Chiu Hung Shun, Paul and Another v. So Ka Tai and Another
Read the full judgment text of CACV 136/2005 on BabelCite. This Court of Appeal judgment was delivered on 5 December 2005 before Ma CJHC, Suffiad J, Barma J.
Civil appeal – water leakage from upper to lower flat – Deed of Mutual Covenant – breach of covenant and nuisance – admission of liability – interlocutory judgment under RDC O.27 r.3 – whether party against whom judgment is sought may apply for judgment on admissions – permanent injunction – Doherty v Allman (1878) 3 App Cas 709 – equitable discretion – whether covenants negative or positive – Incorporated Owners of South Seas Centre v Great Treasure Development Ltd [1994] 1 HKC 197 – continuing breach and risk of repetition – The Attorney-General v Birmingham, Tame, and Rea District Drainage Board [1912] AC 788 – mandatory injunction to repair – undertaking to permit access – indemnity basis costs – contractual right to costs – Gomba Holdings (UK) Ltd v Minories Finance Ltd (No.2) [1993] Ch 171 – residual discretion – partial success on appeal – apportionment of costs at 75% below and 25% of appeal. The Plaintiffs and Defendants are neighbours in Bayshore Towers, Shatin, with the Defendants' flat immediately above the Plaintiffs'; water had seeped from the Defendants' flat into the Plaintiffs' flat since about February 2004. Following a writ on 6 October 2004 relying on covenants in the Deed of Mutual Covenant, the Defendants admitted liability by letter dated 24 February 2005 and offered HK$40,000 and a joint surveyor. The Plaintiffs counter-offered seeking a mandatory and permanent injunction, but no agreement was reached. The Plaintiffs took out a summons on 23 March 2005 under RDC O.27 r.3 seeking judgment and a permanent injunction, and the Defendants took out their own summons on 29 March 2005 also seeking judgment on liability against themselves and the dismissal of the Plaintiffs' summons. Judge Wesley Wong dismissed the Plaintiffs' summons with costs, granted judgment on liability by consent, ordered the Defendants to rectify the leakage within 42 days, and imposed an access undertaking on the Plaintiffs. On appeal, the Court of Appeal held that only a party other than the party against whom judgment is sought may apply under O.27 r.3, so the Defendants' application was misconceived and the Judge erred in dismissing the Plaintiffs' summons with costs. On the permanent injunction issue, the court rejected the submission that Doherty v Allman compelled the grant of an injunction enforcing the negative covenants; properly analyzed the covenants imposed a positive obligation to maintain premises in repair, and with no evidence of continuing risk or intention to repeat the breach, a permanent injunction was not warranted in addition to the mandatory injunction already ordered. The access undertaking was a necessary adjunct to the repair order and was properly imposed. The claim for indemnity basis costs based on the DMC indemnity clause was refused as it had not been raised in correspondence, pleadings, or the original grounds of appeal. The appeal was allowed in part: paragraphs 2 and 5 of the Judge's order were set aside, the Defendants' summons was dismissed, the costs of the action on liability were awarded to the Plaintiffs on a party-and-party basis with certificate for counsel, 75% of the costs of the Plaintiffs' summons and the hearing below were awarded to the Plaintiffs, the costs of the Defendants' summons (other than the hearing) were awarded to the Plaintiffs, and 25% of the costs of the appeal were awarded to the Plaintiffs; the Defendants were given leave to adduce additional evidence.
Legal issues: Proper party to apply for judgment on admissions under RDC O.27 r.3 · Whether a permanent injunction should be granted in addition to a mandatory injunction for water leakage · Propriety of the undertaking to allow the Defendants' surveyor access to the Plaintiffs' premises · Whether costs should be awarded on an indemnity basis under the Deed of Mutual Covenant
Outcome: Appeal allowed in part; the order of Judge Wong dated 1 April 2005 was set aside in part, the Defendants' summons of 29 March 2005 was dismissed, and the Plaintiffs were granted a partial award of costs below and on appeal.
