Great Tower Development Ltd v. The Incorporated Owners of LusoApartments
Read the full judgment text of DCCJ 331/2022 on BabelCite. This District Court judgment was delivered on 17 March 2023.
1. This is the Plaintiff’s application for summary judgment made by summons taken out on 3 March 2022 (“ the Summons ”).
Cites 12 cases
|
DCCJ 331/2022 [2023] HKDC 356 IN THE DISTRICT COURT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION CIVIL ACTION NO 331 OF 2022 -------------------- BETWEEN
--------------------
-------------------- DECISION -------------------- 1.This is the Plaintiff’s application for summary judgment made by summons taken out on 3 March 2022 (“the Summons”). 2.The Plaintiff’s claims in the instant action against the Defendant (“D”) are based essentially on negligence and nuisance.[1] P is and was at the material time the registered owner of Flat D71, 7th Floor, Luso Apartments, 5 Warwick Road, Kowloon Tong, Kowloon, Hong Kong (“D71”). I shall refer to Luso Apartments hereinbelow as “the Building”. The Building has 4 blocks (ie Blocks A to D) and D71 is located at Block D. D is and was at the material time the Incorporated Owners of the Building. By virtue of its position as the Incorporated Owners of the Building, D is and was at the material time in control and possession of all the common areas of the Building, including the external walls adjoining D71. A. P’S PLEADED CASE 3.On 24 January 2022, P issued the instant proceedings against D, and its case is pleaded as follows[2]: -
B. THE BACKGROUND 4.P first discovered the said water seepage in early 2015. After P’s expert conducted an inspection at D71 around 11 December 2015, P via its solicitors first wrote to D on 2 November 2016. There ensued a string of correspondence exchanged between P’s solicitors and D between 2 November 2016 and 26 April 2017.[4] 5.P commenced its first action against D concerning the said water seepage on 19 May 2017. (“the 2017 Action”) 6.On 8 June 2017, D signed an agreement to engage 良友工程有限公司 (Leung Yau Building Limited) (“LYB”) to conduct inspection and repair works on the common parts of the Building under the Mandatory Building Inspection Scheme (“the Refurbishment Works”).[5] (“the Agreement”) 7.Under “SCHEDULE OF RATES BLK D - Schedule No 2: Concrete and Rendering Repair Works at External Walls” and “SCHEDULE OF RATES BLK D - Schedule No 3: Patch repair of External Wall tile” to the Agreement, the repair works included, inter alia, the following: -
8.In 2017, LYB began the Refurbishment Works under the Agreement, and sent out the first questionnaire to all the flat owners of the Building, asking for comments on any structural defects existed in their flats including water seepage (“the 1st Questionnaire”). P did not respond to the 1st Questionnaire.[7] 9.In late 2018 when the Refurbishment Works including the repair works were close to completion, LYB sent out the second questionnaire to flat owners of the Building, asking for comments on any structural defects existed in their flats (“the 2nd Questionnaire”). P only responded to the 2nd Questionnaire by requesting for cleaning works to be done.[8] 10.LYB had conducted checks on the external walls of the Building including conducting hammer tapping tests and replacement of defective external wall tiles when necessary. 11.In or around 3 January 2019, LYB completed the Refurbishment Works under the Agreement. 12.On 17 April 2019, P wrote a letter to notify D that the water seepage still existed after P had conducted repair and decoration works inside D71.[9] (“the 17/4/19 Letter”) 13.The 17/4/19 Letter triggered off another string of correspondence between P and D until 2 December 2019[10] whereby D insisted on the necessity to conduct physical inspection in D71 so as (a) to ascertain the condition and cause of the water seepage in D71 and (b) to work out a practicable proposal and plan to resolve the water seepage problem at D71.[11] P took the position that the water seepage at D71 complained of in the 17/4/19 Letter was related to the subject matter of the 2017 Action and the request for physical inspection in D71 would not assist in the resolution of the dispute in the 2017 Action since each party’s expert had already inspected D71 and filed his expert report.[12] 14.On 14 August 2020, LYB received a questionnaire from P, requesting to deal with the water seepage problem in the 2017 Action, in particular, to follow up on, inter alia, the peeling-off of the wall paint at the dining room, kitchen and bathroom at D71.