Lingnan University (Formerly Known As Lingnan College) v. Alan Chung Wah Tang and Another
Read the full judgment text of HCCW 614/1997 on BabelCite. This High Court CFI judgment was delivered on 8 November 2019.
1. This is the application of Lingnan University (formerly known as Lingnan College) (the “Applicant”), by a summons dated 22 July 2016 (the “Summons”) for the following orders:
Cited by 1 case · Cites 6 cases
|
HCCW 614/1997 [2019] HKCFI 2749 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE COMPANIES (WINDING-UP) PROCEEDINGS NO 614 OF 1997 ______________
______________
______________ Before: Deputy High Court Judge William Wong SC in Chambers Date of Hearing: 17 October 2019 Date of Decision: 8 November 2019 ________________________ DECISION ________________________ 1.This is the application of Lingnan University (formerly known as Lingnan College) (the “Applicant”), by a summons dated 22 July 2016 (the “Summons”) for the following orders:
2.In Mr Ng’s Skeleton Submissions, the amount to be admitted is revised to HK$9,194,047.44. The sum claimed by the Applicant is based on the revised final contract sum and the actual cost of rectification. The details are as follows:
The applicable legal principles 3.It is well established that an application to the court under Rule 95 of the Companies (Winding-up) Rules is by way of a hearing de novo to determine the extent to which the applicant should be allowed to rank as a proving creditor. The court is bound to decide the rights of the applicant in the light of all the evidence before it, and not merely to express a view as to whether the liquidators were right or wrong in rejecting the proof on the evidence available to the liquidators at the time. 4.The onus is on the applicant to show on balance of probabilities that a real debt was due to him. In Trustee in Bankruptcy of Lo Siu Fai Louis v Toohey [2005] 4 HKC 51, Cheung JA at §§10 – 12 said:
Background 5.The Applicant, qua employer entered into a main contract (the “Contract”) with Wan Hin and Company Limited (the “Company”) as the main contractor based on the 1986 RICS standard form, for the construction of the Applicant’s new campus at Tuen Mun (the “Project”) on 13 April 1994. The contract sum was HK$400,600,000. 6.The architect was P&T Architects and Engineers Limited (“P&T”) and the quantity surveyor was Levett and Bailey Chartered Quantity Surveyors (“L&B”). 7.According to the Contract, the completion date of the Project should be 21 June 1995. However, due to delays by the Company, the Project was only completed, in sections, from 13 August 1995 to 9 September 1996. 8.On 21 July 1997, L&B sent a draft final account to the Company for agreement. 9.It is pertinent to note that after taking into account the extension of time (“EOT”) to the original completion date granted by P&T (ie 88 days up to 17 September 1995), L&B assessed that the amount of the liquidated damages (“LD”) should be HK$17,752,992. 10.P&T, the architect issued its Payment Certificate No 29 on 21 January 1998 which also certified the LD to HK$17,752,992. 11.On 30 March 1998, the Company was wound up by the court and the Respondents were appointed as Joint and Several Liquidators of the Company. Analysis 12.Having gone through the contemporaneous documents and heard the parties’ submissions, I am of the view that the Applicant has discharged the relevant burden of proof. Its debt in the sum of HK$9,194,047.44 should be admitted. 13.First, in terms of contemporaneous documents, on 15 June 1998,L&B issued a revised final account. In the revised final account, the amount of the LD was stated as HK$17,752,992 after taking into consideration of 88 days of EOT granted. 14.In the Valuation of Work No 29 issued by P&T, the architect,it was also certified that:
15.Appendix A then comprehensively sets out the detailed calculation of the LD. 16.Further, in P&T’s Payment Certificate dated 20 January 1998,it is recorded that the LD is HK$17,752,992 and the total retention money is HK$9,229,500. 17.In a letter issued by L&B on 5 September 1998, it is recorded that:
18.On 27 July 1998, the project manager, Crow Maunsell Management Consultants Ltd (“CMMC”) stated that they have no adverse comment to the revised draft. 19.On 28 July 1998, P&T, the architect, stated that:
20.On 14 October 1998, L&B stated that:
21.Mr Ng for the Applicant also pointed out to this Court that in fact, in a letter dated 10 February 1999, Mr Alan Tang, one of the Joint and Several Liquidators, had in fact agreed on the final contract sum (subject to the exclusion of contra charges in the amount of HK$2,360,221.74). 22.In view of the above contemporaneous documents, I agree with Mr Ng for the Applicant that all the professionals who had first hand and personal knowledge of the Project have confirmed the amount of the LD owed to the Applicant. They had discussed with the Company’s employees and claim consultants before they concluded the final account and their assessment of the LD. 23.In SGL Carbon Fibres Ltd v RBG Ltd [2012] CSOH 19 at §24,Lord Glennie said:
