropriate Government authorities having been had and obtained”.

7.Whilst the DMC in the cases cited by Mr Lam were all somewhat differently worded, the constant theme was notwithstanding the grant or reservation unto the developer of any “exclusive right” to use the disputed area or to do certain acts, the developer would not have exclusive possession or Exclusive Right over the disputed area (whether external walls or otherwise) if in fact such right (a) was not the entirety of all rights that amounted to exclusive possession or Exclusive Right and/or (b) was qualified by, say, such rights/powers (which might be limited) given to the manager or others. This had to be read together with (i) the definition of common parts in the DMC and any provision in the DMC for absolution of the developer from having to pay costs/charges relating to the management of the building in respect of such common parts (see paragraphs 32 and 40 above), and (ii) Clause 20 of Section V to which I now turn.

78.Clause 20 of Section V insofar as it related to Clause 8(b) gave or reserved unto “the [Developer] …… or licensees of the exclusive right immediately mentioned” “…… the sole and exclusive right …… to install construct erect one or more flue pipes, smoke stacks or chimneys on such part or parts of the external walls at the rear or side or both the rear and side of the Building ……”, but “[notwithstanding] anything to the contrary herein contained” such right was qualified by the following:

(a) “subject to the prior approval in writing of the Director of Lands and the Manager and in accordance with and subject to such conditions provisions and restrictions as may be imposed by them or either of time”;
(b) “PROVIDED ALWAYS such …… flue pipes, smoke stacks or chimneys shall not unduly interfere with each owner’s proper use and enjoyment of his own Unit of the Building”;
(c) “PROVIDED ALWAYS …… the [Developer] …… or licensees shall at all times observe and comply with all the laws and regulations relating to erection maintenance and dismantling of …… chimneys”;
(d) “PROVIDED ALWAYS …… the [Developer] …… or licensees …… shall be solely responsible for the repair maintenance upkeep renewal and removal of any such …… chimneys and such portion(s) of the external walls parapet walls of the Building that have been used by them”;
(e) “Provided Further That the [Developer] …… or licensees for the time being entitled to the said right will each in respect of their liability hereunder at all times indemnify and keep indemnified the other owners and occupiers for the time being of the Building against all loss damage injury costs expenses claims actions and demands arising from or on account of or resulting from the installation reparation renewal maintenance and upkeep of such …… chimneys or resulting from the use of such portion(s) of the external walls parapet walls of the Building or from any defect therein or any failure to maintain the same in proper repair and condition”.

79.Reading Clause 8(b) together with Clause 20 of Section V[47] plainly showed the “exclusive right” given or reserved unto the Developer under Clause 8(b) was qualified/restricted as explained in paragraphs 76-78 above.

80.Indeed, rights given or reserved unto the developer in clause 1.01(C) (see paragraphs 35 and 71 above) and clause 3.02 (see paragraph 35 above) in the DMC in Incorporated Owners of Goa Building contained mirror (or at least very similar) qualifications:

(a) “[subject] to any necessary approval of the Government Authority or Department” (clause 1.01(C));
(b) “[the] person or persons …… in whom the sole and exclusive right and privilege to erect, construct, install, affix, fit up or maintain any …… chimney, flu pipe or smoke stack mentioned in Clause 1.01 hereof …… is for the time being vested …… shall at all times observe and comply with all the laws and regulations relating to the erection maintenance and dismantling thereof ……” (Clause 3.02);
(c) “[the] person or persons …… in whom the sole and exclusive right and privilege to erect, construct, install, affix, fit up or maintain any …… chimney, flu pipe or smoke stack mentioned in Clause 1.01 hereof …… is for the time being vested …… shall be solely responsible for the repair, maintenance, upkeep, renewal and removal of any such chimney, flu pipe or smoke stack and the part of the said Building in common use and the portion or portions of the external walls and the portion or portions of the open yard or yards of the said Building at which and/or to which and/or upon which such …… flu pipe or smoke stack shall be erected, constructed, installed, affixed, fitted up or maintained” (Clause 3.02);
(d) “such person or persons shall at all times indemnify and keep indemnified the owners and occupiers for the time being of the said Building against all loss, damage, injury, costs, expenses, actions, claims and demands arising out of or on account of or resulting from the installation, repair, renewal, removal, maintenance and upkeep of such …… chimney, flu pipe or smoke stack or any defect therein or any failure to maintain the same in proper repair and condition” (Clause 3.02).

It was for these very qualifications/restrictions that Rogers VP came to the view the rights granted or reserved unto the developer by the DMC in Incorporated Owners of Goa Building did not amount to exclusive possession or Exclusive Right over the external walls (see paragraphs 36-37 above). Likewise, the DMC in Incorporated Owners of Shatin New Town contained restrictions/qualifications similar to those in the Subject DMC (see paragraphs 40 and 78(a)-(b) above), and Cheung JA found the so-called “exclusive rights” as to the exterior walls in such DMC only conferred rights for limited purpose and not exclusive possession or Exclusive Rights over the external walls (see paragraph 40 above). The DMC in Incorporated Owners of Hong Leong Industrial Complex had a qualification similar to the one in paragraph 78(a) above, and since the developer’s rights in relation to the external walls were subject to such condition Rogers VP found it did not have exclusive possession or Exclusive Right over the external walls (see paragraph 42 above).

81.Mr Ng tried to downplay the impact of these case authorities, but I disagree with his contentions:

(a) Mr Ng suggested the Court of Appeal was solely focused on the issue of exclusive possession/use in Incorporated Owners of Shatin New Town, and the reason why the disputed area was held to be not within the developers’ exclusive possession was because (i) there would be unthinkable consequences if such area could only be used at the whim and pleasure of the developers and (ii) the only right conferred on the developers was a right to use the disputed area for advertising purposes and to display/install/erect/affix advertising signs etc as well as permission to do such acts (but the right conferred by Clause 8(b) was unqualified use or permission to use).
In my view, although Cheung JA in Incorporated Owners of Shatin New Town discussed the issue of exclusive possession, he did advert to the qualifications referred to in paragraph 40(a)-(b) above and found the so-called exclusive rights conferred on the developers only rights of limited purpose. Further, I am not with Mr Ng in his interpretation/construction of Clause 8(b) (see paragraph 68-70 above), especially when such clause had to be read together with Clause 20 of Section V (see paragraph 78 above). As for the contention in (i) above, that was a separate point addressed in paragraph 86 below. There is no merit to these arguments.
(b) As for Incorporated Owners of Hong Leong Industrial Complex, Mr Ng submitted once again that a key reason for Rogers VP’s decision was that, on true construction of clause 12(a)-(b) of the DMC in that case, the manager of the building in fact retained ultimate control over who could use (or not use) the external walls, but the Developer in the present action retained “exclusive right” to “permit” others to “use” without giving corresponding powers on part of the manager.<
There is no merit to this argument when as explained in paragraph 79 above one could not take a blinkered view of Clause 8(b) without considering Clause 20 of Section V, which provision was stated to be “[notwithstanding] anything to the contrary” and applied to the Developer or its licensee of “the sole and exclusive right …… to install construct erect one or more flue pipes, smoke stacks or chimneys on such part or parts of the external walls at the rear or side or both the rear and side of the Building …….”, which necessarily harked back to Clause 8(b). This showed that if the Developer wanted to erect, say, a chimney at the External Wall at the front of the Building, it was not restricted by Clause 20 of Section V, but the Developer would be subject to and had to comply with such restrictions if it wished to erect, say, a flue pipe on the rear or side External Wall.
(c) Mr Ng submitted Yan Yan Motors Ltd was irrelevant as the rights reserved for the developer there were distinguishable as they involved qualified rights to use the external walls for a specific purpose. But for the reasons set out in (b) above and in paragraphs 76-80 above, I reject such contention.

82.Mr Ng submitted the indemnity proviso in Clause 20 of Section V (see paragraph 78(e) above) supported Ps’ stance. But I find the 2 provisos in paragraph 78(d)-(e) above were in fact against Ps’ contentions. First, as seen in Clause B1(4) of Section VI (see paragraph 74-75 above) and Clause D1 of Section VI, the Subject DMC imposed on the Manager and not Developer the duty to paint, white-wash, tile, treat and maintain the External Walls, and obliged the Owners (except the Developer – see Clause D2 of Section VI) to pay maintenance and management expenses. But the repair/maintenance proviso in paragraph 78(d) above required the Developer to inter alia repair/maintain the chimney erected/installed at the rear/side External Wall and “such portion(s) of the external walls …… that have been used by them” (ie only those parts of the External Walls that had been used for erection/ installation of such chimneys). This did not sit well with Ps’ contention that the Developer had Exclusive Right over all External Walls and hence had obligation to repair/maintain all External Walls (rather than portions used for, say, advertising or putting up a chimney) and pay the costs therefor.

83.Mr Ng submitted the provisos under Clause 20 of Section V would be applicable where the Developer granted permission to a licensee to exercise the rights given or reserved under Clause 8(b). But such provision referred not just to the licensee but also to the Developer itself, and there was no sensible explanation why particular mention was made of the Developer’s responsibility to repair/maintain portions of the External Walls that it had used for the limited purpose of, say, advertising or putting up a chimney. In my view, such proviso was plainly of limited scope and did not reflect Exclusive Right over all External Walls or any obligation on the part of the Developer for all External Walls.

84.Secondly, for the indemnity proviso in Clause 20 of Section V (see paragraph 78(e) above), it likewise provided for the Developer and its licensee to indemnify other Owners/occupiers for loss and damage as a result of, say, installing a chimney on the side/rear External Wall or “resulting from the use of such portion(s) of the external walls …… or from any defect therein or any failure to maintain the same ……” This echoed the repair/maintenance proviso in that the indemnity (insofar as the External Walls were concerned) only covered those parts of the External Walls used for, say, installing a chimney and did not extend to all External Walls. Mr Ng submitted the indemnity proviso was a “catch-all safety-net provision” which the Developer had to be responsible in any event. But if that were the case, there was little point to make particular mention of the Developer’s limited responsibility over portions of the External Walls.