[13] (“the 3rd Questionnaire”) In the 3rd Questionnaire, P asked LYB to confirm with D71 the 4 problem-locations mentioned therein before LYB made appointment with D71 owner to inspect D71. 15.On 25 September 2020, P wrote a letter to D, referring to the 26/9/19 Letter, complaining about further signs of water seepage which were relevant to the subject matter of the 2017 Action and suggesting that the experts appointed by P and D in the 2017 Action would jointly perform a visual inspection at D71 at a mutually convenient time.[14] Thereafter and until the trial of the 2017 Action in late May 2021, the correspondence between P and D revolved around the question of joint inspection at D71, its scope, whether the persons who accompanied P and D to perform the joint inspection at D71 were required to be the experts appointed in the 2017 Action and whether supplemental expert reports should be compiled by P and D for the 2017 Action after the joint inspection.[15] 16.On 15 October 2020, D (by its then chairman and secretary) was refused entry into D71 for the purpose of visual inspection because D was not accompanied by its expert in the 2017 Action, but by a representative from LYB. 17.On 22 March 2021, D via its management office wrote to P’s solicitors, reiterating the 3rd Questionnaire and asking P to make arrangement with the management office so that LYB could inspect and repair D71within the warranty period.[16] 18.By letter dated 13 April 2021[17], P refused the inspection to be carried out by LYB unless D accepted the responsibility of the water seepage problem at D71, a problem having been caused by the defective external wall of the Building. By the same letter, P took the view that even if the water seepage problems were not covered by the 2017 Action, LYB nevertheless did not have the necessary expertise to determine the cause of those problems. 19.The 2017 Action was tried in May and June 2021 and the Judgment handed down on 8 September 2021.[18] 20.After the Judgment was handed down, D emailed P on 10 September 2021, seeking permission from P to enter D71 for inspection.[19] By email dated 20 September 2021, P replied by stating that the water seepage problem at D71 still persisted and asking D to contact its tenant Mr Leung directly for the inspection.[20] 21.On 25 September 2021, D (by chairman Mr Yuen and secretary Dr Woo) visited D71 and observed peeling-off of wall paint. It was agreed that waterproofing works had to be undertaken. 22.By letter dated 7 October 2021, P asked D to provide a rectification plan and the timeline of carrying out the rectification within 42 days, otherwise legal proceedings would be issued without further notice.[21] 23.On 11 October 2021, P’s tenant complained of serious water seepage problem at D71’s dining and living areas after heavy downpour. On the same day, D was notified by the owner of Flat D81, Block D of the Building (“D81”), a vacant flat immediately above D71, that rainwater overflowed on the balcony of D81.[22] Some remedial measures were taken by the owner of D81 and the overflow problem at D81 was resolved. D had received no further water seepage complaint from P and Mr Leung even after typhoon signal No 8 was hoisted on 13 October 2021. 24.By letter dated 2 November 2021, P reiterated its demand to D for a detailed rectification plan within 42 days from 7 October 2021 whilst acknowledging that the overflow of water on the balcony of D81 could also be another possible source of the water seepage problem at D71.[23] 25.In early November 2021, it was agreed by the members of the 3rd Management Committee of D that repair works had to be conducted on the external walls outside both D71 and D81 and scaffoldings erected outside D81.[24] However, D81’s owner refused D’s access to its flat for repair works. Therefore, the members of the 3rd Management Committee of D decided to gain access to D71 to carry out the repair works.[25] 26.By letter dated 8 November 2021, the management office of D proposed to P that it would obtain quotation from contractors to repair external walls outside D71 with access through D71 for 1 week.[26] On 12 November 2021, P rejected D’s proposal.[27] 27.On 16 November 2021, the management office of D contacted BMC Construction Centre Limited (“BMC”) for quotation for the repair and maintenance works to be carried out on the external walls outside 7/F to 9/F of Block D of the Building by scaffoldings to be erected from the roof top to 7/F of Block D of the Building.