Mtr Corporation Ltd v. Ocean System Ltd and Another
Read the full judgment text of HCMP 2140/2024 on BabelCite. This High Court CFI judgment was delivered on 24 April 2026.
1. This is a decision in relation to the costs of an originating summons issued by the plaintiff (“MTRC”) dated 24 October 2024 (“the OS”) against the 1 st defendant (“Ocean System”) and the 2 nd defendant (“Ip Kwan”, the 1 st and 2 nd defendants collectively referred to as “Ds”). It is also in relation to the costs of the inter-parte summons for speedy trial taken out by MTRC on 25 October 2024 for the determination of the issues stated under the OS (“the Summons”).
Cited by 1 case · Cites 16 cases
|
HCMP 2140/2024 [2026] HKCFI 2244 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF FIRST INSTANCE MISCELLANEOUS PROCEEDINGS NO. 2140 OF 2024 ________________________ BETWEEN
________________________
________________________ DECISION ________________________ A. INTRODUCTION 1.This is a decision in relation to the costs of an originating summons issued by the plaintiff (“MTRC”) dated 24 October 2024 (“the OS”) against the 1st defendant (“Ocean System”) and the 2nd defendant (“Ip Kwan”, the 1st and 2nd defendants collectively referred to as “Ds”). It is also in relation to the costs of the inter-parte summons for speedy trial taken out by MTRC on 25 October 2024 for the determination of the issues stated under the OS (“the Summons”). 2.On 1 November 2024, the parties appeared before me for the hearing of the OS and the Summons (“the Hearing”) where counsel for MTRC (Mr Albert Chan) and senior counsel for Ds (Mr Neville Sarony SC) agreed to have the matters resolved in a practical manner after the court had expressed its strong views on how the applications should be dealt with. This resulted in the order made by the court on the same day, based on the directions agreed by the parties’ counsel after they had the chance to discuss the matters amongst them during a short adjournment allowed by the court at the Hearing (“the Order”). The costs for the OS and the Summons, as well as the costs for the Hearing, was reserved under the Order. 3.Pursuant to an order dated 28 February 2025, by consent, a direction hearing was to be fixed for the parties to argue on the issue of costs of the OS and the Summons (“the Costs Issue”). By an order dated 9 June 2025, the court directed that an oral hearing on the Costs Issue should take place before me. 4.The hearing for the Costs Issue took place before me on 23 July 2025 whereby MTRC was represented by Ms Audrey Eu, SC leading Mr Albert Chan, while Ds were represented by Mr William Wong SC leading Mr Martin Lau and Mr Victor Lui. B. BACKGROUND 5.MTRC is the manager of Admiralty Centre. Ocean System is the owner of the office units situated at Units 608-609, Tower 1, Admiralty Centre, 18 Harcourt Road, Hong Kong (“the Office”) and Ip Kwan are its tenants. 6.MTRC, through the letters of MTRC’s solicitors, Messrs. Lo & Lo (“LL”), has since August 2024, requested access to the Office for the inspection, repair, and/or maintenance of Fire Damper (“FD”) Nos 1-4. These FDs are only accessible from inside the Office. By their letters dated 13 August 2024, 14 August 2024, 24 September 2024 and 4 October 2024, LL has made at least 4 requests for entry. 7.On 30 September 2024, the Fire Service Department (“FSD”) issued the Fire Hazard Abatement Notice (“the FSD Notice”) requiring FD2 to be repaired and/or maintained by 29 November 2024 (“the FSD Deadline”), failing which all co-owners of Tower I would be liable to prosecution. 8.MTRC claims that while Ds clearly recognized the urgency and seriousness of the situation, they nevertheless refused LL’s requests, despite MTRC’s repeated assurance[1] that Ds were welcome to take any measures considered necessary and appropriate to record the status of the FDs and/or witness the process of the inspection, repair and/or maintenance. By their letter dated 4 October 2024, Ds effectively cut off any discussion by stating: “We are not to engage into further correspondence with you, which are only to generate costs. If [MTRC] considers justified to take any other course of action, please proceed”. In light of the FSD Deadline and Ds’ attitude, MTRC says it had no option but to issue the OS and the Summons on 24 and 25 October 2024 respectively for speedy entry and necessary works. 9.As said, the matter came before this court on 1 November 2024 and directions were given under the Order at the Hearing. The Order facilitated the subsequent inspection, repairs, and/or maintenance of the FDs (which led to the discovery of FD5 adjacent to FD1). The FSD Notice was complied with in time, and all works were completed by 11 February 2025. As such, MTRC says the purpose of both the OS and the Summons has been achieved. It is therefore no longer necessary for MTRC to seek any relief. In the circumstances, MTRC seeks leave to formally discontinue and/or withdraw the OS and the Summons as part of the Costs Issue. 10.On the other hand, Ds say that the OS is a “satellite litigation” brought by MTRC. Ds submit that it should be viewed against the wider context where an ongoing action between the parties in HCA 1283/2023 (“the HCA Action”) was on foot. In short, Ds say that:-
MTRC’s Primary Submissions 11.Ms Eu SC submits on behalf of MTRC that Ds ought to pay MTRC for the costs of (1) these proceedings (including all reserved costs); and (2) the Summons, on an indemnity basis for the following reasons:-