Cited by 20 cases
|
CACV136/2005 IN THE HIGH COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION COURT OF APPEAL CIVIL APPEAL NO. 136 OF 2005 (ON APPEAL FROM DCCJ NO. 5242 OF 2004) ______________________ BETWEEN
______________________ Before : Hon Ma CJHC, Suffiad & Barma JJ in Court Date of Hearing : 22 November 2005 Date of Judgment : 22 November 2005 Date of Handing Down Reasons for Judgment : 5 December 2005 _________________________ REASONS FOR JUDGMENT _________________________ Hon Ma CJHC : 1.The present appeal was concerned with a dispute between neighbours over the leakage of water from the Defendants’ premises into the Plaintiffs’. Liability was basically admitted but it was the consequential orders made by Judge Wesley Wong in the District Court that formed the subject matter of the appeal. After hearing submissions from counsel (Mr K M Chong and Mr William Leung (Mr Shuni Yoneya) for the Plaintiffs, and Mr Joeson Wong for the Defendants), we allowed the appeal in part (on which I shall elaborate further below), stating that the Reasons for Judgment would be handed down in due course. The facts 2.As mentioned above, the Plaintiffs and the Defendants are neighbours in a building in Shatin, the Plaintiffs owning and occupying a flat on the 9th floor, the Defendants owning and occupying the flat immediately above. It would appear that since about February 2004, there had been seepage of water from the Defendants’ flat into the Plaintiffs’ flat. Whatever repair work that had been carried out by the Defendants obviously did not satisfy the Plaintiffs. Following a letter dated 7 May 2004 from the Plaintiffs complaining about the leakage and offering to settle on various terms, a letter in reply dated 10 July 2004 which denied any responsibility and various other correspondence between the parties’ respective solicitors, a writ was issued on 6 October 2004 in the District Court. 3.Reliance was placed in the Statement of Claim (which was endorsed on the writ) on the following terms of the Deed of Mutual Covenant that governed the relations between the Plaintiffs, the Defendants and other owners of the building in which they lived : -
4.The following relief was claimed in the Statement of Claim : -
5.The Defendants denied liability in their Defence dated 5 November 2004. However, in an open letter dated 24 February 2005 from the Defendants’ solicitors to the Plaintiffs’ solicitors, the Defendants’ erstwhile position changed : -
A draft consent order was enclosed with this letter. 6.By a letter in reply dated 14 March 2005, the Plaintiffs’ solicitors made effectively a counter-offer which stipulated the terms of any judgment to include both a mandatory injunction to remedy the water leakage as well as a permanent injunction in the terms sought in the Prayer to the Statement of Claim. As to costs, the offer was that the Defendants pay the Plaintiffs’ costs on a party and party basis, such costs to be taxed if not agreed. The hearing below 7.No agreement being reached, both parties took out summonses before the Court. First in time was the Plaintiffs’ summons dated 23 March 2005 seeking the following orders : -
8.The Defendants’ summons dated 29 March 2005 sought the following relief : -
9.Both summonses were heard by Judge Wong on 1 April 2005. The following orders were made by him : -
The appeal 10.It is from this order that the Plaintiffs appealed. In the Notice of Appeal dated 15 April 2005, the Plaintiffs sought that the following orders be substituted for the orders made by the Judge : -
11.Before us, Mr Chong focused on four points in appealing the order below : -
12.I now deal with these points in turn. Should the Plaintiffs’ summons have been dismissed? 13.In my judgment, the Plaintiffs’ summons should not have been dismissed by the Judge. The Plaintiffs had sought judgment on liability based on the admission contained in the said letter dated 24 February 2005. Their application for judgment was made under RDC O.27 r.3 and this was clearly justified. On the other hand, the application for judgment contained in the Defendants’ summons (see paragraph 8 above), also made under RDC O.27 r.3, was misconceived. 14.RDC O.27 r.3 (which mirrors RHC O.27 r.3) states as follows : -
It is clear from the italicized words “any other party” that only parties other than the party against whom judgment is sought, can apply for judgment on admissions. The Judge was therefore in error in allowing the Defendants to apply for judgment under RDC O.27 r.3. Permanent Injunction 15.Here, Mr Chong relied on the well-known obiter dicta of Lord Cairns LC in Richard Wheeler Doherty v James Clagston Allman and W.C. Dowden (1878) 3 App Cas 709 HL, at 719-720 where it was said : -