[28] 28.Between 16 and 22 November 2021, the staff of BMC conducted a site visit and expressed safety concerns as to erecting scaffoldings from the roof top to 7/F. BMC proposed to D to erect the scaffoldings from the G/F to 7/F of Block D of the Building. On 23 November 2021, BMC provided D with a quotation, setting out in detail the repair works to be carried out on the external walls of 7/F to 9/F of Block D of the Building at the price of HK$103,600.00.[29] (“the 1st Quotation”) The 1st Quotation provided for erecting scaffoldings from G/F to 9/F of Block D of the Building and 25 to 30 working days for the repair works to be completed.[30] 29.On 26 November 2021, members of the 3rd Management Committee of D decided to undertake repair works on the periphery of D71’s windows and, should there be any further worsening of the cement rendering at D71’s wall, to undertake waterproofing works on the external walls at D71.[31] (“the 26/11/21 Resolution”) 30.On 1 December 2021, P reiterated that D’s proposal made on 8 November 2021 was not acceptable and threatened to take legal proceedings against D.[32] 31.On 8 December 2021, D informed P in writing of the 26/11/21 Resolution and proposed that 2.5 days were needed for the repair works to be done on the periphery of D71’s windows.[33] By letter dated 10 December 2021, D explained to P that since D81’s owner refused D’s access to the external walls through D81 and BMC rejected scaffoldings to be erected from the roof top to D81 and D71, it was to be hoped that the 26/11/21 Resolution would be accepted.[34] 32.On 24 December 2021, P expressed its discontent over the 26/11/21 Resolution, but asked for a detailed plan on effecting repair works on the external walls with access through D71 to be provided.[35] 33.On 5 January 2022, D informed P that it had explored another option to effect repair works on the external walls outside D71 without the need of access to D71 and that the relevant repair works would commence in mid-February 2022.[36] 34.On 12 January 2022, members of the 3rd Management Committee of D approved through Whatsapp the 2nd quotation[37] provided by BMC on 11 January 2022.[38] (“the 2nd Quotation”) Under the 2nd Quotation, the repair works were to be carried out on the external walls of 7/F of Block D of the Building (with access via the staircase window) at a discounted price of HK$35,800.00. 35.On 17 January 2022, D by email asked BMC to provide for an exact date to commence the repair works.[39] On 27 January 2022, BMC by email provided D with a time schedule for erecting scaffoldings on 15 February 2022 and carrying out the repair works from 15 to 18 February 2022.[40] 36.On 24 January 2022, P issued the instant action against D. 37.Between 15 and 17 February 2022, BMC carried out the repair works.[41] 38.On 22 February 2022, P inquired about the scope of the repair works.[42] 39.On 3 March 2022, P took out the Summons. 40.After the issue of the Summons,
41.In support of the Summons, P exhibited an expert report compiled by a surveyor, Mr Lam Wai Keung Andrew (“Mr Lam”) of CBRE Limited dated 6 May 2022.[47] (“the 6/5/22 Report”) In essence, Mr Lam in the 6/5/22 Report opined that the water seepage at the wall of D71’s dining room had either reoccurred or the water seepage had not stopped, that the new waterproofing coating laid in February 2022 was ineffective mainly due to the nature of the material used and the unrepaired external wall rendering and that it was not a reliable method of preventing water from seeping into the external wall and could not solve the water seepage problem.[48] 42.So much for the background of this case. C. THE JUDGMENT 43.This action is not the first action commenced by P against D concerning the said water seepage. As aforementioned, P commenced the 2017 Action on 19 May 2017. P’s claim was then sounded in negligence and breach of the DMC.[49] D counterclaimed P in the 2017 Action, but its counterclaim therein is not relevant to my decision on the Summons. 44.Of relevance are the findings: -
45.In the 2017 Action, the relevant time-frame for HH Judge Au-Yeung to determine whether D had taken appropriate steps in remedying the situation after having been informed of the Subject Seepage Problem was from early 2015 when P first discovered the water seepage problem to 19 May 2017 when the 2017 Action was commenced. At para 37 of the Judgment[54], HH Judge Au-Yeung held the following: -