85.Thirdly, there were similar repair/maintenance and indemnity provisos in the DMC in Incorporated Owners of Goa Building (see paragraph 80(c)-(d) above), and the limitations inherent in such provisos were factors that Rogers VP took into account in coming to the conclusion that the developer in that case did not have exclusive possession or Exclusive Right over the external walls (see paragraph 36 above). In my view, Clause 20 of Section V leaned in favour of D1’s stance and did not help Ps’ stance.

86.Mr Lam next submitted that to read Clause 8(b) as Ps suggested (ie the Developer reserved Exclusive Right over the External Walls) would bring about an absurd result similar to what Rogers VP observed in relation to the proposed reading of clause 1.01 of the DMC in Incorporated owners of Goa Building (see paragraph 37 above). Here, the Developer by Clause 8(b) reserved the right of putting up and using (or allowing others to do so) the objects in paragraph 68(c)(ii) above at “any part of the Building to which no Owner(s) has the exclusive right to occupy including the External Walls”, so the Developer could put up (or allow others to put up) such objects not only at the External Walls but also any other “part of the Building to which no Owner(s) has the exclusive right to occupy” such as the “Common Areas” and/or “Common Parts” as defined in Section I. If Ps’ argument[48] were to its logical conclusion, the Developer also would have sole obligation to repair/maintain the “Common Areas” or at least the “Common Parts”[49] (being areas where the Developer could exercise its alleged Exclusive Right under Clause 8(b)) and to bear the costs/expenses therefor, but at the same time other Owners could also use, occupy and enjoy the other “Common Areas” or “Common Parts” as defined in Section I. After all, Mr Ng made clear Ps accepted the other “Common Areas” and “Common Parts” were common parts of the building for which the Owners and D1 (not the Developer) had responsibility to repair/maintain and to pay the costs therefor. I agree with Mr Lam the construction put forward by Ps would lead to a troubled result, and could not have been the true intention of such provisions in the Subject DMC.

87.I now turn to Clause 8(c). When pared down to the essentials and ignoring the provisos for the time being, the rights reserved unto the Developer under Clause 8(c) could be summarised as follows:

(a) Right (i) “exclusive right to use”;
(ii) “exclusive right to …… grant the right to use”;
(iii) “the right to remove, repair, maintain, service, remove or replace the same [the objects in (c)(ii)-(iii) below]” (my emphasis)
(b) Location “all the external walls parapet walls canopies of the Building or any part or parts thereof ……”
(b) Object (i) “for advertising purpose”;
(ii) “to display, install, erect, affix …… thereon or thereto such advertising signs or structures whatsoever (whether illuminated or not)”;
(iii) “to …… permit to be displayed, installed, erected or affixed thereon and thereto such advertising signs or structures whatsoever (whether illuminated or not)”

88.In my view, Clause 8(c) did not give or reserve unto the Developer Exclusive Right over the External Walls. Rather, it reserved advertising rights in relation to inter alia the External Walls, and such advertising rights would at best be one of the rights in respect of the External Walls. I note Clause 8(c) was similar to clause 1.01(B) of the DMC in Incorporated Owners of Goa Building (see paragraph 35 above) although the wording is not exactly the same:

“The Vendor shall …… have the sole and exclusive right and privilege …… (B) Subject to any necessary approval of the Government Authority or Department to erect, construct, install, affix, fit up, paint and maintain any signs, signboards, advertisements, placards, posters or any other structureswhatsoever of such size and design whether illuminated or otherwise and at to or on such position or positions of the external walls of the said Building and of any part of the said Building in common use as the Vendor shall in its absolute discretion think expedient or desirable and to remove replace or repair the same and to enter upon any unit at all reasonable times with or without workmen for the purpose of so doing …… ” (my emphasis)

Rogers VP held such provision did not give exclusion possession or Exclusive Right over the external walls to the developer, and such rights as given or reserved were merely part of the rights that might be enjoyed by an owner but not the full and exclusive rights (see paragraphs 36-37 above). The discussion in paragraphs 71-75 above applied mutatis mutandis.

89.Further, the advertising rights reserved under Clause 8(c) were in any event limited rights and not any Exclusive Right since they were subject to the provisions of SC6(l) and the requirement for “all necessary approvals and consents of the appropriate Government authorities having been had and obtained”. The discussion in paragraph 77 above also applied mutatis mutandis, so Clause 8(c) had to be read together with Clause 20 of Section V which insofar as it related to Clause 8(c) gave or reserved unto “the [Developer] …… or licensees of the exclusive right immediately mentioned” being “…… the sole and exclusive right to erect install affix fit up exhibit or paint any signboards signs or advertisements (whether illuminated or otherwise) on the external walls parapet walls of the Building”, but “[notwithstanding anything to the contrary herein contained” such right was qualified by the following:

(a) “subject to the prior approval in writing of the Director of Lands and the Manager and in accordance with and subject to such conditions provisions and restrictions as may be imposed by them or either of time”;
(b) “PROVIDED ALWAYS such signboards signs advertisements …… shall not unduly interfere with each owner’s proper use and enjoyment of his own Unit of the Building”;
(c) “PROVIDED ALWAYS …… the [Developer] …… or licensees shall at all times observe and comply with all the laws and regulations relating to erection maintenance and dismantling of signs signboards advertisement ……”;
(d) “PROVIDED ALWAYS …… the [Developer] …… or licensees …… shall be solely responsible for the repair maintenance upkeep renewal and removal of any such signs signboards advertisements …… and such portion(s) of the external walls parapet walls of the Building that have been used by them”;
(e) “Provided Further That the [Developer] …… or licensees for the time being entitled to the said right will each in respect of their liability hereunder at all times indemnify and keep indemnified the other owners and occupiers for the time being of the Building against all loss damage injury costs expenses claims actions and demands arising from or on account of or resulting from the installation reparation renewal maintenance and upkeep of such signs signboards advertisements …… or resulting from the use of such portion(s) of the external walls parapet walls of the Building or from any defect therein or any failure to maintain the same in proper repair and condition”.

90.In my view, Clause 8(c) when read together with Clause 20 of Section V plainly showed the so-called “exclusive rights” given or reserved unto the Developer thereunder was qualified or restricted as explained in the above paragraph. In fact, the rights given or reserved unto the developer in clauses 1.01(B) and 3.02 above (see paragraph 35 above) in the DMC in Incorporated Owners of Goa Building contained mirror or very similar qualifications:

(a) “[subject] to any necessary approval of the Government Authority or Department” (clause 1.01(C));
(b) same as paragraph 80(b)-(d) above save to replace “chimney, flu pipe or smoke stack” with “any sign, signboard, advertisement, placard, poster, other structure” (Clause 3.02).

91.As explained in paragraph 80 above, similar provisions in Incorporated Owners of Goa Building, Incorporated Owners of Shatin New Town and Incorporated Owners of Hong Leong Industrial Complex suggested the so-called “exclusive rights” given or reserved unto the developer were in fact not Exclusive Right over the external walls. I reiterate the discussions in paragraph 81-85 above. In my view, they would inform on the construction Clause 8(c), which by itself contained an added restriction of having to comply with SC6(l) in the exercise of the rights given or reserved thereunder.

92.Mr Lam made submissions mutatis mutandis to paragraph 86 above that since the Developer’s alleged exclusive right under Clause 8(c) to “use” or to grant the right to “use” covered not just the “external walls” but also “parapet walls and canopies of the Building or any part or parts thereof”, so the logical conclusion of Ps’ argument was that the Developer was obliged only to repair/maintain the “external walls” but also the “parapet walls and canopies of the Building or any part or parts thereof” and also to bear the costs therefor whilst the other Owners would enjoy the use, occupation and enjoyment of “the parapet walls, canopies of the Building or any part or parts thereof”. I agree for the same reasons in paragraph 86 above applied mutatis mutandis.

93.Mr Ng made a fall-back submission in relation to Clauses 8(b)-(c) by citing Rogers VP’s observations in Incorporated Owners of Hong Leong Industrial Complex that in practical reality “the only use which could have been made of the external walls would be for putting up signs, signboards or advertisements on the walls, or for erecting a chimney up the side of the building”, which Mr Ng argued was encapsulated in Clauses 8(b)-(c). However, I cannot see how this would assist because in Incorporated Owners of Hong Leong Industrial Complex Rogers VP’s observation was made in the following context (at p 468):

“16. Equally importantly, clause 12(a) and (b) give the Manager the power to absolve an owner from a restriction on placing signs or signboards or advertisements on the external walls. Hence, it was said that whatever interest the first defendant might have in the outer or external walls, it did not have the exclusive possession and the exclusive right to use and enjoy that part of the building because the Manager could permit others to make use of the external walls. In this respect, it is pertinent to observe that under clauses 2(a)(i) and (ii) of the DMC it would seem that, as a matter of practical reality, the only use which could be made of the external walls would be for putting signs, signboards or advertisements on the walls, or for erecting a chimney up the side of the building.”

So even though it was said the only use for the external walls was for, say, advertising purpose or erecting chimney, it was found the developer did not have exclusive possession or Exclusive Right over the external walls because under the DMC in that case the manager could permit others to use the external walls. Although there was no similar provision in the Subject DMC, there were other restriction discussed in paragraphs 76-80 and 91 above.