24.Mr Chu for the Joint and Several Liquidators first submitted that there is no final certificate issued by P&T, the architect, to certify the amount due to the Applicant. This is in fact the Joint and Several Liquidators’ main submission. However, I am of the view that this is neither here nor there. Mr Chu in fact correctly stated that even if there is a judgment, the Joint and Several Liquidators are entitled to look behind the judgment to assess whether a debt is legitimately due or not. A final architect certificate will certainly help the Applicant’s case. Nonetheless,the duty of the Court is to assess all the evidence available before it in order to determine, on a balance of probabilities, whether the Applicant should be allowed to rank as a proving creditor. 25.Further, Mr Chan of L&B confirmed on oath that the reason why no final certificate was issued was that after the winding up of the Company, “the liquidators of the Company did not confirm the acceptance of the revised final account and the matter was left hanging in the air.” (See §9 of the Affirmation of Chan Choi Hing.) 26.In any event, Mr Chan, the director of L&B at the relevant time, formally signed the final account and confirmed on oath that L&B was at all material times satisfied with the truth and accuracy of the revised final account. 27.Secondly, Mr Chu for the Joint and Several Liquidators submitted that there was late delivery of area C which caused delay in the completion of the Project, hence the Applicant is not entitled to claim the LD against the Company. In view of the evidence, I am of the view that there are no merits in such argument:
28.Thirdly, in relation to the allegation that as result of the Applicant’s exercise of its right to take sectional completion, the Company and its sub-contractors were disrupted in their access to parts of the Project’s building, thus making it impossible to complete the contract work on time, I am of the view that there is no substance in such complaint:
29.Fourthly, it was argued that the partial occupation of the Project’s building together with the issue of the Occupation Permit/ Temporary Permit constitutes substantial completion of the Project. As such, the Applicant is not eligible to apply for the LD for the period after the initial occupation date. I disagree:
30.Fifthly, Mr Chu for the Joint and Several Liquidators submitted that the rectification works were incurred outside the 12 months defects and liabilities period and some of the items were not related to rectification works but were mere maintenance works. Mr Chu subsequently agreed that as no final certificate was issued, the time period to rectify defects is at large. 31.Mr Ng for the Applicant submitted that the contractual provisions governing the time period to rectify defects cannot operate as exemption clauses on the Company’s liability to rectify defects after the expire of 12 months. I agree. 32.I also note that in a letter dated 31 December 1997 from P&T, the architect, it is recorded that:
33.As to the quantum, I am satisfied that the Applicant’s claim is supported by:
34.Sixthly, as far as the quantum of retention money is concerned,I am satisfied that the sum of HK$2,000,500 was related to nominated subcontractors and suppliers as shown in P&T’s Payment Certificate dated 20 January 1998. 35.Finally, I agree with Mr Ng for the Applicant that the report by Jean Peter Ho is inadmissible for want of an expert declaration as required by Order 38, rule 37C of the Rules of the High Court. (See Joint & Several Liquidators of China Medical Technologies Inc v KPMG HCCW 435/2012, unreported, 24 February 2016; related appeal dismissed: [2017] 2 HKLRD 1091), at §§52 – 53; cf Re Loong San Investment Co Ltd [2014] 2 HKLRD 1116, at §§11 – 14 per A Chan J.) 36.I am also of the view that the report by Messrs George Berry & Partners prepared in September 1999 is of little probative value because they were instructed to give advice to the Respondents as to how to maximize the Company’s returns from potential recoveries. Crucially, there is no detailed analysis of the Applicant’s claims in the said report. Disposition 37.For all the reasons stated above, I make an order that:
38.I also make an order that costs are to be paid out of the assets of the Company and the Applicant’s costs should be paid in priority to those of the liquidators’ costs. (See Re Tsz Wan Shan Ltd[2010] 4 HKLRD 291 at §8.) 39.Finally, it remains for me to thank Mr Ng for the Applicant and Mr Chu for the Joint and Several Liquidators for their helpful assistance to this Court.
Mr Tom Ng, instructed by Mayer Brown, for the applicant Mr George Chu, instructed by Damien Shea & Co, for the respondents | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCCW 614/1997