46.Hence, I agree with Mr Chok, counsel representing D, that the issue of whether D had taken reasonable/appropriate steps in remedying the said water seepage from early 2015 to 19 May 2017 is res judicata[55] and P has been precluded from raising this issue again in the instant action. 47.The same however cannot be said to be true when one considers whether D has been precluded from raising the issue as to whether water seepage problem was caused by defective external wall outside D71 from 19 May 2017 to 8 September 2021. Since the Judgment has chosen 19 May 2017 (ie the date of issue of the 2017 Action) as the “cutting-off” point on the basis of the agreement between the parties and dismissed the 2017 Action, it must be the case that the cause of the water seepage problem to D71 after 19 May 2017 would not be necessary or fundamental to the Judgment.[56] To demonstrate the lack of fundamentality of the aforesaid issue, the relevant question would be: Even if there is no finding on the aforesaid issue, does it follow that the Judgment cannot stand? In the present case, the answer to this relevant question is a resounding “No”. D. THE LAW 48.The legal principles applicable to an application for summary judgment are trite and beyond dispute. In Ju Yan Di Emperory Genesisy v Yan Wai Han [2015] 1 HKLRD 822, Cheung JA held at p 827, para 14 as follows: -
49.The parties have helpfully referred to the court various cases illustrating similar legal principles.[57] But I do not think I need to lengthen this Decision by citing those cases in extenso. 50.Where the plaintiff seeks equitable relief (e.g. a mandatory injunction), summary judgment may not be appropriate even if there is no defence as regards the plaintiff ’s cause of action, as the question of whether the Court should grant equitable relief may depend on fact- sensitive issues (e.g. acquiescence or hardship).[58] 51.Hence, where a plaintiff ’s claim is for a discretionary remedy, e.g. an injunction, even if the court is satisfied that there is no defence, it remains necessary for the plaintiff to satisfy the court that the discretionary remedy should be granted.[59] E. ANALYSIS E-1. P’s Arguments 52.In a nutshell, P contends the following: -
E-2. D’s Arguments 53.D however argues the following: -
E-3. My View 54.As I have said in the earlier part of this Decision, the issue of whether D had taken reasonable/appropriate steps in remedying the said water seepage problem at D71 from early 2015 to 19 May 2017 is res judicata. P cannot in this action raise this issue again and contend otherwise to support its claim in breach of duty under section 18(1) of BMO, negligence and nuisance. During oral submissions, it appeared that the parties were ad idem on this aspect. 55.The nub of this case is whether, for the period between 19 May 2017 and 24 January 2022,
56.It is well established that it is not for D to find out the source of the water seepage into D71 or to prove that the water seepage did not come from the defective external wall of the Building.[61] The doctrine of res ipsa loquitur does not apply in the present case.[62] The burden is on P to prove that the water seepage was originated from the defective external wall of the Building. I have also taken the view that the Judgment does not preclude D from raising the issue as to whether water seepage problem at D71 was caused by the defective external wall of the Building from 19 May 2017 to 8 September 2021. However, the tenor of D’s argument does not seem to have raised the cause of the water seepage as an issue. The only issue raised by D is that D had taken reasonable steps to remedy the defective external wall to stop the water seepage problem at D71. 57.Almost all the background facts mentioned in this Decision are indisputable and are evidenced by contemporaneous documents exhibited by the parties. Upon a reading of all the background facts and all the evidence filed by the parties, I am of the following view: -
F. DISPOSITION 58.In light of the aforesaid, I am driven to hold that D has demonstrated to my satisfaction that there is a fair or reasonable probability that D has a real or bona fide defence to the instant action. 59.Accordingly, I refuse to give summary judgment for P. But I am not satisfied that this is an appropriate case for me to dismiss the Summons outright. I hereby grant D unconditional leave to defend the instant action and pursuant to Ord.14, r.6 of the Rules of District Court (Cap.336H) (“RDC”), prescribe the following consequential directions for the future conduct thereof[63]: -
60.I further make a costs order nisi that the costs of and occasioned by the Summons be in the cause with certificate for one counsel. 61.Lastly, it remains for me to thank counsel for their helpful assistance.