94.In my view, Clauses 8(b)-(c) did not support Ps’ contentions. It was even more obvious when such clauses were read together with Clause 8(d) that reserved unto the Developer the right to assign all or part of the “Common Parts” (and corresponding undivided shares) “to the Manager (or to an incorporated company whose principal business is that of estate management) for the general amenity of the Owners and other residents of the Building” but subject to the Subject DMC and the particulars and conditions of the New Grant. In my view, since the “Common Parts” (which included the External Walls) could only be assigned to the Manager or estate management company (and not exclusively any individual Owner) for the common use, occupation and enjoyment of all the Owners, such provision flied against any contention that the Developer reserved exclusive possession or Exclusive Right over the External Walls.

95.As alluded to above, Mr Lam submitted there were other provisions in the Subject DMC in relation to “Common Areas” and “Common Parts” supporting the construction that the External Walls were for common enjoyment of the co-owners/co-occupiers for the time being of the Building:

(a) Section III set out the easements, rights and privileges the benefit of which was held by each Owner, and Clause A gave each Owner the full right and liberty in common with the co-owners to “go pass and repass over and along and use the Common Areas …… of the Building for all purposes connected with the proper use and enjoyment of his Unit”.
I agree this was a relevant provision supporting D1’s proposition that the Developer had no exclusive possession or Exclusive Right over the Common Areas that included the External Walls,[50] and for reasons elaborated above I reject Mr Ng’s submissions that Clause 8(b)-(c) gave or reserved exclusive right that was “unqualified” and superior to those of the Owners under Clause A of Section III. Even though Mr Ng submitted the latter clause was qualified by “for the proper use and enjoyment of his Unit”, the significance of such right under Clause A of Section III was not whether it was qualified, but that it gave others (ie other Owners) rights over the External Walls that demonstrated the Developer did not have all the rights in relation the External Walls.
(b) Section IV set out the easements, rights and privileges to which each Owner was subject, and Clause 1 gave the Manager full rights and privileges to enter into and upon each Unit to inspect, examine, maintain and repair such Unit or the Building or any part(s) thereof “including cleaning of the Common Areas”.
Mr Ng submitted D1 did not plead reliance on this provision. But this court still had to consider the whole Subject DMC to ascertain the true meaning of the relevant provisions. It is inappropriate for this court to take a blinkered view of the provisions that Ps relied without proper consideration of the Subject DMC as a whole. Mr Ng next submitted these provisions were irrelevant, insignificant and/or had no bearing on the reservation of “exclusive use areas” in the Subject DMC, and they were subordinate to other rights of the Owners. I disagree. Having come to my construction of Clauses 8(b)-(c), these provisions only served to bolster my construction.
(c) Section V set out the covenants, provisions and restrictions to be observed and performed by the Owners. Clauses 4, 18 and 19 thereof prohibited the Owners (including the Developer) from “use cut injure alter or interfere with any part or parts of the Common Areas ……” and from putting up signs, signboards and other projections at the exterior of the Building or exterior walls of the shops without written consent or prior approval of the Manager and the Director of Lands. Clause 29 provided no Owner (including the Developer) shall cause any damage to or interfere “in any way” with the Common Areas. The detailed provisions are set out in the Annexure.
Although D1 did not specifically plead reliance on these provisions, the court had to consider the whole Subject DMC for proper construction of its provisions.
Mr Ng argued Clauses 18-19 only restricted the specific right to erect external projections and to display advertisements, which had no bearing on the general and unqualified reservation of “exclusive use areas” under Clause 8(b)-(c), and did not give the Manager a general right to permit others to use the External Walls. But the fact others could put up signs, signboards and other projections on the exterior walls with approval of the Manager and Director of Lands tended to show the Developer’s rights over the External Walls were not exclusive, which supported my construction of Clauses 8(b)-(c), ie the Developer did not have Exclusive Right over the External Walls.
Mr Ng argued Clause 29 was irrelevant as the External Walls were not “Common Areas” (which contention I have rejected), were insignificant, and had no bearing on the reservation of the exclusive use areas under the Subject DMC. In this respect, I reiterate my observations in (b) above. Instead, I find these provisions sat well with my construction of Clauses 8(b)-(c), ie the External Walls were common parts of the Building and hence the Manager rather than the Developer had obligations as to their condition, use and maintenance.
(d) Section VI dealt with the management of the Building, and Clauses B1(1), B1(15), B1(18), B1(20) and B1(26) empowered the Manager to employ a qualified architect to inspect inter alia the entire Building (save only the interior of the Building), Building Foundations, and “Common Areas”, to remove any structure, installation, signboard in or on “any part of the Building” which have been erected in contravention of the terms of the Subject DMC, to do all things for the purposes of maintaining and improving all facilities and services in or on the Building, to prevent “any person” from occupying or using the “Common Areas” otherwise than in accordance with, say, SC6(l) and the provisions of the Subject DMC, and to insure and keep insured the “Common Areas” and such insurance to be in the name of the Manager itself “for and on behalf of all the Owners”. The detailed provisions are set out in the Annexure.
Mr Ng submitted D1 did not plead reliance on such provisions, and in any event they were irrelevant (as the External Walls were not part of the “Common Areas”) and insignificant, and had no bearing on the reservation of the “exclusive use areas” under the Subject DMC. In this respect, I reiterate my observations in (b)-(c) above.

96.For all of the above reasons, the External Walls were common parts of the Building and not the Developer’s “exclusive use areas”. The Developer (who was merely the legal owner of the Common Parts Shares) never had any exclusive possession or Exclusive Right over the External Walls. In the circumstances, Ps’ claim fell to be dismissed without going into the Duty and Relief Issues (see paragraphs 17(c) and 97 below). However, for the sake of completeness, I will briefly deal with the Duty Issue.

III.  DUTY ISSUE

97.Irrelevance of Duty Issue  Clauses D1(b), (f), (g) and (m) of Section VI provided “[each] owner” (ie all co-owners of the Building) shall pay (a) the cost of carrying out all or any of the duties of the Manager set out in the Subject DMC, (b) the cost of effecting insurance in respect of or in connection with the management of the Building, (c) all charges payable by the Owners in respect of “all parts of” the Common Areas, and (d) any other items of expenditure, charges, premium, fees and other outgoings relating to the management, maintenance, operation, servicing, renewal, renovation or replacing of the Building necessary for good estate management of the Building. Thus, the Developer never had any general obligation to repair/maintain the External Walls except for limited obligation under Clause 20 of Section II to repair/maintain parts of the External Walls used for inter alia advertising signs and signboards or flue pipes and chimneys put up pursuant under Clauses 8(b)-(c) and 20.

98.Further, by reason of the matters discussed in paragraph 21(c), 23(c) and 64 above and Clause D2 of Section VI, the Developer had no obligation under the Subject DMC to pay or contribute to the management expenses and/or repair/maintenance expenses. So quite irrespective of the Assignment, the Owners (and later the IO) were responsible for the repair/maintenance of the External Walls and for payment of costs/expenses therefor. So Ps’ complaints about the Assignment and renovation works for the External Walls carried out in 2008 to 2012 were irrelevant to the issue of liability, and Mr Ng properly conceded Ps’ claim fell to be dismissed without going into the Duty and Relief Issues should I find (which I did) the External Walls to be common parts of the Building.

99.Duty Issue  The Duty Issue concerned inter alia whether D1 properly took up the External Walls (being part of the “Common Parts” and “Common Parts Shares”) from the Developer by way of the Assignment and/or whether it was in breach of duties owed to the Owners (including Ps) in doing so. Ps’ attack against the Assignment was limited to the External Walls and not other parts of the “Common Parts”, so for convenience I refer to the Assignment insofar as it related to the External Walls as “EW Assignment” below.

100.There was no dispute that D1, Developer and Manager were bound to comply with and observe the stipulations in the New Grant and Subject DMC and also the provisions in the BMO.

101.Ps’ case  In paragraphs 9-15 of Mr Ng’s written opening submissions, it was said D1 owed each Owner (including Ps) statutory,[51] fiduciary[52] and common law agency duties.[53] On such basis, Ps claimed that by implication of law D1 owed Ps inter alia the following duties: (a) to act in the best interests of Ps, (b) to exercise reasonable care and skill in the discharge of its duties, (c) not to put itself in a position where its interest and duty conflict, (d) to act in good faith, and (e) to act for proper purposes. Ps further claimed D1 owed a duty of care to them on the basis that inter alia it had assumed responsibility vis-à-vis them to take due care in execution of the Assignment and in managing/handling affairs in relation to the “Common Parts” and/or External Walls.

102.   On such basis, Ps claimed D1 was in breach of such duties:

(a) D1 failed to give Ps notice of the EW Assignment whether before or after execution thereof;
(b) D1 failed to convene any Owners’ meeting to approve/sanction D1’s execution of the EW Assignment, and there was no resolution passed at any Owners’ meetings to such effect;
(c) D1 put the Owners (including Ps) to unwarranted burden, risk and expenses by executing the EW Assignment at a consideration for $1, which was contrary to Ps’ best interests, because at that time the “Common Parts” were already encumbered with the 1st Order;
(d) with knowledge (i) the “Common Parts” and/or External Walls were encumbered with the 1st Order and (ii) all or at least part of the renovation expenses in respect of or pertaining to the External Walls ought to have been borne/paid by the Developer (which contention I have rejected), D1 failed to obtain an indemnity from the Developer for such expenses upon execution of the EW Assignment;
(e) the EW Assignment did not mention the “Common Parts” and/or External Walls were sold/assigned to D1 subject to the 1st Order and/or D1 shall bear all or at least part of the expenses for discharge of the 1st Order, but the Developer remained liable to comply with and discharge the 1st Order at its own expenses (which contention I have rejected as the Developer was not liable for the costs/expenses of any repair/maintenance of the External Walls) regardless of the 2nd Order, so D1 should have sought but failed to seek an indemnity from the Developer for costs/expenses incurred for compliance with the 2nd Order upon execution of the EW Assignment;
(f) since none of Ps ever authorised, consented to or appointed D1 as trustee to take up the EW Assignment and to hold the “Common Parts” and/or External Walls for the benefit or on behalf of Ps or any of them, D1 by executing the EW Assignment wrongfully imposed undue burden/liabilities on Ps;
(g) no legal advice was made available to Ps or other Owners regarding their rights, obligations as well as risks and liabilities prior/subsequent to D1’s purported execution of the EW Assignment;
(h) D1 forcibly imposed beneficial interests of the “Common Parts” and/or External Walls upon Ps.

