Grand Power International Ltd v. Chan Sing Hoi Enterprises Ltd and Others
Read the full judgment text of LDBM 329/2014 on BabelCite. This Lands Tribunal judgment was delivered on 8 March 2019.
1. By the judgment handed down by me on 1 November 2018 (“the Judgment”), I made a costs order nisi (“the Costs Order Nisi”) that:-
Cites 8 cases
|
LDBM 329/2014 [2019] HKLdT 16 IN THE LANDS TRIBUNAL OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION BUILDING MANAGEMENT APPLICATION NO 329 OF 2014 _______________
_______________
_________________________ DECISION _________________________ Background 1.By the judgment handed down by me on 1 November 2018 (“the Judgment”), I made a costs order nisi (“the Costs Order Nisi”) that:-
2.Unless otherwise stated, I will adopt the abbreviations used in the Judgment. 3.By the Summons (“A’s Summons”) dated 14 November 2018, A seeks an order to vary the Costs Order Nisi as follows:-
4.By the Summons (“R1’s Summons”) dated 15 November 2018, R1 seeks an order to vary the Costs Order Nisi as follows:
A’s Summons 5.I shall deal with A’s Summons first. 6.I agree with the submission of Mr Lee for A that the starting point is section 12 of the Lands Tribunal Ordinance (Cap 17) (“LTO”) which provides as follows:
7.Mr Lee submitted that after the CJR, the courts are more ready to depart from the general rule that costs should follow the event: Pfeiffer GmbH v Cheung Hay Kit trading as Sun Wai Construction, CACV 245/2013 (29 October 2014) at §§7-10 (perKwan JA giving the reasons for judgment of the Court of Appeal). Lord Woolf’s observations cited in Pfeiffer’s caseat §8 are particularly germane in the present context:
8.In Chan Shun Kei trading as Chan Shun Kei Construction Works v Hong Kong Construction (HK) Ltd, CACV 192/2014 (7 March 2016) at §24, Lam VP (giving the judgment of the Court of Appeal) noted that the plaintiff failed in respect of 6 issues out of 8 issues addressed at the trial and said:
9.On the other hand, Mr Fan cited SNE Engineering Co Ltd v Hsin Chong Construction Co Ltd (HCA 1466/2012), in which Lok J ordered the plaintiff (the losing party) to pay the costs of the 2 defendants after trial. The plaintiff applied to vary the costs order on the ground that there should be issue-based approach in dealing with costs. The learned judge having considered Pfeiffer’s case as well as Chinachem Charitable Foundation Ltd v Chan Chun Chuen & Anor[1] handed down the Decisions on 23 June 2015 refusing to vary the original costs order. 10.The plaintiff appealed to the Court of Appeal[2] (CACV 88/2014, 6 August 2015) which dismissed the appeal and said in the judgment:
11.In short, I am of the view that the Tribunal must have very wide discretion for the question of costs and that not only in patent cases, issue-based approach is also not a strict rule of law for determination of such question in building management cases which much depend on their own facts. The ultimate aim is always to make a cost order which reflects the overall justice of the case[3]. As required by section 12 LTO, it is also necessary for the Tribunal to consider the matters mentioned in Order 62 Rule 5 of the Rules of the High Court (Cap. 4A), which provides that:-
12.Mr Lee for A submitted that this Tribunal dismissed both A’s claims as well as R1’s counterclaim which is substantially a cross-action, not merely a defence to the plaintiff’s claim. In my view, all the declaratory reliefs counterclaimed by R1 are in effect almost mirroring and corresponding to the declaratory reliefs sought by A. The actual time spent by A in opposing R1’s counterclaim is very minimal since if A succeeds in obtaining the injunctions sought, R1’s counterclaim will be bounded to be dismissed. I consider that it has not caused any significant increase in the length of the proceedings. 13.Mr Lee for A indeed heavily relies upon the issue-based approach and submitted that R1 only prevailed in respect of 6 out of 13 issues in dispute and failed in respect of the remaining issues addressed at the trial. However, I think that there are much more side or sub issues in dispute which are inter-related to each other. Some of them are complicated legal issues but involves very little factual dispute whilst some are pure factual disputes not really involving much legal principles. Of course, there are some mixed question of law and facts to different extent. It is always difficult to say how much time is actually spent on each of these issues. I further consider that issue-based approach which should not be regarded as strict rule of law cannot be an arithmetic exercise to determine the percentage of the costs to be borne by the parties. After all, it is just one of the factors affecting the wide discretion given to the Tribunal under section 12 LTO. 14.Mr Lee for A submitted that R1 adopted a “kitchen-sink” approach in conducting these proceedings, contesting against A’s claims every step on the way, apparently without consideration of the underlying merits and contrary to the underlying objectives of proportionality and procedural economy. 15.In my view, the injunctions sought by A must have great importance to R1 which has used to lease the 4 units ie G/F No 72, G/F No 74, 1/F No 74 and 1/F No 76 for profit for the past many years as well as in the future. Bearing in mind their location in the heart of Causeway Bay, the redevelopment value of the Building is extremely high. Besides, in view of the existence of the Acquisition Campaign found by me in the Judgment, not just the rental, even the market value of these units are very likely adversely affected if the injunctions were granted. 