Mr Andrew Mak leading Mr Abel Lam, instructed by Tsang, Chan & Woo Solicitors & Notaries, for the plaintiff Mr Brian Chok, instructed by Chiu, Szeto & Cheng Solicitors, for the defendant [1] The Plaintiff (“P”) has pleaded to rely on clause 7(ii)(a) of and clause 5 of the 4th Schedule to the Deed of Mutual Covenant registered by Memorial No 767905 (“the DMC”), and section 18(1) of the Building Management Ordinance (Cap 344) (“BMO”) as the bases giving rise to the duty of care owed by D to P. [2] See P’s Statement of Claim indorsed on the Writ of Summons issued on 24 January 2022 (“the Statement of Claim”) at pp 5-13 of Hearing Bundle A. [3] P itemized its damages claim as (a) damages for distress, discomfort and inconvenience since the date of the Judgment ie, 8 September 2021 to be assessed, (b) costs of repair and rectification of the water seepage in the sum of HK$12,050.00 already incurred and (c) cost of repair and rectification of the water seepage in the sum of HK$15,000,00 to be incurred. [4] See a succinct summary of the correspondence by HH Judge Au-Yeung from paras 18 to 35 of the Judgment at pp 79-88 of Hearing Bundle B(1). [5] At Hearing Bundles B(2) & (3), pp 622-716. [6] The test involved accurately and clearly marking out any bulged, loose, honey combed and spalling concrete. Any unpatent defects should also be marked out by tapping with a wooden mallet. Areas sounding ‘hollow’ which indicated voids or delamination should be noted. Carefully hack off the marked areas instructed by the Architect to a sound base. Remove all rust and scale from exposed reinforcement with wire brush and prepare concrete substrate as per tender drawing. The prepared concrete substrate and reinforcement shall be inspected by and to the satisfaction of the Architect prior to the application of any bond coat, primer or repair mortar. Smooth surfaces should be mechanically roughened by scabbing to form a good mechanical key. [7] By P’s letter to D dated 26 September 2019 (“the 26/9/19 Letter”), P denied receipt of the 1st Questionnaire, see Hearing Bundle B(3), at p 744, para 4. [8] At Hearing Bundle B(3), p 718. In the 26/9/19 Letter, P oddly denied receipt of the 2nd Questionnaire, see Hearing Bundle B(3), at p 744, para 4. [9] At Hearing Bundle B(3), p 720. This was the first letter P wrote to complain about the water seepage after the commencement of the 2017 Action. [10] At Hearing Bundle B(3), pp 728-741. [11] See in particular the letter by the management office for D to P’s solicitors dated 28 May 2019, at Hearing Bundle B(3), p 732. [12] See in particular the 26/9/19 Letter, at Hearing Bundle B(3), at pp 743-744. [13] At Hearing Bundle B(3), p 857. [14] At Hearing Bundle B(3), p 748. [15] At Hearing Bundle B(3), pp 748-774, 783-788. [16] At Hearing Bundle B(3), p 785-786. [17] At Hearing Bundle B(3), p 787-788. [18] See the 1st page of the Judgment at p 68 of Hearing Bundle B(1). [19] At Hearing Bundle B(3), p 789. [20] At Hearing Bundle B(3), p 789. [21] At Hearing Bundle B(3), p 792. [22] At Hearing Bundle B(3), p 793. [23] At Hearing Bundle B(3), p 794. [24] At Hearing Bundle B(4), p 924. [25] At Hearing Bundle B(4), pp 924-925. [26] At Hearing Bundle B(3), p 795. [27] At Hearing Bundle B(3), pp 796-797. [28] At Hearing Bundle B(4), p 930. [29] At Hearing Bundle B(4), p 941. [30] It was recorded in the minutes of the zoom meeting of the 3rd Management Committee held on 22 February 