103.In short, Ps alleged the Assignment was not in the common or best interest of the Owners, and its execution (and manner thereof) was contrary to D1’s duties owed to the Owners (including Ps), which breach of duty was not cured by subsequent resolution/approval by the Owners in respect of renovation works for the External Walls and collection of contributions from the Owners (including Ps) for such purpose. Ps’ complaints essentially focused on (a) whether proper notice with adequate disclosure had been given to the Owners (including Ps) in relation to renovation of the External Walls and EW Assignment, and (b) whether in the decision-making process D1 had sought/provided to the Owners (including Ps) any or any proper legal advice in relation to the External Walls. Further and/or alternatively, Ps claimed insofar as attributable or pertaining to the External Walls, all or at least part of the costs/expenses for discharge of the 2nd Order (being a continuation of and in identical terms to the 1st Order) should have been borne and paid by the Developer, who should have kept D1 fully indemnified of any claim or enforcement action by BA (which contention I have rejected).

104.D1’s case  D1’s responses can be summarised as follows:

(a) The duties of D1 as an IO were governed by the BMO, and none of the duties set out in paragraph 101 above was found in the BMO, so there was no breach of any provision of the BMO and no breach of statutory duty on the part of D1.
(b) D1 denied it owed any fiduciary or common law agency duties to the Owners (including Ps) because as a matter of law D1 was not a fiduciary or agent of the Owners (including Ps).
(c) Even before the 1st Order, the Manager had managed the CCCs, and the Owners/occupiers for the time being of the Building (except the Developer) paid/contributed to the costs/expenses therefor in accordance with the provisions of the Subject DMC. Actually, the Manager had previously carried out repair /maintenance of the External Walls upon receiving complaint of water seepage, loose/defective tiles and fallen concrete, and the costs/expenses of such works were paid out of management expenses contributed to by the Owners/occupiers of the Building except the Developer.
(d) The Assignment was in the common interests of Ps and D1.
(e) Renovation works for the “Common Parts” (including the External Walls), the costs thereof, and the contributions to be collected from the Owners (including Ps) were discussed and resolved at the Owners’ meetings held on 25 April and 9 October 2009, 30 July 2011 and 6 October 2012.
(f) According to what was discussed/resolved at the Owners’ meeting held on 25 April 2009, the Owners by necessary implication had notice of and approved the Assignment, and D1’s MC in meeting held on 9 October 2009 resolved to acquire the “Common Parts” from the Developer.
(g) D1 denied any procedural irregularity, which in any event would not invalidate the OC’s, MC’s and Owners’ meetings.[54]

105.For the purpose of the Duty Issue, I assume (but without making any findings on law and/or facts at all) D1 owed the duties alleged in paragraph 101 above to Ps.

106.Witnesses  Mong Kwok Keung (director of the 6th plaintiff that bought Shop K in 2003, “Mong”) gave evidence for Ps. Tse Ka Ho (D1’s chairman at the time of trial who lived at the Building since 1994 and who owned a residential unit thereat since 2007, “Tse”), Kwong Yuen Cheung (owner/occupier of a residential unit of the Building from 1996 to 2011 and former chairman of D1, “Kwong”) and Chan Lap Yin (property manager of the Manager who was assigned to manage the Building from 2008 to 2012, “Chan”) gave evidence for D1. All witnesses adopted their respective statement evidence, and Kwong/Chan adopted parts of Tse’s statement evidence that were relevant to them.

107.Tse and Kwong gave statement/oral evidence to the effect that they suspected Ps’ motive in commencing the present action against D1 was to take revenge against D1’s/Manager’s demands and legal actions against various owners/occupiers of the shops on the ground floor of the Building for occupying the “Common Areas” and/or “Common Parts” to display their wares in breach of the Subject DMC. In light of my conclusion on the External Walls Issue, it was unnecessary for me to delve into Ps’ motives for the present action for the purpose of the Duty Issue.

108.Historical matters The Building was completed in mid-1980s. Tse said the Developer never enjoyed Exclusive Right over the CCCs, and all Owners/occupiers for the time being of the Building had common use and enjoyment thereof. Due to natural wear and tear of the CCCs (eg (a) deterioration of the physical condition of the passageways, lift lobbies, lighting system, transformer room and other facilities, (b) expiry of the validity period of fire services tanks/facilities, and (c) occurrence of cracks,[55] water seepage[56] and fallen concrete[57] at the External Walls).[58] Tse said and I accept the Manager arranged for cleaning, repair and maintenance of those parts of the External Walls in (c) above with corresponding costs/expenses paid from management fees contributed to by the Owners/occupiers for the time being of the Building (except the Developer). Even Mong “見到嗰個 …… 外牆啲位有啲地方係有啲崩缺位” and agreed general repairs (“一般嘅維修”) were carried out every now and then even though he personally had not seen/noticed repairs done to and/or scaffolding erected on the External Walls.

109.Tse explained that as the Building aged over the years, the physical condition of the CCCs deteriorated more rapidly, so repairs/maintenance (as needed) became more frequent, and loosened/ fallen concrete from the walls and ceilings (including the External Walls) exposed the steel bars and reinforced concrete structure underneath.

110.Tse said quite a few Owners felt these minor repairs/ maintenance failed to solve the more fundamental problems (eg cracks at the External Walls causing water seepage) and they feared loosened/ defective tiles and concrete falling off the External Walls might cause danger, so since 2003 there were requests for large scale renovation of the CCCs. In 2004, the Manager engaged a surveyor to ascertain what parts of the CCCs required large scale renovation and to submit a report. By its report, the surveyor proposed inter alia to replace the fresh water pipes, to repair/maintain the External Walls, and to carry out waterproofing work on the roof at an estimated cost of about $2,700,000.[59] Due to the cost involved, the Owners decided to first replace the fresh water pipes, and such works were completed in 2005, and the relevant cost and expenses were paid for as part of the management expenses contributed to by the Owners/ occupiers of the Building except the Developer. Mong had no impression of such survey and works on the fresh water pipes in 2004-2005.

111.Tse said quite a few Owners continued to request for large scale renovation of the Building (including the External Walls). In early 2007, the OC again discussed such matter, and the Manager proposed to ascertain the preliminary views of the Owners thereto by questionnaire survey.[60] The questionnaire was issued to the Owners, and the outcome was that most of the Owners who submitted responses supported a large scale renovation of the Building with contributions for expenses to be collected from the Owners over 36 months.[61] The OC asked the Manager to put forward 2 proposals for renovation of the External Walls, and to put such proposals to the Owners for consideration by way of questionnaire.[62] In 2008, the Manager issued such questionnaire with 2 proposals for renovation of the External Walls to the Owners for their views,[63] but Mong claimed the 6th plaintiff and some shop owners did not receive such questionnaire. The majority of the replies preferred partial rather than total repairs of the External Walls. The combined outcome of the 2 questionnaire surveys suggested the preferred option was to have partial repairs to the External Walls with collection of contributions from the Owners for such expenses over 36 months. The OC discussed such outcome and considered the way forward, including coming up with cost estimation for such renovation and arranging Owners’ meeting to discuss such matters.[64] On 17 March 2009, the Manager informed the OC in meeting that representatives from the Home Affairs Department (“HAD”) and Hong Kong Housing Society (“HKHS”) would be invited to attend the proposed Owners’ meeting to explain about formation of an IO and also about the Building Maintenance Assistance Scheme (“Scheme”).[65]

112.Before I turn to the various OC, MC and Owners’ meetings, I deal briefly with notice of such meetings/minutes. Mong confirmed that usually notice of meeting (with agenda) and minutes of meeting for Owners’ and OC’s/MC’s meetings would be posted on the notice board at the ground floor entrance hall of the Building, but the Manger would send the same by delivery/fax to the Owners of the shops on the ground floor. Tse said it was possible (but not necessarily so) that documents/information mentioned in the minutes of meeting would also be posted up at the notice board, but the OC/MC would provide copy to any resident who wished to read the same. Tse accepted that normally an Owner (who was not a member of the OC/MC) would learn about the topics for discussion at the aforesaid meetings from the agenda in the notice of meeting.

113.Mong said that since 2009 he started to pay attention to the affairs of the Building. BA issued the 1st Order on 31 March 2009. The OC convened an Owners’ meeting on 25 April 2009 attended by inter alia Tse, Mong and representatives from BA, HKHS and HAD. BA’s representative explained to the Owners the 1st Order was issued to the registered owner of the “Common Parts” to carry out the specified works on the “Common Parts” and External Walls.[66] HKHS’ representative gave explanation about the Scheme and application for subsidy thereunder for large scale renovation of common parts of the Building.[67] HAD’s representative gave explanation about the formation of an IO.[68] After discussion, the Owners passed resolution by majority vote to carry out large scale renovation of common parts of the Building including repairs to the External Walls, and to collect contributions of not more than $4,000,000 for such purpose from the Owners by 24 monthly instalments commencing from 1 July 2009.[69] Mong said there was no breakdown of the estimated cost for repairs solely for the External Walls. In my view, such complaint was immaterial since I have found the External Walls to be part of the common parts of the Building.