16.Some of the relevant covenants being negative ones (see paragraph 3 above), it is then submitted that a permanent injunction should therefore have been granted by the Judge. In my view, the Judge was right to have refused to grant the Plaintiffs such an injunction : -
The undertaking 17.This point can be shortly disposed of. Such an undertaking or order was obviously necessary so as to ensure that the mandatory injunction regarding the repair of the leakage by the Defendants could be effectively carried out by an inspection of the Plaintiffs’ premises. The submission that somehow access would be unrestricted, uncontrolled or for an indefinite period, was far fetched : such a right to access could only be for the purposes of effecting the repairs to stop the leakage and insofar as any conditions were necessary to ensure that the Plaintiffs were not unduly disturbed or inconvenienced, suitable conditions could have been suggested to the Judge or use made of the liberty to apply implicit in the Judge’s order. Costs 18.Mr Chong referred us to Gomba Holdings (UK) Ltd and Others v Minories Finance Ltd and Others (No.2) [1993] Ch 171 where at 194, Scott LJ (now Lord Scott of Foscote) said : -
This reflects the law and practice in Hong Kong but it is important to remember that a residual discretion nevertheless rests with the Court regarding costs. 19.In the present case, there were (as will presently be seen) good grounds not to give the whole of the costs of the action to the Plaintiffs in the first place. Coupled with the fact that an order for costs on the indemnity basis was not sought in correspondence (see paragraph 6 above), the pleadings or even in the Notice of Appeal, the belated attempt by the Plaintiffs to claim costs on this basis could not be permitted and accordingly leave to amend the Notice of Appeal was refused. The order in this appeal 20.Mr Wong submitted that the appeal was somehow academic since repairs had already been effected. In my view, the appeal was clearly not academic since there were other matters (principally the issue regarding the dismissal of the Plaintiffs’ summons and the question of costs) that still had to be resolved on appeal. 21.Even though many of the Plaintiffs’ arguments on appeal have had to be rejected, they nevertheless had to come to the Court of Appeal to seek a reversal of the order below dismissing their summons with costs. In my judgment, the Judge was wrong to have made this order. I have already earlier dealt with why the Defendants’ summons, in seeking judgment against themselves by admission, was misconceived. So was the seeking of an order that a surveyor be appointed whose findings, opinion and certification would be final and conclusive. This was not an order to which the Defendants were entitled. Apart from anything else, the Court would be extremely hesitant to allow a third party to determine, instead of the Court, whether an order of the Court had been complied with. Indeed, I cannot conceive of any situation in which such an order would be made unless the parties agreed by consent to do so (in the form usually of a Tomlin order). 22.As for the costs of the action and of the hearing before the Judge, the Plaintiffs again had to go to Court in order to get an order ensuring not only that judgment was entered in their favour but also that repairs would be duly carried out. Although this had been suggested by the Defendants in correspondence, the suggested imposition of a condition that a surveyor be appointed whose findings, opinion and certification would be final and conclusive, was not for the reasons stated above, acceptable. In my view, the Plaintiffs were entitled to an order of costs in their favour, although in view of the failure on the part of the Plaintiffs of many of their arguments, there should only have been a partial order in their favour which we decided at 75%. 23.As for the costs of the appeal, again in view of the partial failure on the part of the Plaintiffs, this should be reflected in the final order. We thought that the Plaintiffs should be entitled to 25% of their costs. 24.Accordingly, the order made at the conclusion of the appeal was as follows, namely that : -
Hon Suffiad J : 25.I agree. Hon Barma J : 26.I agree.
Mr K M Chong & Mr William Leung (Mr Shuni Yoneya) instructed by Messrs Peter Mo & Co for the Plaintiffs/Appellants Mr Joeson Wong instructed by Messrs Peter K H Wong & Co for the Defendants/Respondents | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Other judgments that cite this case