16.It is understandable as to why R1 has to vigorously contest A’s claims. In the circumstances, I do not agree that R1 unreasonably raised those defences or issues even though they were eventually rejected by me. 17.Although most of the evidence given by R1’s witness, Yuen, were not accepted, in particular his evidence concerning the Common Assumptions, in the Judgment, I consider that he still in any event had to give oral evidence at the trial regarding other matters and defences of R1, such as acquiescence and waiver, which were accepted by me. On the other hand, I rejected the evidence of A’s witness, Yip that the issue of safety was the reason for instituting these proceedings and I also found against him that he turned his blind eyes as to the existence of the incorporated owners of the Building without making reasonable enquiries. 18.In fact, one of the most difficult legal issues in the present case is whether A is bound by the defence of waiver and acquiescence established against its predecessor in view of the conflicting authorities. After analysing a lot of legal authorities, I found this issue against A in the Judgment. However, this issue does not much depend on the evidence of the parties’ witnesses. 19.Concerning the conduct of the parties, I spent about half day in the 1st day trial to deal with A’s summons to expunge certain paragraphs of the witness statements of R1 and R2 and delivered the oral reasons for decision in the 2nd day morning. Then A took almost the entire remaining time in the 2nd day trial to reach the settlement with R2 whereas the solicitors and Counsel of R1 seemed to have nothing to do but wait. In my view, I can see no reason why A and R2 together with their legal representatives could not do the negotiation earlier or during the lunch break or even after the hearing. Some costs of R1 must be wasted and I have to take this into account in exercising the discretion as to costs. 20.As a whole, I do not find that R1 raised the issues which have the effect of unnecessarily prolonging the trial or caused a significant increase in the length of the trial. After all, many issues overlap and are interrelated with each other. As said above, the injunctions sought by A have great impact on the value of R1’s 4 units, R1 should be entitled to raise all reasonable defences in order to defeat A’s claims. I therefore refuse to apportion the liability for costs in respect of those issues pursued by R1 but rejected by the Tribunal. 21.In the Judgment, I also exercised the discretion not to grant the injunctions even if R1 failed to establish the defences of waiver and acquiescence. R1 should be regarded as the winning party in any event. Having carefully considered all the circumstances of this particular case and with a view to reflecting the overall justice, I maintain that A shall pay R1 costs of the proceedings. A’s Summons be dismissed accordingly. R1’s Summons 22.R1 has advanced two reasons to justify its request for indemnity costs. 23.First, R1 relies on Clause 10 of the DMC which states:
24.This clause consists of several parts, and R1 is relying on the last part namely, to indemnify all other owners against all actions, proceedings, claims and demands whatsoever arising out of or in respect of any loss or damage to any person or property caused by the act negligence or default of all such persons, which is referring to the persons occupying or using the unit with this unit owner’s consent. 25.Mr Fan for R1 submitted that under this clause as properly construed, the “act” shall include an “act to sue”. With respect, I disagree. I fail to understand as to how the “act” could include an “act to sue” of the persons occupying or using the unit with that owner’s consent. In my view, what this clause means is that if owner X takes legal actions against another owner Y in respect of any loss or damage caused by the act negligence or default of the persons who occupy or use Y’s unit with Y’s consent, Y shall indemnify X against such actions, including the legal costs incurred by X. 26.The defence of R1 to A’s claims as well as R1’s counterclaim against A for various declarations are certainly not within the scope of this clause since it has nothing to do with the act of the persons who occupy or use the A’s unit with its consent. This reason relied on by R1 must be rejected. 27.Secondly, Mr Fan for R1 submitted as a further or alternative ground for an award of indemnity costs, that there exists in the present case some special or unusual features. 28.The principles governing the award of costs on an indemnity basis were summarized by Ribeiro PJ in Libertarian Investments Ltd v Thomas Alexej Hall, FACV 14/2012 (11 March 2014) at §6 as follows:
29.In my view, there is no “special or unusual feature” justifying the Tribunal to exercise discretion to order for costs on an indemnity basis against A. As said in para 131 of the Judgment, I was not able to guess what A’s motives of commencing the present proceedings were. In other words, I cannot find any ulterior motive or improper conduct relating to the conduct of the litigation on the part of A, though it is the losing party. 30.Hence, R1’s Summons be dismissed. Costs of these 2 applications 31.Parties’ Counsel accepted that costs shall follow event. Usually, A shall pay R1 costs of A’s Summons whereas R1 shall pay A costs of R1’s Summons. However, in view of the fact that 2 applications were heard together and both Counsel made submissions at the same time, I consider that costs of these 2 applications would be more or less the same. After setting off, the difference should be very small. Thus, in order to save time for taxation, I exercise the discretion to make no order as to costs for these 2 applications.
Mr Jason Lee, instructed by Mayer Brown, for the applicant Mr Alex Fan, instructed by Hon & Co., for the 1st respondent [1] unreported, HCAP 8/2007 (16 April 2010), decided by Lam J (as he then was) [2] BeforeLam VP, Cheung and Kwan JJA [3] Para 48 of the Decisions of Lok J in HCA1466/2012 dated 23 June 2015 and para 11 of the Judgment of Mr Justice Christopher Clarke in Travelers Casualty & Surety Co of Canada v Sun Life Assurance Co of Canada (UK) Ltd [2006] EWHC 2885 (Comm) | ||||||||||||||||||||||||||||
Cases cited in this judgment
Further hearings and rulings under LDBM 329/2014