114.Tse said the Owners at such meeting knew the Developer was the registered owner of the “Common Parts”, and the 1st Order was addressed to the Developer. Some Owners asked who (ie the Developer or Owners) were legally responsible for the repair/maintenance of the Common Parts (including External Walls), and Tse said the solicitor engaged by the OC, ie 陳志華 (“Mr Chan”) of Cheung & Kwan, explained “(大意是)[Building’s]公用部份(包括外牆)屬於所有業主共同享有及使用, 因此保養維修責任屬於所有業主”. According to the minutes of such meeting, Mr Chan gave the following explanation (B/312):

“[Mr Chan]表示, 根據土地註冊處資料, [the Building]的公眾地方登記名屬一間私人公司所擁有。但依據終審庭的過案, 公契下的公眾地方是視乎實際的使用, 而實際受益人是業主, 所以泛指公眾地方的負責人都是眾業主負責。而業主未有收到維修命令是基於不同部門的法例所規管。[BA]是根據建築物條例第123章, 向業權人發出維修命令。但執行者是根據物業樓易及財產條例辦事, 而建築物管理條例第344章則按實際使用地方的受益人, 其次維修分攤費是根據公契([the Building]是以單位面積分攤維修費用)。”

115.Mong claimed the Owners at such meeting were anxious over who would be responsible for funding the renovation costs as there was concern the Owners would be responsible, but BA’s representative explained the 1st Order was issued to the legal owner, and repeatedly said it was for “Avante”, ie the Owner (according to the land search records and Subject DMC) of the common parts and External Walls, to deal with the 1st Order, so the Owners “起哄” and said the Developer should be responsible for the renovation costs for the External Walls (but the Developer did not send any representative to attend such meeting).

116.On balance, I do not accept Mong’s evidence that the Owners at such meeting had impression that the Developer should be responsible for the cost of renovating the External Walls. First, Mong complained that Mr Chan was only introduced as a solicitor, and the Owners did not know why he attended such meeting and who was his client. On balance I do not accept such complaint. The Developer did not attend such meeting. Other than representatives of BA, HKHS and HAD, there was just the OC and Manager. In my view, the Owners could not fail to appreciate Mr Chan was engaged by the OC and/or Manager.

117.Secondly, the minutes of meeting showed Mr Chan made clear that notwithstanding (a) the External Walls were privately owned and (b) the BA was statutorily required to issue the 1st Order to the registered owner, the owners having actual use and enjoyment of the common parts were responsible for the same, and under the BMO the owners had to make contributions according to the provisions of the Subject DMC. In my view, there was nothing unclear about such explanation which put the responsibility of cost of repairs to the common parts of the Building squarely on the Owners. Mong tried to shy away from this by saying Mr Chan only made a general observation (“一般情況, 好籠統, 好快咁樣就講咗”) that “在所謂「通常」的情況下[DMC]的[common parts]是視乎實際的使用, 而「通常」的情況下受益人是業主所以我們都要負責” with brief mention of a case authority and the Conveyancing and Property Ordinance Cap 219 but without specific advice as to the External Walls of the Building and the Subject DMC when the Developer was still the legal owner of the External Walls. But Mong’s account of Mr Chan’s explanation was similar to what was recorded in the minutes of meeting. Even if Mr Chan did not make any specific reference to the Subject DMC, he did not suggest the obligation to pay the cost of repairs for the External Walls amounted to any exception to the general position, and I do not believe the Owners thought differently. This explained why Mong said that after Mr Chan’s explanation, the Owners quietened down, “…… 佢話咁樣樣, 所以大家都冇再喺嗰度去討論喇, 已經基本上就係咁”.

118.Thirdly, in light of my conclusion on the External Walls Issue that the External Walls were common parts of the Building, Mr Chan’s advice was plainly correct and not in any way misleading or inadequate.

119.Mong confirmed when the resolutions in paragraphs 113 above were passed by the Owners they knew an essential part of the large scale renovation concerned the External Walls, and also knew contribution of $4,000,000 to be collected from the Owners were for renovation of the common parts including the External Walls (of which the Developer was still the legal owner). Mong said after Mr Chan’s explanation, “佢話係我哋嘅責任, …… 咁我哋咪唯有係履行番即係做一個小業主嘅責任囉”.

120.On 31 May 2009, the Manager issued a notice to inform the Owners of the amount of their respective contribution towards the costs of the large scale renovation of the common parts of the Building (B/594). At the Owners’ meeting held on 6 June 2009, the Owners passed resolutions by majority vote to incorporate an IO and to elect members of the MC (B/322-325). Kwong was elected chairman of the MC (and remained as such until 2011), and Tse was elected member of the MC. D1 was incorporated on 10 July 2009. Kwong said up until the execution of the Assignment, the MC considered it unnecessary to seek (and did not seek) further legal advice about liability for renovation costs in respect of the External Walls. I see nothing wrong about this as Mr Chan’s views as expressed at the Owners’ meeting held on 25 April 2009 were correct.

121.At a meeting of the 1st MC held on 6 August 2009, it was resolved D1 should apply to HKHS under the Scheme for financial subsidy to carry out large scale renovation of the common parts of the Building including the External Walls.[70] On/about 26 August 2009, D1 submitted such application to HKHS. The minutes of such meeting of D1’s MC noted the Manager reported that:[71]

“…… 另外, 早前[MC] 提出要求為公眾地方(業主為「Avante Company Limited」) 轉名予[D1] 名下。「新鴻基」對上述要求持開放及同意態度, 但要再詳細研究<大廈公契>之條文, 並了解[D1] 是否需要以象徵式收費取回大廈公眾部份。而上述轉名的律師費[the Manager] 陳先生表示需由大廈支付。稍後等了解<大廈公契>後, 面向[MC] 交代細節。”

122.The 3rd meeting of D1’s 1st MC was held on 9 October 2009. According to the notice of such meeting dated 30 September 2009 prepared by the Manager and signed by the secretary of the MC, the relevant agenda items included “商討大廈大維修事宜” and “其他事項”. Tse attended such meeting. He said certain member(s) of the MC noted (a) Mr Chan’s views at the Owners’ meeting held on 25 April 2009 and (b) the reality was that ever since completion of the construction of the Building the Owners were responsible for repair/maintenance of the CCCs even though the Developer was registered owner of the “Common Parts”, and suggested that for better management (including repair/maintenance) of the CCCs it would be preferable to transfer ownership of the Common Parts to D1. Tse said that after discussion the MC unanimously resolved to have the ownership of the “Common Parts” transferred to D1 as being in the common interests of all Owners (including Ps). Paragraph 5.1 of the minutes of such meeting (B/406) recorded as follows:

“…… [the Manager]陳先生表示, 需要[MC]通過有關跟進工作, 經各委員商討後一致贊成將大廈公共部份由大業主Avante Company Limited轉名予[D1]的名下。

[The Manager]陳先生表示, 轉名所需之有關法律費用需由[MC]負責, 有關費將於下次會議向各委員提交。”

Thereafter, the MC engaged solicitors to deal with the relevant legal procedures.

123.Mr Ng complained the discussions about the proposed Assignment at the MC’s 1st and 3rd meetings as documented in the minutes of meeting merely referred to the “Common Parts” and not to the External Walls specifically. This was a constant theme in Mr Ng’s cross-examination of Tse and Kwong in relation to a number of Owners’ and MC’s meetings. In my view, there was no merit in such complaint as I have found the External Walls were defined as part of the “Common Parts” and they were also common parts as defined in the BMO.

124.Mong complained the Owners trusted and relied on D1 in respect of “所謂集資計劃” and they paid to “[D1]聲稱的大維修款項”, but D1 kept them in the dark about the proposed Assignment. But Tse said the proposed Assignment was raised at the 3rd MC meeting as a follow-up from the 1st MC meeting even though it was not the agenda, “大家都有諗過, 想了解下嗰個--即係轉名嗰--嗰件事情嘅, …… 即係嗰個大廈嗰個公用部分轉番嚟法團名下嗰個跟進成點呀, 想了解清楚啲嘅, 本身都一致--有咁嘅諗法嘅, 都有”. Tse added that MC meetings were transparent as the MC welcomed owners to sit in their meetings to understand more about the affairs of the Building, and “可以當場嚟諮詢或者問 ……” and minutes of MC meetings were posted on the notice board.

125.In my view, there is nothing in Mong’s complaint of secrecy on the part of the MC over the Assignment. Given that D1/Owners had use, occupation and enjoyment of the “Common Parts” (including the External Walls despite certain rights given to the Developer under Clauses 8(b)-(c) and Clause 20 of Section V) and had obligation to repair and maintain the same under the DMC, and the Owners (except the Developer) were responsible for the costs and expenses in repairing/maintaining the “Common Parts”, ie D1/Owners had the benefit and burden of the “Common Parts” (including the External Walls), it made sense and in the common interest of the Owners (including Ps) to have the legal title of the “Common Parts” transferred to D1 for nominal consideration. In any event, the Assignment caused no loss to the Owners (including Ps) at all. In such circumstances, this could be appropriately handled by the MC (see section 29 of the BMO).

126.On 10 November 2009, HKHS wrote to D1 saying it would process D1’s application under the Scheme after it had acquired registered ownership of the “Common Parts”. Tse said this reinforced the MC’s belief that their resolution in paragraph 122 above was correct and in the common interest of all Owners, so they urged the solicitors to deal with the relevant legal procedures as soon as possible.[72] D1 executed the Assignment on 19 April 2010 (see paragraph 10 above). This was the first time Tse saw the Assignment. There was some complaint that the MC failed to keep themselves apprised of the progress of preparation of the Assignment by reviewing the solicitors’ correspondence and the draft assignment. However, this had no adverse consequence for the External Walls were part of the “Common Parts” and (and as explained above) it was in the common and best interests of the Owners (including Ps) to have the legal ownership of the same under its own name. On 28 October 2010, BA issued the 2nd Order to the IO.