Ds’ Primary Submissions 12.Mr Wong SC on the other hand submits on behalf of Ds that:-
13.For the reasons stated in Ds’ written submissions which were expanded in his oral submissions at the hearing before me, he says that MTRC should pay Ds’ costs of and occasioned by the OS, including but not limited to the Summons, the Hearing and all costs reserved.[2] C. DISCUSSION The HCA Action 14.There is no dispute that a fire happened at the Office in 2018 which had caused severe damage to it. It necessitated large-scale renovations. Ds allege the Office was also disturbed by smell generated by the operation and activities performed in the plant room after the fire. Ds further allege that since 2018, the Office has been suffering from nuisance of various forms. They claim that the situation worsened in 2022 when the Office was attacked by sudden and loud “bong” noises for multiple times daily. 15.In May 2023, Ip Kwan engaged an acoustic and heating, ventilation and air-conditioning (“HVAC”) expert. The expert advised that the cause of the noises could be “due to the automatic opening or closing of the dampers/values installed for the ductworks and/or pipeworks”. The expert also explained that Regulations 5 and 5A of Building (Ventilating Systems) Regulations (Cap. 123J) required every FD to be inspected and certified annually to ensure safe and efficient working order. It is claimed that Ds then became aware of the issues concerning the maintenance and inspection of the FDs. 16.Ds’ complaints were disputed by MTRC, including the noise nuisance. 17.Ds then commenced the HCA Action on 14 August 2023 against MTRC as 1st defendant and its contractor responsible for the ventilation and air-condition system of Admiralty Centre, namely, The Jardine Engineering Corporation, Limited (“Jardine”) as 2nd defendant in that case. Part of Ds’ claim against MTRC and Jardine concerns the failure to inspect and manage the FDs. Both MTRC and Jardine deny liability. 18.The HCA Action remains pending and discovery has not been completed yet. The Issues in Dispute under the OS 19.While the HCA Action provides a useful background to the dispute between the parties under the present proceedings, I note that it does not involve the same issues as what MTRC had asked the court to resolve under the OS and the Summons. Hence, one must not conflate the issues raised by Ds in the HCA Action and those raised by MTRC under the OS. In my view, they involve very different issues. They also involve different parties as Jardine is not a party to the OS. Events leading to the issue of the OS 20.It is not disputed by the parties that the inspection of the FDs was as a result of an inspection carried out by the FSD officers at the Office of Ip Kwan on 7 August 2024. On that occasion, two FSD officers attended the Office and performed inspection of the 4 FDs according to the layout plan provided to them by Ms Corrina Kwan (“Ms Kwan”) of Ip Kwan: see §§57 and 58 of Ms Kwan’s affirmation filed on 21 March 2025 (“KLYC 1st”). 21.It is also not disputed on that occasion neither MTRC nor Jardine’s representatives were present as they were not invited to nor notified of the FSD’s inspection. It was arranged by Ip Kwan without the knowledge of MTRC: see §29 of affirmation of Chau Wing Kit filed on 25 October 2024 on behalf of MTRC (“CWK 1st”). 22.Following the FSD’s inspection on 7 August 2024, MTRC was orally informed by the officers on site of the following matters:-
23.On 13 August 2024, MTRC through its solicitors LL wrote to Ip Kwan requested Ds to grant access to the Office so that an inspection of FDs 1, 3 and 4 could be arranged on 15 or 16 August 2024. If those 2 dates were not convenient, Ds were invited to propose other alternative dates. To facilitate the proposed inspection, LL included a 9-page method statement prepared by Jardine (“the August Method Statement”) to inform Ds of the nature, procedure, and duration of the works to be performed. 24.As regards the repair of FD2, LL informed Ds that the FSD required maintenance work to be carried out as soon as possible, and in any event within 60 days; and invited Ds to confirm when would be the best time for such repairs to be carried out by MTRC’s contractor. 25.This was the first time MTRC asked for an inspection of the Office in relation to the FSD Notice. 