2022 that the reason why the management office of the Building had not tabled the 1st Quotation for the deliberation of the 3rd Management Committee was that the price quoted therein exceeded HK$100,000.00 and it was unable to seek more than one tender, see Hearing Bundle B(1) at p 146, para 6.3 and Hearing Bundle B(4), p 953, para 6.3. [31] At Hearing Bundle B(4), pp 943-945. [32] At Hearing Bundle B(3), p 799. [33] At Hearing Bundle B(3), p 798. [34] At Hearing Bundle B(3), p 800. [35] At Hearing Bundle B(3), pp 803-804. [36] At Hearing Bundle B(3), p 805. [37] At Hearing Bundle B(1), p 158 and Hearing Bundle B(4), p 935. [38] Due to the pandemic, the meeting of the Management Committee of D was held by Whatsapp and no physical meeting was held, see pp 926-928 of Hearing Bundle B(4). [39] At Hearing Bundle B(4), p 933. [40] At Hearing Bundle B(4), p 937. [41] At Hearing Bundle A, p 45, para 77 and Hearing Bundle B(4), pp 947-949. [42] At Hearing Bundle B(3), p 839. [43] At Hearing Bundle A, p 45, para 81 and Hearing Bundle B(3) at p 840-841. [44] At Hearing Bundle B(3), pp 842 & 844-851. [45] At Hearing Bundle B(1), pp 165-168 and Hearing Bundle B(3), pp 852-855. [46] At Hearing Bundle B(1), p 170, para 6.4 and Hearing Bundle B(4), p 967, para 6.4. [47] At Hearing Bundle B(1), pp 268-314. [48] At Hearing Bundle B(1), p 274 (para 5.1), p 275 (para 5.4), p 276 (para 6.2). [49] See para 1 of the Judgment at p 69 of Hearing Bundle B(1). [50] At Hearing Bundle B(1), p 71. [51] At Hearing Bundle B(1), p 90. [52] The Subject Seepage Problem was an abbreviated reference to the problem of water seeping into the left bottom corner of the wall at the dining room of D71, see para 1 of the Judgment at p 69 of Hearing Bundle B(1). [53] At Hearing Bundle B(1), p 93. [54] At Hearing Bundle B(1), pp 88-89. [55] In the form of issue estoppel. [56] The doctrine of res judicata in the form of issue estoppel only applies where, inter alia, the issue has been finally determined by a court of competent jurisdiction as a necessary step in reaching judgment in case between the same parties or their privies, see China North Industries Investment Ltd v Chum [2010] 5 HKLRD 1, at pp 18-19, para 47. [57] Yui Tat Nam Darney & Anor v Century Bridge Limited, DCCJ 2399/2016 (Unreported), 28 October 216, at pp 9-12, para 26; Heng Wah (Hong Kong) Decoration Co Ltd v Bonjour Holdings Ltd [2022] HKCFI 3487 at pp 4-5, para 15; John Joseph MC Gee v Nold (HK) Limited & Others [2022] HKCFI 3598 at pp 11-12, paras 21 & 22. [58] Hong Kong Civil Procedure 2023 (Vol 1), p 353, para 14/4/9B. [59] Hong Kong Civil Procedure 2023 (Vol 1), p 351, para 14/4/8. [60] Constructive knowledge means any knowledge which the defendant should have acquired with normal and reasonable diligence. [61] 張秀玲及吳炳漢 v 鄭禮莊, CACV 268/1998 (supra). [62] Hui Ling Ling v Sky Field Development Limited, CACV 122/2012 (Unreported), 22 March 2013, per Kwan JA (as she then was), at para 42. [63] Allowing for proportionality, reasonable expedition, fairness and costs control in light of the underlying objectives of Ord.1A, r.1 of RDC. [64] To-date, about 14 months have elapsed since D was served with the Statement of Claim, and D should have been in a position to put its case in its pleadings expeditiously. In my view, a period of 14 days is adequate for D to file and serve its Defence and Counterclaim (if any). | |||||||||||||||||||
Cases cited in this judgment