127.At the annual general meeting of the IO held on 9 October 2010 (which Mong did not attend), the Owners were told HKHS’ subsidy might be about $576,000.[73] The Manager explained and the Owners passed resolutions by majority vote on the methodology for locating defective areas of the External Wall and on the appointment of consultant for the large scale renovation of the common parts of the Building.[74]

128.Mong complained D1 failed to disclose to the Owners at such annual general meeting that the IO had secretly entered into the Assignment a few months ago without notice to the Owners, and there was no explanation given to the Owners (including Ps) as the pros/cons of such Assignment of the “Common Parts” (including the External Walls), whether the Assignment was necessitated by the financial subsidy under the Scheme, and why the IO executed the Assignment without protective indemnity provisions when the External Walls were encumbered by the 1st Order which the Developer failed to comply with. Mong claimed Ps only discovered the Assignment in early 2013 when they inspected the minutes of MC’s meetings, and he alleged the Assignment “是不可接受的行為並明顯是疏忽和蓄意出賣業主的利益” as the IO/Owners were forced to comply with the 2nd Order and bear the cost of repairs/renovation of the External Walls. For reasons set out in paragraph 125 above, I reject such complaints. I have found that the Owners (and not the Developer) were in fact liable for the repair and renovation costs vis-à-vis the External Walls.

129.After completion of the tendering and selection process,[75] at the annual general meeting of the IO held on 30 July 2011, the Owners were told the total costs/expenses for the large scale renovation of the common parts of the Building (including the External Walls) would be about $5,600,000 instead of the previous estimation of $4,000,000, but taking into account HKHS’ financial subsidy of $576,000 further contribution of $1,000,000 would have collected from the Owners. A resolution was passed on majority vote that such $1,000,000 was to be collected from the Owners by 6 monthly instalments.[76] The consultant also reported to the Owners on the status and scope of works in relation to the common parts, and a resolution was passed on majority vote at such meeting to appoint the contractor for carrying such works.[77] Although Mong could not be sure whether he attended such annual general meeting, he knew of the resolution for collection of further contribution of $1,000,000 for the large scale renovation because he either attended such meeting or the 6th plaintiff paid its share of the further contribution of $1,000,000 by 6 instalments.

130.The large scale renovation works in relation to the common parts of the Building (including the External Walls) were eventually completed, and on 25 July 2012 the BA issued a certificate of compliance. At the annual general meeting of the IO held on 6 October 2012 (which Mong believed he did not attend), the Owners were informed the large scale renovation of the common parts of the Building had been completed, and the 2nd Order has been discharged.[78] The Owners passed a resolution by majority vote to defray the costs/expenses of such large scale renovation in the total sum of $5,445,400 from contribution payments by the Owners ($5,000,000) and by HKHS’ financial subsidy ($596,000).[79] Mong said he personally learnt of such costs/expenses about half year later or in 2013.

131.On/about 23 November 2012, HKHS granted a financial subsidy of $596,000 under the Scheme for D1 to carry out large scale renovation works of the CCCs including the External Walls. Tse said had D1 not entered into the Assignment, it would not have been able to obtain such financial subsidy, which meant the Owners (including Ps) would have to pay increased contributions for costs/expenses of such large scale renovation. In my view, this lent weight to the view that the Assignment was in the common interest of the parties.

132.Mong agreed that the minutes of the Owners’ meetings and OC’s/MC’s meetings from 2009 (when large scale renovation of inter alia the External Walls was first mentioned) to 2012 (when the specified works under the 2nd Order were completed) showed the OC/D1 had given information to the Owners “包括局部抑或全面維修外牆。二,分別涉及嘅費用。三,勘察外牆嘅方法。四,預計總額是多少。五,各業主應付數額。六,集資嘅時段” to let them choose whether to support or oppose the proposed resolutions.

133.Mong complained such voting would only be fair to the Owners/Ps had they been aware who owned and who was responsible for the External Walls, or had D1 secured for them proper legal advice on whether the Owners or particular Owner were/was responsible before they could make any informed decision whether to support or oppose the relevant resolutions. On balance I reject such argument. For reasons explained above, the Owners/Ps had sufficient notice, advice from Mr Chan and explanations from representatives of BA, HKHS and HAD before they voted to pass the resolution for carrying out renovation works for the common parts (including the External Walls).

134.Bearing in mind the Subject DMC and section 18(1)(a) of the BMO required the Owners (except the Developer) to repair/maintain the common parts including the External Walls, and section 18(2)(g) of the BMO enabled D1 in its discretion to act on behalf of the Owners in respect of any matter in which the Owners have a common interest, it must be in the Owners’ common interest to repair/maintain the CCCs including the External Walls in a state of good and serviceable repair and clean condition, and to acquire the “Common Parts” of the Building including the External Walls for the purposes of regularising legal ownership of the “Common Parts” of which the IO/Owners in any event had the benefit and burden and of making application and obtaining HKHS’ financial subsidy for the large scale renovation of the common parts of the Building including the External Walls. Given Mr Ng’s concession that any procedural irregularity in relation to the aforesaid meetings was not any standalone argument but premised on success on the External Walls Issue, any such procedural irregularity (which I do not accept) would not take Ps’ case any further.

135.In all the circumstances, I reject Ps’ contentions that D1/Manager wrongfully failed to carry out their duties in not demanding/ collecting payment contributions from the Developer relating to inter alia repair/maintenance of the External Walls.

IV.  RELIEF ISSUE

136.In light of my conclusions in the External Walls and Duty Issues, there is no need to deal with the Relief Issue.

V.  CONCLUSION

137.In the premises, Ps’ claim against D1 is dismissed. There is no reason why costs should not follow event. I grant a costs order nisi that Ps shall pay D1 costs of the action including all costs reserved if any on High Court scale to be taxed if not agreed.

  (Marlene Ng)
  Deputy High Court Judge

Mr Ernest Ng, instructed by Ng & Co, for the 1st, 2nd, 4th, 5th, 6th, 8th, 11th, 12th and 14th plaintiffs