26.It should be noted here that the above letter of LL dated 13 August 2024 (as in all their subsequent correspondence on the subject matter) was written under the caption of “Fire Damper Inspection Admiralty Centre”. This is in contrast to Ip Kwan’s reply letter on 13 August 2024 (and in all their subsequent correspondence on the subject matter) which was written under the caption of “Re: HCA 1283 of 2023”. This marked a fundamental difference of how the parties viewed the FSD Notice issued by the FSD and the inspection and repair of the FDs. 27.In a highly emotional reply letter dated 13 August 2024, Ip Kwan pointed out what they considered as the “false” contents of LL’s letter. A lot of serious accusations have been made against MTRC regarding its conduct under that letter. In particular, Ip Kwan accused MTRC of fabricating the suggestion that FD 1&3 were blocked by Ds’ false ceiling or decorative structures, and also acting dishonestly, wilfully, and with an intention to mislead Ds into believing that the fault was on them. Further, Ip Kwan dismissed the August Method Statement “is not the information requested by us” and the “irrelevant material” would cost them time and costs in reading them. They were also unable to see how it would assist them to “understand and plan for the inspection and make precaution and measurements to address the interferences caused to our operation.” They asked MTRC to contact Ms Kwan immediately to discuss “the issues involved and the logistics for the carrying out of the inspection”. 28.In a letter dated 14 August 2024 in reply to the above letter, LL suggested “it may be useful for the purpose of planning the inspection and repair work if [MTRC] and [Jardine]’s representatives can attend [the Office] to briefly review the 4 fire dampers.” They suggested this preliminary inspection should take approximately 30 minutes only. This was MTRC’s second request for an inspection. 29.In a lengthy reply to the above letter of LL, Ip Kwan in their letter dated 14 August 2024 started by stating “we do not understand ‘what contents’ in our letter which justifies an inspection of the fire dampers for 30 minutes inside the office”. After a lengthy complaint of the conduct of MTRC and Jardine since the fire in 2018, the letter ended with “[W]e await the opportunity to discuss the issues in relation to the requested inspection of the fire dumpsters.” but without making any concrete proposal as to when MTRC could enter the Office for the purpose of carrying our either the preliminary inspection and/or the inspection and repair itself. 30.On 26 August 2024, LL wrote to Ip Kwan and explained the reason why MTRC considered a brief review of the 4 FDs in order to assess the situation and draw up an inspection and repair work procedures (or method statement) suitable to the situation of the Office. LL stated clearly that it would be difficult for MTRC to discuss the logistics of the inspection and repair work if they are unable to conduct the requested preliminary visit. LL made it clear in their letter that the inspection of the FDs was necessary regardless of the HCA Action. If preservation of evidence was their concern, LL suggested that the parties could take photographs of the relevant FDs and their surrounding areas as appropriate before carrying out any inspection and/or repair work. 31.In another lengthy reply to the above letter of LL on the same day, ie 26 August 2024, Ip Kwan stated, inter alia, the following:-
32.Ip Kwan also stated that the issues could not simply to resolve by taking of pictures. The examination of the FDs and the subsequent repair involved technical special knowledge and skills. Ds maintained that they needed to be assisted by specialists throughout. They said that these costs need to be incurred solely because of the current condition of the FDs which were MTRC’s responsibility. They also said there were other issues which need to be resolved and requested the person in charge of the matter at MTRC or the handling solicitor at LL should immediately approach Ms Kwan for discussion and sorting out the issues. 33.In any event, no consent has been given by Ip Kwan to allow MTRC to carry out the preliminary inspection and/or the inspection and repair needed in order to comply the FSD Notice. 34.Further correspondence had been exchanged between Ip Kwan and LL from 26 August to 10 September 2024 but they were in relation to the discovery of the Section 5A Certificates under the HCA Action and not about the FD inspection. 35.In reply to Ip Kwan’s letter dated 26 August 2024, LL wrote in a short letter dated 10 September 2024 summing up the position of MTRC as follows:-