Mr Allen Lam, instructed by S H Chan & Co, for the 1st defendant

Schedule



Section I “Common Areas” mean “all those areas of the Land and the Building which comprises
……
(j) All Flat-roofed areas in the Building (including the Flat-roofed area on the Main Rood and the Upper Roof);
(k) External Walls of the Building; and
(l) Those other parts of the Building the right to use of which is given and/or reserved by this Deed to more than one Owner.”
Section I “Common Parts” mean “Common Areas” (excluding all the Flat-roofed areas referred to in sub-paragraph (j) of the definition of Common Areas).
Section I “Common Parts Shares” mean “all those Shares allocated to the Common Parts as more particularly specified in the Second Schedule” (and in Second Schedule 20 undivided shares were allotted for “Common Parts”).
Section I “Owner(s)” mean “the person or persons in whom for the time being the legal estate in a Share is vested ……”
Section I “Share” means “an equal undivided share of and in the Land and Building”.
Section I “Unit” means “where the context permits or requires include Flat, Shop or self-contained portion of the building intended for separate use and occupation”.
Section II
Clause 1
The Registered Owner [ie Developer] and the Covenanting Owner [ie first purchaser] …… grant unto the Registered Owner and Covenanting Owner ……the full right and privilege to the exclusive use occupation and enjoyment and this rents and profits of the part of the Building and the Land set out in the Second Column of the Third Schedule hereto opposite to the respective names of the Owners set out in the Fist Column of the said Third Schedule TO THE INTENT that the Registered Owner and the Covenanting Owner hereto shall be entitled to the exclusive use occupation and enjoyment and the rents and profits of the part of the Building and the Land so set out opposite their respective names.
Third Schedule In respect of the “Registered Owner”, “All Those the Shops, Flats and self-contained portions and other portions (not otherwise intended to be used for the common enjoyment of the co-owners and co-occupiers for the time being of the Building) comprised in the Building other than those portions exclusively held used occupied and enjoyed by the Covenanting Owner as next hereinafter mentioned”
In respect of the “Covenanting Owner”, “All That Flat G on the 10th Flor of Glamour Garden (12/2, 320th shares)
Section II
Clause 8
there are reserved unto the Registered Owner its successors and assigns the following rights and privileges :-
……
(b) subject to all necessary approvals or consents of the appropriate Government authorities having been had and obtained the exclusive right to install in or affix to and use (or permit any person or corporation to install in or affix to and use) any part of the Building to which no Owner(s) has the exclusive right to occupy including the external walls such flues, pipes conduits, …… as the Registered Owner shall think fit, together with the right to repair, maintain, service, remove or replace the same;
(c) subject to the provisions of Special Condition No.(6)(1) of the Conditions and subject to all necessary approvals and consents of the appropriate Government authorities having been had and obtained the exclusive right to use or grant the right to use all the external walls parapet walls canopies of the Building or any part or parts thereof with the necessary right of support on any part of the flat roofs of the Ground Floor and the First Floor thereof and the Main Rood and Upper Rood for advertising purposes and to display, install, erect, affix or permit to be displayed, installed, erected or affixed thereon and thereto such advertising signs or structures whatsoever …… and with the right to remove, repair, maintain, service or replace the same provided that the same shall not necessarily interrupt the enjoyment of any unit in the Building.
(d) the right to assign all or any of the Common Parts together with the number of undivided shares relating to the Manager (or to an incorporated company whose principal business is that of estate management) for the general amenity of the Owners and other residents of the Building subject to this Indenture and subject to the Conditions.
……
Section III
Clause A
Subject to …… the Owner of each said undivided share shall have the benefit of the following easements rights and privileges:-
(a) Full right and liberty (in common with all other persons having the like right) to go pass and repass over and along and use the Common Areas and Common Facilities of the Building for all purposes connected with the proper use and enjoyment of his Unit.
……
Section IV
Clause 1
The Manager shall have full rights and privileges at all reasonable times upon giving reasonable advance notice (except in the case of emergency) …… to enter into and upon each Unit of the Building for the purpose of inspecting examining maintaining and repairing such Unit or the Building or any part or parts thereof (including cleaning of the Common Areas) or any Common Facilities therein or any other apparatus and equipment used or installed for the benefit of the Building or any part or parts thereof as part of the amenities thereof and not by an individual Owner for his own purpose of enjoyment. Provided that the Manager in exercise of this right and privilege shall act with all due expedition causing as little disturbance as possible and making good any damage caused thereby. The Manager shall indemnify and keep indemnified the Owners against all liabilities costs claims damages demands charges actions or proceedings of whatsoever nature arising out of or in connection with the negligent exercise of such right and privilege.
Section V
Clause 4
No Owner shall make any structural alterations or additions to any part of the Building owned by him which may damage or affect or interfere with the use and enjoyment of any other part or parts of the Building whether in separate or common occupation nor shall any Owner cut injure alter or interfere with any part or parts of the Common Areas ……
Section V
Clause 10
Each owner shall notwithstanding the obligations of the Manager to maintain the entire Building keep the part of the Building in respect or which he is entitled to exclusive possession in good repair and condition and shall for the purpose of clause 1(3) of Subsection B of Section VI maintain the same ……
Section V
Clause 13
No part of the Common Areas shall be obstructed or incumbered nor shall any articles boxed material refuse or any other matter or things be placed or left thereon nor shall any part of such Common Areas be used for any business or private purpose and no Owner will do or suffer or permit to be done anything in such Common Areas as may be or become a nuisance or cause annoyance to any other Owners or occupiers of the Building.
Section V
Clause 18
No external signs signboards notices advertisements flags banners poles cages brackets flower shelves or other projections or structures whatsoever extending outside the exterior of the Building shall be erected installed or otherwise affixed or projected from the Building or any part thereof without the prior written consent of the Manager and the Director of Lands and subject to Clause 19 immediately following no Owner shall erect affix install or attach or permit or suffer to be erected affixed installed or attached in or on the Building or to be displayed from any Unit any advertising or other sign or notice of any description without the prior written approval of the Manager and the Director of Land.
Section V
Clause 19
The Owners of the shops or commercial units on the Ground Floor of the Building shall subject to the prior approval in writing of the Director of Lands and the Manager and in accordance with and subject to such conditions provisions and restrictions as may be imposed by them or either of them be permitted to affix and install such signs or signboard on the exterior walls of their own shops Provided that such signs and signboard shall not in any way protrude above the level of the roof slab of the Ground Floor in height Provided further that the Owners installing such signs or signboard shall at all times observe and comply with all the laws and regulations relating to the erection and maintenance and dismantling of such signs or signboard and shall indemnify or keep indemnified the other Owners and occupiers for the time being against all loss and damage injury costs expenses claims and demands arising from or on account of or resulting from all the installation reparation maintenance and upkeep of such sign or signboards.
Section V
Clause 20
Notwithstanding anything to the contrary herein contained the Registered Owner its successors assigns or licensees of the exclusive right immediately hereinafter mentioned shall subject to the prior approval in writing of the Director of Lands and the Manager and in accordance with and subject to such conditions provisions and restrictions as may be imposed on them or either of them have the sole and exclusive right to erect install affix fit up exhibit or paint any signboards signs or advertisements …… on the external walls parapet walls of the Building and to install construct erect one or more flue pipes …… on such part or parts of the external walls at the rear or side or both the rear and side of the Building …… PROVIDED ALWAYS …… the Registered Owner its successors and assigns or licensees shall at all times observe and comply with all the laws and regulations relating to erection maintenance and dismantling of signs signboards advertisements or chimneys and shall be solely responsible for the repair maintenance upkeep renewal and removal of such signs signboards advertisements or chimneys and such portion(s) of the external walls parapet walls of the Building that  have been used by them Provided Further That the Registered Owner or its successors and assigns or licensees for the time being entitled to the said right will each in respect of their liability hereunder at all times indemnify and keep indemnified the other owners and occupiers for the time being of the Building against all loss damage injury costs expenses claims actions and demands arising from or on account of or resulting from the installation reparation renewal maintenance and upkeep of such signs sign-boards advertisements chimneys or resulting from the use of such portion(s) of the external walls parapet walls of the Building or from any defect therein or any failure to maintain the same in proper repair and condition.
Section V
Clause 29
No Owner shall cause any damage or interfere in any way with the Common Areas ……
Section VI
Clause B1
The Manager will manage the Building in a proper manner and in accordance with this Indenture and except as otherwise herein expressly provided the Manager shall be responsible for and shall have full and unrestricted authority to do all such acts and things as may in its opinion be necessary or requisite for the proper management of the Building. Without in any way limiting the generality of the foregoing the Manager shall have the following duties namely:
(1) To employ a qualified architect to inspect the entire Building (save only the interior of the Units) the Building Foundations the Common Areas and Common Facilities at such time as the Manager shall deem necessary and to prepare a report of such inspection ……
……
(4) To paint white-wash tile (or otherwise treat as may be appropriate) and put in hand any other necessary maintenance of the exterior wall and the Common Areas at such intervals as the same may in the opinion of the Manager be reasonably required to be done.
……
(15) To remove any structure installation signboard sunshade bracket fitting or other things in or on any part of the Building which have been erected in contravention of the terms of this Indenture or of the regulations of the Buildings Ordinance and/or without the prior written permission of the Manager (or if such permission has been given upon expiration or withdrawal of the same) ……
……
(18) To do all things which the Manager shall in his absolute discretion deem necessary or desirable for the purposes of maintaining and improving all facilities and services in or on the Building for the better enjoyment or use of the Building by its Owner occupiers and their licensees.
……

(20) To prevent any person from occupying or using the Common Areas otherwise than in accordance with the Conditions[80] and the provisions of this Indenture.
……
(26) To insure and keep insured the Common Areas and the Common Facilities and all parts thereof against loss or damage by fire and to effect public liability and/or occupiers’ liability and employees’ compensation liability in such items or in such amounts as the Manager may think fit such insurance to be in the name of the Manager itself for and on behalf of all the owners according to their respective interests ……
Section VI
Clause D1
Each Owner shall pay all costs expenses and outgoings incurred in such proportion as is hereinafter specified in relation to the management of the building …… whether the Manager be obliged hereunder to incur such expenditure or not and including but without limiting the generality of the foregoing the following items :-
……
(b) The cost of carrying out all or any of the duties of the Manager set out herein.
……
(f) The cost of effecting insurance in respect of or in connection with the management and the staff of the Building.
(g) All charges assessments impositions and other outgoings payable by the Owners in respect of all parts of the Common Areas.
……
(m) Any other items of expenditures charges premiums fees and other outgoings relating to the management, maintenance, operation, servicing, renewal, renovation or replacing of the Building (as the case may be) which are in the absolute discretion of the Manager necessary for good estate management of the Building.
Section VI
Clause D2
Each Owner shall upon the issue of the Occupation Permit of the Building is liable to pay or contribute towards the maintenance and management expenses of the Building as set out in the preceding Clause of this Subsection D in such proportion as shall be determined by reference to the saleable area of his Unit to the total saleable area of the Building (hereinafter referred to as “the saleable area basis”). The expression ‘the saleable area’ shall have the same meaning ascribed to it in the form of the Sale and Purchase Agreement approved by the Registrar General (land officer) for Units of the Building.


[1] defined as “Common Parts Shares” in Section I

[2] see minutes of the 5th meeting of the 7th OC held on 13 March 2007

[3] see Clause 8(c) of Section II

[4] see definition of “Common Areas” in Section I that comprised inter alia “External Walls of the Building” (see sub-paragraph (k))

[5] see definition of “Common Parts” in Section I being “Common Areas” that included inter alia the External Walls (see footnote 4 above) (but except all flat-roofed areas in the Building including the flat-roofed area on the Main Roof and Upper Roof)

[6] at the commencement of the present action there were other plaintiffs apart from Ps, and all such plaintiffs sued both D1 and D2

[7] “(1) Where a person who owns any part of a building, has the right to exclusive possession of any part of a building or has the exclusive right to the use, occupation or enjoyment of that part, as the case may be, but the deed of mutual covenant in respect of the building does not impose an obligation on that person to maintain the part in good repair and condition, that person shall maintain that part in good repair and condition. (2) The obligation in subsection (1) shall be deemed to be an obligation owed to all owners of the building under the deed of mutual covenant.”

[8] “(2) In the event of any inconsistency between [Part VIA of the BMO] and the terms of a deed of mutual covenant or any other agreement, this Part shall prevail.”