36.From the above letter, what MTRC asked for (through its solicitors LL) was very simple. They only wanted a preliminary visit in order to ascertain how the inspection of the FDs on the Office could be carried out. LL strenuously denied the allegations of (1) and (2) above. They pointed out that such allegations served no useful purpose to the planning, arranging and/or conducting the preliminary visit, fire damper inspections and repair. They also did not agree that the condition of the FDs would “inevitably the altered or tampered in the course of inspection” as suggested in Ip Kwan’s letter. LL also pointed out that Ocean System and Ip Kwan’s rights in the HCA Action could well be preserved by taking of photographs. They put on record that in related to these engaged specialists, MTRC would not agree to bear their costs and would ask the court to disallow such costs during taxation (if any). 37.LL’s letter ended with the sensible suggestion that in order to facilitate instructions being taken by them from the client, they say it would be helpful if Ip Kwan could specify in writing “the exact parameters or conditions for the proposed preliminary visit”. 38.This short letter dated 10 September 2024 from LL invoked yet another lengthy reply from Ip Kwan on 10 September 2024. This letter again linked the issues of the HCA Action rather than dealing with the simple request made by MTRC for carrying out the preliminary inspection first and then to agree on the method statement for the inspection and repair of the FDs. For example, this letter included the following matters which were highlighted by Mr Wong SC in his submissions:-
39.In the reply letter by LL dated 24 September 2024, LL pointed out that there was no reason or basis to accuse MTRC of tampering with the evidence or attempting to perform unrelated tasks during the proposed preliminary visit and/or the inspection and maintenance of the FDs. The specifically mentioned that the purpose of the visit to the Office was strictly for “the inspection and maintenance of the FDs”. 40.In the same letter, LL also repeated the position that they had time and again invited Ip Kwan to set out the proposed conditions for the visit (if any), then it was considered necessary to record the status of the FDs. Up to that date, Ip Kwan insisted there are conditions to be imposed, but yet refused to state what they are, despite having been clearly informed of the purpose of the visit. Again, they repeated MTRC’s position on the preliminary visit as follows: -
41.In the same letter, LL also gave notice pursuant to Clause 9(a)(7) of the DMC to attend Ip Kwan’s office on 2 alternative time given to them either on 27 September 2024 or 4 October 2024. LL invited Ip Kwan to make necessary arrangements to facilitate the inspection and maintenance of the 4 FDs. They also invited Ip Kwan to take any measures as they consider necessary and appropriate to record the status of and/or witness the process of the inspection and maintenance, with the issue of costs reserved. 42.On the same day, ie 24 September 2024, Ip Kwan replied to the above letter of LL. Again, writing under the heading of the HCA Action, Ip Kwan tried to link the inspection and examination of FDs issue with the issues under the HCA Action. For example, the following matters which were not related to the request from MTRC for the preliminary inspection have been stated:-
43.The letter ended with Ip Kwan asking LL to provide answers to the 5 questions they have set out in the previous letter without agreeing to MTRC’s request for the preliminary inspection in order to comply with the FSD Notice:-
44.Further letters were written by Ip Kwan on 25 September 2024, 27 September 2024 and 2 October 2024. Suggestion has been made by Ip Kwan for appoint a mediator so that “the parties could discuss the differences directly and the concerns and logistics could be addressed and sorted out ASAP”. 45.In the letter dated 2 October 2024, Ip Kwan mentioned that they had just been served with the FSD Notice by the FSD. They understood that the FSD Notice would be sent to all co-owners of Admiralty Centre. Instead of focusing on the request only by MTRC for arranging the inspection of FD2 which was the subject matter of the FSD Notice, Ip Kwan again linked the request by MTRC for preliminary inspection to the issues in the HCA Action as the following paragraphs in that letter would demonstrate:-
46.In the reply to the Ip Kwan’s 2nd letter dated 24 September 2024, letters dated 25 September 2024, 27 September 2024 and 2 October 2024, LL in their letter dated 4 October 2024, writing under the heading of “Fire Damper Inspection, Repair and/or Maintenance Fire Hazard Abatement Notice dated 30 September 2024 Admiralty Centre”, set out MTRC’s position clearly as revealed in the ensuring paragraphs:-
47.In the reply letter of the same day, ie on 4 October 2024, Ip Kwan disputed the contents of the LL’s letter and concluded by stating the following:-
48.Given Ip Kwan’s position on the matters as stated clearly in the above letter, MTRC took out the OS on 24 October 2024. Events after the Issue of the OS on 24 October 2024 49.Under the OS, MTRC basically was seeking the same things as they had been asking for all along from Ip Kwan through the correspondence of its solicitors LL. For the sake of completeness, the following are the orders which MTRC were seeking under the OS:-
50.The OS was supported by CWK 1st which consisted of 28 pages, summarizing MTRC’s position on this matter and the basis of the application. 51.Somehow this caused Ms Kwan to file a 77-page long affirmation in reply on 21 March 2025. Two shorter affirmations (2nd affirmation consisted of 3 pages and 3rd affirmation consisted of 7 pages) were filed by Ms Kwan on 14 April 2025. Mr Chau filed his 2nd affirmation on 9 May 2025 in reply to Ms Kwan’s above three affirmations. 52.I note that, after the issue of the OS by MTRC, there has been a noticeable change of attitude and stance on the part of Ds. For example, in the letter dated 28 October 2024, for the first time since LL made the first request for inspection on 13 August 2024, Ip Kwan responded positively to the proposal of a preliminary inspection to locate the 4 FDs. For the first time in over 2 months, they stated that:-
53.The letter went on to say the following:-
54.A further letter written by Ip Kwan on the same day agreed that arrangement should be made regarding the preliminary inspection of the 4 FDs to take place on 30 October 2024. 55.On 30 October 2024 and 31 October 2024, Ds further suggested the parties to jointly apply to the court to vacate the Hearing returnable on 1 November 2024, so that they would have time to work out the logistics. However, MTRC declined the offer of an adjournment on the grounds that “Ds still took [sic] issue of remaining paragraphs in the OS including the logistic in carrying out the inspection’” and “[a]s a consequence, entry to the [Office] for purpose of dealing with the 4 FDs remain unresolved”. 56.On 1 November 2024, the Hearing of the OS and the Summons took place before me. At the Hearing:-
57.As a result, the parties were able to reach consensus which resulted in the court making the Order based on the agreement of the parties. 58.As both Ms Eu SC and Mr Wong SC have repeatedly stated during the hearing on the Costs Issue before me on 23 July 2025, the parties were only able to come up with a practical solution on the method and timing of the inspection (in the form of the draft consent order reached between counsel outside of the court room) after the court had “knocked some sense into the heads” of them. APPLICABLE LEGAL PRINCIPLES 59.The principles governing costs are well-established. The court takes into account holistic considerations including those set out in Rules of the High Court (Cap. 4A) O. 62 r. 5. 60.In Cheung Kong Property (Business Development) Ltd v. Gold Brilliant Investment Ltd [2021] HKCFI 2330, the court held at §39 that:-
61.Where a case is settled save as to costs, the principles set out in Famous Marvel Co Ltd and Others v. Conversant Group Ltd and Ors HCA 2153/2009 (Unreported, 29 October 2012) at §22 are relevant:-
62.Litigants who conduct their cases in bad faith, or who cause costs to be incurred irrationally or out of all proportion as to what is at stake, may not only expect to pay costs, but also be ordered to pay costs on an indemnity basis if they lose, and have part of their costs disallowed if they win: see Chan Chung Sing v. Chan Andy Yuan [2024] 2 HKLRD 828 at §74. 63.The court has a wide discretion as to what, if any, terms should be imposed when giving leave to withdraw: see §28 of WSSA v SYH [2024] HKCA 1150. Generally speaking, upon an application for leave to discontinue proceedings, the discontinuing party will be required to pay the costs of the other party, unless exceptional circumstances can be shown to justify a different order: see §29 of WSSA. The overriding objective is to do justice between the parties; and a broad-brush approach is justified: see §32 of WSSA. 64.If a plaintiff withdraws an action or a summons because the defendant had done something, after the issuance of writ of summons or summons, which renders it unnecessary or academic for the plaintiff to proceed with the action or application, the court has a full discretion to award costs to the plaintiff after taking all the circumstances of the case into consideration, including that the respondent could have acted sooner: see §27 of Lo Siu Tim [2022] HKCFI 2946 per DHCJ Leung; §28 of Perrine Chamonix Limited (HCA 1139/2017, 13 Sep 2017) per DHCJ William Wong SC; §§4, 8 of Osman Mohammed Arab [2025] HKCFI 545 per DHCJ Grace Chow. 65.The authorities recognize the “effective winner” principle: see §§20, 29 of China Shanshui Cement Group Limited v Ng Sau Man Clifford [2020] HKCFI 2677 per K Yeung J, as explained at §§20-24, 28 thereof:-