[9] eg flats and carparking spaces

[10] eg common areas which can be physically enjoyed such as gardens, yards, swimming pools and tennis courts, common parts or facilities which are not capable of physical use or occupation by individuals such as machine rooms, pump rooms, pipes and wiring ducts, and common routes of access which are set aside for the purpose of entry to and egress from the areas of exclusive use such as entrances and passageways, driveways, staircases and landings

[11] eg an area which is reserved for exclusive use may contain a structure which is a common part under the DMC or BMO

[12] see Clause 1 of Section II and Third Schedule

[13] see Clause A(a) of Section III

[14] except the Developer who did not have to contribute towards management expenses payable by reference to saleable area of the Unit

[15] [2010] 2 HKC 241, 244

[16] [2001] 1 HKLRD 463, 467-468

[17] see Jumbo King Ltd v Faithful Properties Ltd & ors (1999) 2 HKCFAR 279, 290

[18] being an instrument registered in the Land Registry

[19] see Lily Tse Lai Yin & ors v The Incorporated Owners of Albert House (also known as The Owner Incorporation of Albert House) HCPI828/1997, Suffiad J (unreported, 23 December 1999) para 40 (applied by DDJ Angela Kot (as she then was) in Green & Grace Ltd v Wang Lung Industrial Building (IO) [2015] 5 HKLRD 170, 183)

[20] see Merry, Building Management in Hong Kong 3rd ed (2016) paras 2.12-2.15 at p 18

[21] at p 296

[22] [2001] 1 HKLRD 463

[23] [2003] 1 HKLRD 455

[24] consequently, the developer (and first owner) did not have Exclusive Right over the “Common Parts” (which right was reserved to all co-owners of the building) to assign to the 1st defendant, and as it was a right that ran with the land it could only be enforced by or against co-owners who were either parties to the DMC or were bound by the DMC

[25] (2003) 6 HKCFAR 446

[26] LDBM34/2002, DDJ M Wong (as he then was) (unreported, 26 November 2002)

[27] [2004] 1 HKC 348

[28] LDBM339/2007, HHJ Wong (unreported, 11 February 2009)

[29] [2010] 2 HKC 241

[30] “the external walls of the said Building and of any part of the Building in common use ……”

[31] [2009] 4 HKLRD 692

[32] [2010] 4 HKC 463

[33] HCSA7-13/2015, Chow J (unreported, 18 September 2015)

[34] [1999] 4 HKC 141

[35] [2015] 5 HKLRD 170

[36] HCPI828/1997, Suffiad J (unreported, 23 December 1999)

[37] such provision did not provide an exhaustive list of the common parts since the word “includes” was used, and if there was ambiguity and uncertainty in the deed of mutual covenant, one could resort to the definition in the BMO (at p 178)

[38] such clauses prohibited specified actions involving the external or exterior of the building (that included the external walls) except with prior permission, prior consent in writing or prior written approval by the manager, but such prohibition was expressly “[subject] to the provisions of cl.7 of Section I”

[39] such clause gave the manager a duty to paint, white-wash, tile or otherwise treat as might be appropriate the exterior walls of the building and common area at such intervals as the same might reasonably be required to be done

[40] eg clause 16 of section IV did not touch on the external walls of the building

[41] eg the developer did not require the consent of the manager in doing anything stipulated in clauses 17-18 and 25 of section IV of the DMC

[42] sub-paragraph (j) in the definition of “Common Areas” was excluded in the definition of the “Common Parts”

[43] see observations by Hoffmann NPJ in Jumbo King Ltd at p 296 (see paragraph 28 above) and by Chow J in paragraph 21 in Yan Yan Motors Ltd (see paragraph 44 above)

[44] see discussion on Clauses 8(b)-(c) below but suffice to state here this view is not affected by such discussion

[45] Clause D2 of Section VI provided that management fees payable by each Owner shall be determined by reference “to the saleable area of his Unit to the total saleable area of the Building”, but (a) the External Walls were not any Unit(s), and (b) there could not be any saleable area ascribed for the “Common Areas”, “Common Parts” and/or External Walls in the Sale and Purchase Agreement approved by the Registrar General (Land Officer) “for Units of the Building”

[46] ignoring just for present purpose “[subject] to all necessary approvals or consents of the appropriate Government authorities having been had and obtained”

[47] as they must be so read as explained by Lord Hoffmann NPJ in Jumbo King Ltd (see paragraph 28 above) and by Chow J in Yan Yan Motors Ltd (see paragraph 44 above)

[48] ie the Developer by Clause 3(b) reserved Exclusive Right to the External Walls such that it was solely responsible to repair/maintain the External Walls and to bear the costs/expenses therefor

[49] eg the lift lobbies and staircase/passage on each floor from the ground floor to the 35th floor being sub-paragraphs (e)-(f) of the definition of “Common Areas” in Section I being obvious common parts of the Building in respect of which no Owner had any Exclusive Right

[50] see similar provision in the DMC in Incorporated Owners of Shatin New Town which Cheung JA took into account in coming to similar conclusion (see paragraph 40 above)

[51] Ps claimed D1 was under a statutory duty to act in the common interest of the Owners (including Ps) and to protect their best interest pursuant to inter alia sections 18(1)-(2) of the BMO with a further duty of adequate disclosure

[52] Ps claimed that vis-à-vis the Owners (including Ps) D1 was a fiduciary generally and also specifically in respect of the renovation works for the External Walls and the Assignment to act in the best interest of the Owners (including Ps)

[53] Ps claimed D1 was an agent vis-à-vis the Owners (including Ps) in respect of the renovation works for the External Walls and the Assignment, and owed common law duties to act with reasonable care and skill

[54] Mr Ng made clear the complaint of procedural irregularity was not a standalone contention but was subject to the External Walls Issue and the court’s findings as to the nature/extent of the duties (if any) D1 owed to Ps – see paragraph 17(e) above

[55] see paragraph 3.1 of the minutes of the 5th meeting of the 7th OC held on 13 March 2007 (B4/366)

[56] see paragraph 5.9 of the minutes of the 2nd meeting of the 1st MC held on 4 September 2009 (B4/400)

[57] see paragraph 3.1 of the minutes of the 5th meeting of the 7th OC held on 13 March 2007 (B4/366)

[58] Tse said “沙磚牆身防水批盪工程” was carried out on the external “沙磚牆身” outside the toilet with pipes affixed thereto

[59] see paragraph 3.1 of the minutes of the 5th meeting of the 7th OC held on 13 March 2007 (B4/366)

[60] see paragraph 3.1 of the minutes of the 6th meeting of the 7th OC held on 5June 2007 (B4/369)

[61] see paragraph 4 of the minutes of the 7th meeting of the 7th OC held on 13 September 2007 (B4/373)

[62] see paragraph 4.2 of the minutes of the 7th meeting of the 7th OC held on 13 September 2007 (B4/373)

[63] see paragraph 2 of the minutes of the 8th meeting of the 7th OC held on 20 December 2007 (B4/375-376) and paragraph 2.1 of the minutes of the 9th meeting of the 7th OC held on 8 April 2008 (B4/378) and form of questionnaire at B/251-254

[64] see paragraph 2 of the minutes of the 9th meeting of the 7th OC held on 8 April 2008 (B4/378-379) and paragraph 3 of the minutes of the 11th meeting of the 7th OC held on 9 January 2009 (B4/382)

[65] see paragraph 4 of the minutes of the 12th meeting of the 7th OC held on 17 March 2009 (B4/386)

[66] see paragraph 1.1 of the minutes of the Owners’ meeting dated 25 April 2009 (B/311-312)

[67] see paragraph 1.2 of the minutes of the Owners’ meeting dated 25 April 2009 (B/315)

[68] see paragraph 1.2 of the minutes of the Owners’ meeting dated 25 April 2009 (B/315)

[69] see paragraphs 2-4 of the minutes of the Owners’ meeting dated 25 April 2009 (B/316-319)

[70] see paragraph 1 of the minutes of the 1st meeting of the 1st MC held on 6 August 2009 (B/389)

[71] see paragraph 8.1.14 of the minutes of the 1st meeting of the 1st MC held on 6 August 2009 (B/392-393)

[72] see paragraph 6 of the minutes of the 4th meeting of the 1st MC held on 20 November 2009 (B/413), paragraph 1.4 of the minutes of the 5th meeting of the 1st MC held on 18 December 2009 (B/418), paragraph 4 of the minutes of the 6th meeting of the 1st MC held on 29 January 2010 (B/427), paragraph 4.1 of the minutes of the 7th meeting of the 1st MC held on 12 March 2010 (B/433), and paragraph 3 of the minutes of the 8th meeting of the 1st MC held on 16 April 2010 (B/442)

[73] see paragraph 1.6 of the annual general meeting of the IO held on 9 October 2010 (B/327)

[74] see paragraphs 2-3 of the annual general meeting of the IO held on 9 October 2010 (B/328-330)

[75] see paragraph 3 of the minutes of the 9th meeting of the 1st MC held on 28 May 2010 (B/448), paragraph 4 of the minutes of the 10th meeting of the 1st MC held on 25 June 2010 (B/453-454), paragraph 3 of the minutes of the 11th meeting of the 1st MC held on 6 August 2010 (B/458), minutes of special meeting of the 1st MC held on 19 August 2010 (B/461-464), paragraphs 1 and 3 of the minutes of the 12th meeting of the 1st MC held on 17 September 2010 (B/466-467), paragraph 3 of the minutes of the 13th meeting of the 1st MC held on 5 November 2010 (B/471), paragraphs 2 and 7.1 of the minutes of the 14th meeting of the 1st MC held on 10 December 2010 (B/475-476), see paragraph 2 of the minutes of the 15th meeting of the 1st MC held on 14 January 2011 (B/479-481), see paragraphs 2-3 of the minutes of the 16th meeting of the 1st MC held on 25 February 2011 (B/484-485), paragraphs 2-3 of the minutes of the 17th meeting of the 1st MC held on 11 March 2011 (B/488-489), paragraphs 2-3 of the minutes of the 18th meeting of the 1st MC held on 15 April 2011 (B/493), paragraphs 2 and 5 of the minutes of the 19th meeting of the 1st MC held on 22 June 2011 (B/497-499), and paragraphs 2-3 and 6 of the minutes of the 20th meeting of the 1st MC held on 15 July 2011 (B/502-503)

[76] see paragraph 5 of minutes of annual general meeting of the IO held on 30 July 2011 (B/348)

[77] see paragraph 6 of minutes of annual general meeting of the IO held on 30 July 2011 (B/348-352)

[78] see paragraph 1.1 of the minutes of the annual general meeting of the IO held on 6 October 2012 (B/357)

[79] see paragraph 3 of the minutes of the annual general meeting of the IO held on 6 October 2012 (B/359)

[80] “Conditions” was defined in section I of the DMC as “the Particulars and Conditions” of the New Grant, and SC6(1) provided that “The Grantee [ie Gladforce Limited and its assigns, ie the Developer] shall not display any advertisement, signs or notices in or on the building or buildings to be erected on the lot without first obtaining the prior written consent of the Director and then only in accordance with and subject to such conditions provision and restrictions as may be imposed by him”