The Crux of the Costs Issue 66.In my view, the real crux of the Costs Issue is who was the effective winner of the OS and the Summons in the present proceedings – was it MTRC or Ocean System/Ip Kwan? 67.For the reasons stated below, I have little doubt that the effective winner of the OS and the Summons was MTRC. General comments on Ds’ conduct 68.First and foremost, I consider these whole proceedings was unnecessary and avoidable had Ds been acting more reasonably with some common sense and objectivity. Instead of agreeing to a practical solution to the repeated requests made by MTRC on the inspection and repair of the FDs, Ds tried to conflate the issues stated in the OS with the issues in the HCA Action. In particular, multiple disproportionally lengthy and rather personal letters had been written by Ip Kwan trying to argue Ds’ case (by linking to the issues raised by them in the HCA Action) without really providing any definite reply to the rather simple and modest request made by MTRC for the inspection and repair to the FDs in order to comply with the FSD Notice. 69.While the court can understand the strong sentiments of Ds against MTRC after the fire which took place in the Office in 2018, it is most unfortunate in my view that Ds saw fit to link the issues raised in the HCA Action with the simple and modest request made by MTRC for the inspection and repair. It is apparent to me that Ds were trying to get as much mileage or leverage out of the inspection / repair of the FDs to bolster their claims in the HCA Action when the case is nowhere even close to the trial stage. 70.Second, it is clear that there was a marked change in Ds’ attitude after the commencement of the present proceedings. I have already mentioned the change in their attitude in §§52-55 above. I do not propose to repeat them here. I am of the view that had MTRC not issued the OS and the Summons, Ds would not have changed their stance and would not have agreed to the method statement and subsequent inspection. They had repeatedly refused to do so since LL made the first request on behalf of MTRC on 13 August 2024. Thus, in my view, it was the steadfast refusals on the part of Ds to agree to the requests made by MTRC that had caused MTRC to issue the OS and the Summons. 71.Third, in my view, had the court not forced the parties to put their heads together at the Hearing and “knocked some sense into their heads”, Ds would not have agreed to the method statement and the subsequent inspection. This again shows that the issue of the OS and the Summons by the MTRC were necessary. Ds’ irrelevant and unreasonable demands 72.In my judgment, Ds have made a number of irrelevant and unreasonable demands making the issue of the OS and the Summons by MTRC inevitable. 73.First, they included the unreasonable demands/conditions for allowing entry into the Office. Ds have by their letter dated 27 September 2024 claimed that no entry will be permitted as it is a law office “with large volume of client confidence retained” unless MTRC provided the information demanded in its letters dated 16 September 2024 and 24 September 2024. 74.However, in my view, these demands have nothing to do with preserving client confidence. Similar inspections had been carried out by MTRC before without any objection. I cannot see how the inspection and repair would affect client’s confidentiality of Ip Kwan at all. Further, as pointed out by MTRC, the entry was for the inspection and repairs to FDs located in the ceiling, and had nothing to do with any files. Any confidential materials could simply be put away; and any “concern” can sensibly be resolved by the use of screens/curtains/pieces of cloth. 75.Second, against the background that Ds have made claims in the HCA Action which related to the FDs’ condition, Ds have, by Ip Kwan’s letter dated 24 September 2024, accused MTRC: “If, before [Ds]’ experts have performed the examination and taken record of the condition of the fire dampers…[MTRC] has asked to inspect them singly and change their conditions, the request is clearly and undoubtedly an attempt to tamper of [sic] the evidence and to prejudice [Ds] irretrievably so much so that [Ds] would not be able to call evidence on the pleaded issues.” 76.However, even before that letter was issued, LL had on 10 September 2024[5] already indicated that “[Ds] may engage specialists as they think fit…”; and LL also gave further assurances on 24 September 2024 and 4 October 2024 that Ds were welcome to take any measures considered necessary and appropriate to record the status of the FDs and/or witness the process of the inspection, repair and/or maintenance. In my view, this should alleviate Ds’ concerns. In KLYC 1st at §115, Ds relied specifically upon LL’s aforesaid assurance and engaged experts to inspect the FDs, but this was only after these proceedings started. No explanation has been provided as to why this was not done earlier. 77.As it turned out, this was exactly what happened during the subsequent inspection and repair after the Order was made. On several occasions during inspection and repair to the FDs from November 2024 to February 2025, both sides’ experts were present[6]. 78.Third, Ds had, in contrast to their stance contained in Ds’ 29 October 2024 Skeleton, made the mere discussion of logistics conditional upon MTRC’s concession to its demands. These demands related to Ds’ claims in the HCA Action and not related to the FD inspection or repair. In my judgment, Ds were trying to extract and/or fish for admissions, evidence, documents, and an advantageous costs order for the purpose of the HCA Action. LL had already pointed this out by letter dated 4 October 2024 which I have set out in §46 above. 79.In my judgment, Ds have sought to capitalize on the urgency and seriousness created by the FSD Notice. What Ds basically said was that if MTRC wanted to comply with the FSD Deadline, it would have to make concessions in the HCA Action. Such a tactic in my opinion is oppressive and done at the expense of all the other owners. In my judgment, Ds have conducted themselves in bad faith, as a personal vendetta, in an improper/oppressive manner, and/or caused costs to be incurred irrationally out of all proportion to what is at stake. I am therefore of the opinion that it is appropriate to award costs on an indemnity basis. MTRC was the effective winner of the OS 80.Specifically, I consider that MTRC was the effective winner of the OS as they managed to obtain what they have asked for under the OS. I shall briefly deal with each of them below. §1 of the OS: Declaration that MTRC has the power to enter 81.I note it was only after the commencement of the proceedings that Ds were willing to concede that MTRC had the power to enter the Office. Ds confirmed by §3 of Ds’ 29 October 2024 Skeleton that they would not contest the declaration sought by §1 of the OS, which is based on DMC Clauses 9(a)(5), (7); 4 and paragraph B sub-clause 1(a) of the First Schedule. Accordingly, MTRC has obtained what it specifically sought in §1 of the OS. 82.As a consequence of Ds’ concession, there is no dispute MTRC also has the power under the DMC to enter the Office at reasonable hours upon 2 days’ notice for the purposes of: (1) repairing FD2; and (2) carrying out an annual inspection of FDs 1, 3 and 4; and if necessary, to carry out their repair and/or maintenance. Pursuant to Paragraph B sub-clause 1(a) of the First Schedule, MTRC has the “full right and privilege” to do so. 83.These clauses were drawn to Ds’ attention by letter dated 24 September 2024 (ie prior to the OS). Nevertheless, Ds refused access, necessitating the issuance of the OS. 84.Thus, I am of the view that MTRC was the effective winner on this matter. §§2-4 of the OS: Orders to allow entry into the Office 85.By §3 of Ds’ 29 October 2024 Skeleton, Ds state they “only took issue of the remaining paragraphs in the OS including the logistics in carrying out the inspection.” At §4, Ds refer to their “Logistics Proposal” contained in their letters dated 28 October 2024. However, I note that this only came after the issue of the OS and just before the Hearing. There is no explanation why Ds could not have made this Logistics Proposal earlier and since 13 August 2024. 86.In Ds’ belated Logistics Proposal:-
87.Hence, on this matter, I agree with the following submissions made by Ms Eu SC. 88.It was only by these proceedings that MTRC secured a preliminary inspection and a rational discussion as to logistics. Before all this, Ds’ stance was that a preliminary inspection was not necessary; and Ds had (by letters dated 24 September 2024 and 2 October 2024) made even the mere discussion of logistics conditional upon agreeing to their demands. As MTRC’s request for a preliminary inspection was made on 13 August 2024, Ds could and should have agreed much sooner. Instead, such agreement only came belatedly (ie after the issue of the OS on 24 October 2024) and as a result of having to attend court at the Hearing. 89.As to the Ds’ assertion at that the Hearing should have been vacated, I find that (1) Ds have not agreed to MTRC’s method statement or logistics for carrying out works on the FDs; (2) the FSD Deadline was imminent (as explained in LL’s letter of 31 October 2024); (3) Ds were only compelled to discuss the logistics for carrying out the necessary work outside the court room at the Hearing which led to the Order. 90.Thus, on this issue, I am of the view that MTRC was the effective winner. §§2-4 of the OS: Orders to allow entry into the Office 91.In my view, the terms of the Order also reflect that MTRC was the effective winner. 92.By §1 of the Order, MTRC was to provide a broad written method statement addressing (1) the protective measures and any necessary reinstatement to be undertaken in the course of repairing FD2 and carrying out an annual inspection of FDs 1, 3 and 4 (and if necessary, their repair and/or maintenance); and (2) the estimated time (“the Method Statement”). 93.The fact of the matter is that MTRC had never been opposed to this. In fact, the August Method Statement was provided to Ds before the OS but Ds did not comment on it at the time. 94.Importantly, the August Method Statement had already outlined the following:-
95.Ds have had ample time and countless opportunities to express any suggestions it may have in relation to the August Method Statement to be adopted but they did not. 96.MTRC duly provided the Method Statement on 7 November 2024. The protective works described were essentially those in the August Method Statement, but with specifics in view of the preliminary inspection on 5 November 2024. That was also the case with the reinstatement works. A time estimate was also provided. 97.In accordance with §2 of the Order, Ds replied on 8 November 2024, and no objections were raised to the Method Statement (as supplemented by correspondence exchanged between the parties). As such, pursuant to §3, Ds allowed MTRC entry on 9 and 16 November 2024. No affirmations were filed in accordance with §§4-5 and the hearing fixed for 21 November 2024 was vacated by Order dated 19 November 2024 in view of the parties’ joint letter dated 18 November 2024. 98.Thus, FD4 and FD2 (which was subject to the FSD Deadline) were dealt with on 9 November 2024 and 16 November 2024 respectively. In respect of FDs 3, 1, 5, the parties (as evidenced by the joint letter dated 18 November 2024) required more time to discuss the logistics of the examination, inspection, and repair. Ultimately, FDs 3, 1, 5, were dealt with on 12 December 2024, 8 January 2025, and 11 February 2025. 99.In light of the above, MTRC had entered the Office for the purposes of repairing FD2 and carrying out an annual inspection of FDs 1, 3, 4 (and 5) and their repair/maintenance (where necessary). This was the relief sought in §§2-4 of the OS. In this regard, I agree with Ms Eu SC that, but for the OS and the Summons, MTRC would not have obtained the relief it needed to comply with the FSD Deadline. Again, had Ds acted sooner and reasonably, MTRC would not have had to commence these proceedings in the first place. 100.Thus, on this matter, I consider MTRC was the effective winner also. Was the issue of the Summons necessary and was MTRC the effective winner? 101.I agree with Ms Eu SC that in view of the FSD Deadline, MTRC had to proceed speedily with the Hearing and obtain the Order. 102.Pursuant to §§4-7 of the Order, if the parties were unable to agree on the method statement, they were to file evidence by 11 and 15 November 2024 respectively; and a hearing was fixed for 21 November 2024 to resolve such differences. This was in line with the timetable sought by the Summons, whereby parties were to file evidence by 8 and 15 November 2024, with a hearing fixed not later than 29 November 2024. Thus, the Order provided an expedited timetable in view of the FSD Deadline. In my view, the timetable in the Order shows that MTRC was the effective winner of the Summons. 103.With the benefit of the Order, MTRC was able to deal with FD2 before the FSD Deadline. This was one of the main purposes of the OS, and the reason why the Summons for a speedy trial was sought. 104.Thus, I find MTRC was the effective winner of the Summons and/or the key purpose of the action has been achieved. D. CONCLUSION 105.In the aforestated premises, I grant leave to MTRC to withdraw and/or discontinue the OS and the Summons, with costs to be paid by Ds to MTRC on an indemnity basis, including all the costs reserved, with certificate for two counsel, such costs to be taxed if not agreed. 106.It remains for me to thank counsel on both sides for their helpful assistance.
Ms Audrey Eu SC leading Mr Albert Chan instructed by Lo & Lo for the plaintiff Mr William Wong SC leading Mr Martin Lau and Mr Victor Lui instructed by Ip, Kwan & Co. for the 1st defendant and the 2nd defendant [1] Including by letters dated 24 September 2024 and 4 October 2024. [2] A number of “reserved costs” orders were made in the course of these proceedings including those appeared at [B/14/§11]; [B/17/§4]; [B/20/§5] [B/23/§4]; [B/24-02/§6] [3] Applied and explained in Dixie Engineering Company Limited v Long Engineering Limited [2025] HKCFI 1809 at §§2-3 per Harris J [4] Applied in §48 of Preamble Properties Finance Limited [2020] HKDC 404 perHHJ Andrew Li [5] See also: LL’s letter dated 26 August 2024: “If preservation of evidence is your clients’ concern, the parties could take photographs of the relevant [FDs] and their surrounding areas…” [6]See Summary of Entry to the Office due to FDs prepared by Ds at [D/58/543-544] |
Cases cited in this judgment
Other judgments that cite this case
Further hearings and rulings under HCMP 2140/2024